101RS-2
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Civil Constructors, Inc. d/b/a/ Helm Civil Low bidder | $1,497,763 | ||
| 2 | Martin & Company Excavating | $1,671,878 | +11.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Civil Construct… | #2 Martin & Compan… |
|---|---|---|---|---|---|---|---|
| 1 | X4200001 | CIR-FDR EMULS ASPHALT | 128,143 | GALLON | $1.80 | $2.45 | |
| 2 | X4200002 | CIP RECYCLING, 4.0" | 73,225 | SQ YD | $2.76 | $3.47 | |
| 3 | X4400196 | HMA SURF REM SPL | 1,408 | SQ YD | $9.33 | $32.00 | |
| 4 | X7830070 | GRV RCSD PVT MRKG 5 | 79,588 | FOOT | $0.3500 | $0.2700 | |
| 5 | X7830076 | GRV RCSD PVT MRKG 9 | 286 | FOOT | $0.5000 | $0.5300 | |
| 6 | X7830078 | GRV RCSD PVT MRKG 13 | 240 | FOOT | $1.00 | $0.8500 | |
| 7 | X7830090 | GRV RCSD PVT MRKG 25 | 80 | FOOT | $2.00 | $1.75 | |
| 8 | Z0004542 | HMA REMOVAL SPL | 21 | SQ YD | $92.00 | $50.00 | |
| 9 | Z0055100 | RUMBLE RESURF | 102 | SQ YD | $75.00 | $25.00 | |
| 10 | 40600290 | BIT MATLS TACK CT | 21,001 | POUND | $0.5000 | $0.5000 | |
| 11 | 40600990 | TEMPORARY RAMP | 3,841 | SQ YD | $8.00 | $5.60 | |
| 12 | 40604050 | HMA SC IL-9.5 C N50 | 9,376 | TON | $57.00 | $55.00 | |
| 13 | 40800050 | INCIDENTAL HMA SURF | 345 | TON | $98.00 | $78.00 | |
| 14 | 44000157 | HMA SURF REM 2 | 3,231 | SQ YD | $2.00 | $5.44 | |
| 15 | 44000160 | HMA SURF REM 2 3/4 | 73,225 | SQ YD | $2.20 | $2.27 | |
| 16 | 48102100 | AGG WEDGE SHLD TYPE B | 4,330 | TON | $15.00 | $21.00 | |
| 17 | 63301210 | REM RE-E SPBGR TY A | 775 | FOOT | $20.77 | $23.00 | |
| 18 | 66700305 | PERM SURV MKRS T2 | 2 | EACH | $1,750.00 | $1,800.00 | |
| 19 | 67000400 | ENGR FIELD OFFICE A | 4 | CAL MO | $1,750.00 | $2,500.00 | |
| 20 | 67100100 | MOBILIZATION | 1 | L SUM | $80,000.00 | $90,000.00 | |
| 21 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $1,925.00 | $2,000.00 | |
| 22 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $1,925.00 | $2,000.00 | |
| 23 | 70300100 | SHORT TERM PAVT MKING | 7,700 | FOOT | $0.8000 | $0.5000 | |
| 24 | 70300150 | SHRT TRM PAVT MK REM | 909 | SQ FT | $5.20 | $3.00 | |
| 25 | 78000200 | THPL PVT MK LINE 4 | 79,588 | FOOT | $0.5500 | $0.5700 | |
| 26 | 78000500 | THPL PVT MK LINE 8 | 286 | FOOT | $1.25 | $1.20 | |
| 27 | 78000600 | THPL PVT MK LINE 12 | 240 | FOOT | $2.00 | $1.80 | |
| 28 | 78000650 | THPL PVT MK LINE 24 | 80 | FOOT | $4.00 | $3.50 | |
| 29 | 78009004 | MOD URETH PM LINE 4 | 1,452 | FOOT | $3.75 | $3.60 | |
| 30 | 78200005 | GRDRAIL REF TYPE A | 20 | EACH | $10.00 | $11.00 |