(B)BDR
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Path Construction Company, Inc. Low bidder | $239,261 | ||
| 2 | ERA-Valdivia Contractors, Inc. | $252,751 | +5.6% | |
| 3 | Civil Constructors, Inc. d/b/a/ Helm Civil | $299,501 | +25.2% | |
| 4 | MYS, Incorporated | $367,932 | +53.8% | |
| 5 | Sjostrom & Sons, Inc. | $397,467 | +66.1% | |
| 6 | Martin & Company Excavating | $487,189 | +103.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Path Constructi… | #2 ERA-Valdivia Co… | #3 Civil Construct… | #4 MYS, Incorporat… | #5 Sjostrom & Sons… | #6 Martin & Compan… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $8,540.00 | $9,000.00 | $8,540.00 | $25,000.00 | $50,000.00 | $15,000.00 | |
| 2 | Z0012102 | CONC BR DECK SCAR 3/8 | 2,353 | SQ YD | $20.00 | $17.60 | $22.50 | $26.86 | $40.77 | $60.00 | |
| 3 | Z0012193 | BR DK TH POLY OVL 3/8 | 2,353 | SQ YD | $52.00 | $59.95 | $74.50 | $80.00 | $75.00 | $108.00 | |
| 4 | Z0016200 | DECK SLAB REP (PART) | 101 | SQ YD | $455.00 | $464.32 | $400.00 | $650.00 | $480.08 | $285.00 | |
| 5 | 67100100 | MOBILIZATION | 1 | L SUM | $11,000.00 | $9,750.00 | $17,970.06 | $15,000.00 | $22,221.94 | $25,000.00 | |
| 6 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1,000.00 | $1,100.00 | $1,000.00 | $1,500.00 | $1,000.00 | $2,000.00 | |
| 7 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $100.00 | $100.00 | $100.00 | $500.00 | $100.00 | $200.00 | |
| 8 | 70107025 | CHANGEABLE MESSAGE SN | 90 | CAL DA | $20.00 | $22.00 | $20.00 | $66.00 | $20.00 | $200.00 | |
| 9 | 78001110 | PAINT PVT MK LINE 4 | 1,450 | FOOT | $1.00 | $1.00 | $1.00 | $2.00 | $1.00 | $2.00 |