(141-2HB-1)BDR
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Martin & Company Excavating Low bidder | $782,871 | ||
| 2 | Civil Constructors, Inc. d/b/a/ Helm Civil | $929,474 | +18.7% | |
| 3 | ERA-Valdivia Contractors, Inc. | $969,694 | +23.9% | |
| 4 | Sjostrom & Sons, Inc. | $1,026,445 | +31.1% | |
| 5 | Martam Construction Incorporated | $1,037,752 | +32.6% | |
| 6 | Alliance Contractors, Inc. | $1,294,840 | +65.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Martin & Compan… | #2 Civil Construct… | #3 ERA-Valdivia Co… | #4 Sjostrom & Sons… | #5 Martam Construc… | #6 Alliance Contra… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X5030250 | BR DECK GROOVING LONG | 1,048 | SQ YD | $9.25 | $12.10 | $15.00 | $11.30 | $9.94 | $10.35 | |
| 2 | X7030005 | TEMP PAVT MKING REMOV | 7,664 | SQ FT | $0.5500 | $0.6000 | $1.00 | $0.0100 | $0.6800 | $0.6000 | |
| 3 | Z0007101 | C&D LEAD PT CL RS N1 | 1 | L SUM | $12,000.00 | $9,000.00 | $15,000.00 | $10,000.00 | $35,281.42 | $8,100.00 | |
| 4 | Z0010501 | CLEAN & PT STL BR N1 | 1 | L SUM | $50,500.00 | $39,500.00 | $60,000.00 | $40,000.00 | $93,000.00 | $72,900.00 | |
| 5 | Z0012142 | BR DECK SCAR 2 1/4 | 1,368 | SQ YD | $54.00 | $83.80 | $60.00 | $85.00 | $41.71 | $40.15 | |
| 6 | Z0012164 | BR DK MIC C OVL 2 1/2 | 1,868 | SQ YD | $55.00 | $73.00 | $92.00 | $85.00 | $52.48 | $171.25 | |
| 7 | Z0012754 | STR REP CON DP = < 5 | 262 | SQ FT | $195.00 | $223.00 | $112.05 | $205.00 | $220.67 | $195.77 | |
| 8 | Z0021904 | SILICONE JT SEAL 1 | 136 | FOOT | $52.00 | $38.70 | $22.00 | $28.00 | $10.00 | $19.00 | |
| 9 | Z0029090 | DIAMOND GRIND BR SEC | 1,340 | SQ YD | $18.90 | $21.00 | $24.00 | $14.00 | $12.74 | $13.35 | |
| 10 | Z0041895 | POLYMER CONCRETE | 25 | CU FT | $1,250.00 | $262.00 | $1,278.75 | $555.00 | $650.00 | $255.00 | |
| 11 | 20200600 | EXC & GR EX SHOULDER | 25 | UNIT | $315.00 | $1,200.00 | $300.00 | $800.00 | $1,417.13 | $50.00 | |
| 12 | 44000500 | COMB CURB GUTTER REM | 1,326 | FOOT | $7.10 | $10.20 | $12.00 | $5.00 | $7.50 | $15.00 | |
| 13 | 44003100 | MEDIAN REMOVAL | 330 | SQ FT | $6.00 | $4.67 | $25.00 | $10.00 | $10.42 | $5.00 | |
| 14 | 44003510 | MEDIAN REMOVAL (PD) | 4,502 | SQ FT | $3.66 | $2.75 | $2.50 | $15.00 | $6.37 | $4.45 | |
| 15 | 44004250 | PAVED SHLD REMOVAL | 172 | SQ YD | $5.00 | $21.70 | $25.00 | $15.00 | $16.46 | $25.00 | |
| 16 | 48203033 | HMA SHOULDERS 9 | 2,507 | SQ YD | $35.13 | $44.35 | $48.50 | $46.00 | $49.99 | $55.55 | |
| 17 | 50102400 | CONC REM | 11 | CU YD | $1,700.00 | $4,554.00 | $2,200.00 | $4,217.00 | $1,300.00 | $7,575.00 | |
| 18 | 50104000 | BRIDGE RAIL REMOVAL | 526 | FOOT | $1.00 | $1.65 | $40.00 | $9.00 | $9.10 | $8.00 | |
| 19 | 50300255 | CONC SUP-STR | 37 | CU YD | $2,140.00 | $824.00 | $1,950.00 | $2,700.00 | $2,250.00 | $5,795.00 | |
| 20 | 50300300 | PROTECTIVE COAT | 1,869 | SQ YD | $3.10 | $3.80 | $2.00 | $1.00 | $2.11 | $1.75 | |
| 21 | 50800205 | REINF BARS, EPOXY CTD | 6,406 | POUND | $3.00 | $5.29 | $4.50 | $3.45 | $3.83 | $2.35 | |
| 22 | 50800515 | BAR SPLICERS | 32 | EACH | $75.00 | $10.05 | $60.00 | $60.00 | $101.48 | $80.00 | |
| 23 | 52000110 | PREF JT STRIP SEAL | 137 | FOOT | $255.00 | $217.00 | $250.60 | $234.00 | $210.00 | $210.00 | |
| 24 | 60608700 | COMB CC&G TM6.06 AEP | 1,326 | FOOT | $14.00 | $56.40 | $38.00 | $30.00 | $26.00 | $42.15 | |
| 25 | 60625600 | ISLAND PAVEMENT 6 | 37 | SQ YD | $240.00 | $98.20 | $215.00 | $185.00 | $110.00 | $185.00 | |
| 26 | 67000400 | ENGR FIELD OFFICE A | 2 | CAL MO | $3,200.00 | $3,790.00 | $2,000.00 | $3,000.00 | $4,500.00 | $500.00 | |
| 27 | 67100100 | MOBILIZATION | 1 | L SUM | $42,000.00 | $55,768.00 | $37,000.00 | $58,100.00 | $62,265.13 | $77,000.00 | |
| 28 | 70100200 | TRAF CONT-PROT 701331 | 1 | EACH | $12,500.00 | $16,000.00 | $15,000.00 | $22,000.00 | $105,900.00 | $34,675.00 | |
| 29 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $3,000.00 | $1,000.00 | $10,368.00 | $1,000.00 | $11,497.46 | $1,000.00 | |
| 30 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $3,500.00 | $1,000.00 | $5,184.00 | $1,000.00 | $11,497.46 | $1,000.00 | |
| 31 | 70103815 | TR CONT SURVEILLANCE | 14 | CAL DA | $400.00 | $550.00 | $500.00 | $700.00 | $619.96 | $550.00 | |
| 32 | 70307120 | TEMP PVT MK L4 T4 TAPE | 11,176 | FOOT | $1.60 | $1.15 | $1.50 | $1.50 | $1.30 | $1.15 | |
| 33 | 78000100 | THPL PVT MK LTR & SYM | 94 | SQ FT | $7.00 | $6.00 | $6.75 | $6.00 | $11.27 | $6.20 | |
| 34 | 78000200 | THPL PVT MK LINE 4 | 6,482 | FOOT | $0.9300 | $0.8500 | $1.00 | $0.9000 | $1.75 | $0.9000 | |
| 35 | 78300202 | PAVMT MRKG REM WTR BL | 1,459 | SQ FT | $3.20 | $2.10 | $3.50 | $5.00 | $2.37 | $2.10 |