HC BRIDGE REPAIR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Martin & Company Excavating Low bidder | $1,029,566 | ||
| 2 | Civil Constructors, Inc. d/b/a/ Helm Civil | $1,193,271 | +15.9% | |
| 3 | Brandt Construction Co. | $1,704,955 | +65.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Martin & Compan… | #2 Civil Construct… | #3 Brandt Construc… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0326806 | WASHOUT BASIN | 1 | L SUM | $500.00 | $1,700.00 | $3,250.00 | |
| 2 | X5030301 | CONC WEARING SURF VD | 372 | SQ YD | $215.00 | $160.00 | $350.00 | |
| 3 | X6310187 | TRAF BAR TERM T6 MOD | 1 | EACH | $9,000.00 | $8,116.00 | $9,150.00 | |
| 4 | X6640300 | CH LK FENCE REMOV | 16 | FOOT | $12.00 | $9.80 | $65.00 | |
| 5 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $10,500.00 | $9,100.00 | $12,000.00 | |
| 6 | Z0001900 | ASB BEARING PAD REMOV | 44 | EACH | $50.00 | $80.00 | $175.00 | |
| 7 | Z0012754 | STR REP CON DP = < 5 | 17 | SQ FT | $240.00 | $322.00 | $900.00 | |
| 8 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $3,500.00 | $7,000.00 | $16,000.00 | |
| 9 | 20200100 | EARTH EXCAVATION | 437 | CU YD | $24.00 | $60.00 | $45.00 | |
| 10 | 20700220 | POROUS GRAN EMBANK | 10 | CU YD | $42.00 | $85.00 | $260.00 | |
| 11 | 20800150 | TRENCH BACKFILL | 18 | CU YD | $42.00 | $30.00 | $75.00 | |
| 12 | 21101615 | TOPSOIL F & P 4 | 876 | SQ YD | $5.00 | $11.00 | $17.00 | |
| 13 | 25000115 | SEEDING CL 1B | 0.2 | ACRE | $11,000.00 | $10,000.00 | $11,250.00 | |
| 14 | 25000400 | NITROGEN FERT NUTR | 20 | POUND | $2.00 | $1.00 | $1.15 | |
| 15 | 25000500 | PHOSPHORUS FERT NUTR | 20 | POUND | $2.00 | $1.00 | $1.15 | |
| 16 | 25000600 | POTASSIUM FERT NUTR | 20 | POUND | $2.00 | $1.00 | $1.15 | |
| 17 | 25100105 | MULCH METHOD 1 | 0.2 | ACRE | $11,000.00 | $10,000.00 | $11,250.00 | |
| 18 | 28000250 | TEMP EROS CONTR SEED | 11 | POUND | $5.00 | $5.00 | $5.50 | |
| 19 | 28000400 | PERIMETER EROS BAR | 638 | FOOT | $5.25 | $4.00 | $4.50 | |
| 20 | 28000510 | INLET FILTERS | 4 | EACH | $125.00 | $250.00 | $375.00 | |
| 21 | 28100705 | STONE DUMP RIP CL A3 | 18 | SQ YD | $65.00 | $72.00 | $98.00 | |
| 22 | 28200200 | FILTER FABRIC | 24 | SQ YD | $5.00 | $5.00 | $40.00 | |
| 23 | 31102600 | SUB GRAN MAT C 9 | 150 | SQ YD | $14.00 | $28.00 | $48.00 | |
| 24 | 35101100 | AGG BASE CSE A 12 | 730 | SQ YD | $19.00 | $22.00 | $40.00 | |
| 25 | 40200500 | AGG SURF CSE A 6 | 180 | SQ YD | $10.00 | $17.00 | $25.00 | |
| 26 | 40600275 | BIT MATLS PR CT | 1,643 | POUND | $1.00 | $1.00 | $1.00 | |
| 27 | 40600290 | BIT MATLS TACK CT | 730 | POUND | $1.00 | $0.6000 | $1.00 | |
| 28 | 40600982 | HMA SURF REM BUTT JT | 31 | SQ YD | $25.00 | $15.00 | $118.00 | |
| 29 | 40602978 | HMA BC IL-9.5 N50 | 57 | TON | $170.00 | $120.00 | $235.00 | |
| 30 | 40604000 | HMA SC IL-9.5FG C N50 | 57 | TON | $180.00 | $120.00 | $300.00 | |
| 31 | 42400200 | PC CONC SIDEWALK 5 | 1,363 | SQ FT | $11.00 | $10.00 | $18.00 | |
| 32 | 44000600 | SIDEWALK REM | 1,376 | SQ FT | $2.00 | $2.00 | $2.00 | |
| 33 | 48203021 | HMA SHOULDERS 6 | 150 | SQ YD | $66.50 | $60.00 | $135.00 | |
| 34 | 50101500 | REM EXIST SUP-STR | 1 | EACH | $60,000.00 | $120,000.00 | $200,000.00 | |
| 35 | 50102400 | CONC REM | 11.1 | CU YD | $450.00 | $2,885.00 | $5,400.00 | |
| 36 | 50200100 | STRUCTURE EXCAVATION | 20.4 | CU YD | $60.00 | $70.00 | $100.00 | |
| 37 | 50300225 | CONC STRUCT | 33.7 | CU YD | $1,250.00 | $1,600.00 | $3,300.00 | |
| 38 | 50300255 | CONC SUP-STR | 26.3 | CU YD | $1,200.00 | $1,700.00 | $3,200.00 | |
| 39 | 50400405 | P P CONC DK BM 21 DP | 1,444 | SQ FT | $109.00 | $114.00 | $125.00 | |
| 40 | 50400505 | P P CONC DK BM 27 DP | 1,898 | SQ FT | $112.00 | $118.00 | $127.00 | |
| 41 | 50800205 | REINF BARS, EPOXY CTD | 14,230 | POUND | $2.90 | $3.10 | $3.50 | |
| 42 | 50901720 | BICYCLE RAILING | 160 | FOOT | $350.00 | $343.00 | $380.00 | |
| 43 | 50901750 | PARAPET RAILING | 100 | FOOT | $140.00 | $138.00 | $145.00 | |
| 44 | 50901760 | PIPE HANDRAIL | 37 | FOOT | $280.00 | $261.00 | $300.00 | |
| 45 | 51100100 | SLOPE WALL 4 | 70 | SQ YD | $120.00 | $530.00 | $685.00 | |
| 46 | 51500100 | NAME PLATES | 1 | EACH | $1,350.00 | $980.00 | $1,375.00 | |
| 47 | 52000110 | PREF JT STRIP SEAL | 66 | FOOT | $400.00 | $258.00 | $400.00 | |
| 48 | 54262715 | METAL FL END SEC 15" | 1 | EACH | $325.00 | $1,100.00 | $1,050.00 | |
| 49 | 550A0050 | STORM SEW CL A 1 12 | 48 | FOOT | $90.00 | $97.00 | $138.00 | |
| 50 | 550B0360 | STORM SEW CL B 2 15 | 40 | FOOT | $60.00 | $99.00 | $238.00 | |
| 51 | 60235705 | INLETS TA T3V F&G | 2 | EACH | $2,800.00 | $2,900.00 | $5,000.00 | |
| 52 | 60240215 | INLETS TB T1F CL | 1 | EACH | $3,900.00 | $2,900.00 | $7,300.00 | |
| 53 | 60240222 | INLETS TB T3V F&G | 2 | EACH | $4,100.00 | $3,100.00 | $5,750.00 | |
| 54 | 60605000 | COMB CC&G TY B-6.24 | 82 | FOOT | $60.00 | $69.00 | $85.00 | |
| 55 | 63000001 | SPBGR TY A 6FT POSTS | 90 | FOOT | $39.00 | $34.28 | $38.00 | |
| 56 | 63000003 | SPBGR TY A 9FT POSTS | 80 | FOOT | $47.00 | $43.16 | $48.00 | |
| 57 | 63000035 | BCK SD PROT OF GRDRL | 235 | FOOT | $25.00 | $22.11 | $25.00 | |
| 58 | 63100070 | TRAF BAR TERM T5 | 2 | EACH | $1,200.00 | $1,131.00 | $1,275.00 | |
| 59 | 63100085 | TRAF BAR TERM T6 | 1 | EACH | $4,600.00 | $4,417.00 | $4,975.00 | |
| 60 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,500.00 | $3,366.00 | $3,790.00 | |
| 61 | 63200310 | GUARDRAIL REMOV | 467 | FOOT | $6.26 | $6.26 | $7.00 | |
| 62 | 67000500 | ENGR FIELD OFFICE B | 6 | CAL MO | $3,200.00 | $3,300.00 | $4,500.00 | |
| 63 | 67100100 | MOBILIZATION | 1 | L SUM | $58,000.00 | $71,596.28 | $100,000.00 | |
| 64 | 78005110 | EPOXY PVT MK LINE 4 | 420 | FOOT | $10.00 | $9.15 | $30.00 | |
| 65 | 78008210 | POLYUREA PM T1 LN 4 | 903 | FOOT | $10.50 | $9.85 | $14.00 |