19-00187-00-BR
- Let date
- Friday, January 21, 2022
- Contract
- 85717 · job page
- District
- District 2
- County
- Stephenson
- Highway
- Limits
- Replace the existing box culvert over Cedar Creek, 2.5 miles north of Dakota, with a triple cell box culvert.
Bidders 7
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | M & M Concrete, Inc. Low bidder | $534,166 | ||
| 2 | Sjostrom & Sons, Inc. | $556,072 | +4.1% | |
| 3 | Martin & Company Excavating | $557,046 | +4.3% | |
| 4 | Stenstrom Excavation & Blacktop, Inc. | $708,655 | +32.7% | |
| 5 | Civil Constructors, Inc. d/b/a/ Helm Civil | $718,757 | +34.6% | |
| 6 | O'Brien Civil Works, Inc. | $887,052 | +66.1% | |
| 7 | Phoenix Corporation of the Quad Cities | $1,128,928 | +111.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 M & M Concrete,… | #2 Sjostrom & Sons… | #3 Martin & Compan… | #4 Stenstrom Excav… | #5 Civil Construct… | #6 O'Brien Civil W… | #7 Phoenix Corpora… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0900064 | MEMBR WTRPR SYS B STR | 244 | SQ YD | $39.00 | $45.00 | $44.00 | $46.55 | $40.00 | $50.00 | $45.00 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $1,900.00 | $3,000.00 | $2,200.00 | $2,010.00 | $1,900.00 | $2,200.00 | $3,500.00 | |
| 3 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $2,500.00 | $3,500.00 | $2,500.00 | $2,645.00 | $4,000.00 | $3,000.00 | $3,500.00 | |
| 4 | 20200100 | EARTH EXCAVATION | 224 | CU YD | $31.50 | $116.41 | $44.00 | $52.75 | $31.00 | $36.00 | $35.00 | |
| 5 | 20700220 | POROUS GRAN EMBANK | 259 | CU YD | $50.00 | $62.13 | $48.00 | $68.40 | $48.00 | $41.00 | $80.00 | |
| 6 | 25000200 | SEEDING CL 2 | 0.2 | ACRE | $8,300.00 | $5,000.00 | $6,000.00 | $9,210.00 | $5,000.00 | $5,000.00 | $9,500.00 | |
| 7 | 25000400 | NITROGEN FERT NUTR | 18 | POUND | $5.00 | $1.00 | $2.00 | $3.20 | $1.00 | $5.00 | $7.00 | |
| 8 | 25000500 | PHOSPHORUS FERT NUTR | 18 | POUND | $5.00 | $1.00 | $2.00 | $3.20 | $1.00 | $5.00 | $7.00 | |
| 9 | 25000600 | POTASSIUM FERT NUTR | 18 | POUND | $5.00 | $1.00 | $2.00 | $3.20 | $1.00 | $5.00 | $7.00 | |
| 10 | 25100630 | EROSION CONTR BLANKET | 385 | SQ YD | $2.50 | $7.00 | $8.00 | $3.20 | $7.00 | $2.00 | $5.00 | |
| 11 | 28000305 | TEMP DITCH CHECKS | 90 | FOOT | $7.00 | $15.00 | $20.00 | $16.40 | $15.00 | $15.00 | $10.00 | |
| 12 | 28000400 | PERIMETER EROS BAR | 512 | FOOT | $3.00 | $3.00 | $3.50 | $3.90 | $3.00 | $6.00 | $4.50 | |
| 13 | 28100107 | STONE RIPRAP CL A4 | 91 | SQ YD | $50.05 | $94.99 | $66.00 | $98.00 | $60.00 | $85.00 | $65.00 | |
| 14 | 28200200 | FILTER FABRIC | 91 | SQ YD | $9.00 | $10.88 | $5.00 | $4.55 | $5.00 | $3.50 | $2.50 | |
| 15 | 35101400 | AGG BASE CSE B | 324 | TON | $24.00 | $35.60 | $26.00 | $20.60 | $28.00 | $26.00 | $38.00 | |
| 16 | 40600275 | BIT MATLS PR CT | 2,012 | POUND | $0.0100 | $0.0100 | $0.5000 | $0.5300 | $0.0100 | $0.8500 | $0.0100 | |
| 17 | 40600290 | BIT MATLS TACK CT | 110 | POUND | $0.0100 | $0.0100 | $1.00 | $0.8000 | $0.0100 | $5.50 | $0.0100 | |
| 18 | 40603080 | HMA BC IL-19.0 N50 | 111 | TON | $98.00 | $98.00 | $110.00 | $125.00 | $100.00 | $150.00 | $107.00 | |
| 19 | 40604050 | HMA SC IL-9.5 C N50 | 83 | TON | $97.00 | $97.00 | $110.00 | $126.00 | $97.00 | $165.00 | $106.00 | |
| 20 | 48101200 | AGGREGATE SHLDS B | 62 | TON | $30.00 | $37.49 | $30.00 | $48.00 | $30.00 | $50.00 | $35.00 | |
| 21 | 50100100 | REM EXIST STRUCT | 1 | EACH | $24,860.00 | $28,373.18 | $24,000.00 | $9,785.00 | $85,000.00 | $26,000.00 | $40,000.00 | |
| 22 | 50200100 | STRUCTURE EXCAVATION | 200 | CU YD | $39.00 | $63.24 | $45.00 | $153.50 | $38.00 | $75.00 | $30.00 | |
| 23 | 50800105 | REINFORCEMENT BARS | 79,510 | POUND | $1.60 | $0.8000 | $1.66 | $0.8000 | $1.96 | $1.90 | $1.90 | |
| 24 | 50800205 | REINF BARS, EPOXY CTD | 1,110 | POUND | $2.15 | $3.21 | $1.90 | $0.9000 | $2.69 | $2.00 | $2.10 | |
| 25 | 51500100 | NAME PLATES | 1 | EACH | $675.00 | $619.90 | $750.00 | $610.00 | $450.00 | $1,000.00 | $800.00 | |
| 26 | 54003000 | CONC BOX CUL | 322 | CU YD | $635.00 | $801.44 | $700.00 | $1,347.00 | $930.00 | $1,550.00 | $1,970.00 | |
| 27 | 63000001 | SPBGR TY A 6FT POSTS | 162.5 | FOOT | $36.00 | $44.20 | $50.00 | $46.80 | $44.20 | $40.00 | $42.00 | |
| 28 | 63000054 | WPGR ATT CLVRT CASE 5 | 124 | FOOT | $322.00 | $182.65 | $190.00 | $193.30 | $182.65 | $355.00 | $360.00 | |
| 29 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,100.00 | $3,540.00 | $3,700.00 | $3,745.00 | $3,540.00 | $3,400.00 | $3,500.00 | |
| 30 | 63200310 | GUARDRAIL REMOV | 450 | FOOT | $8.00 | $5.50 | $5.00 | $5.85 | $5.50 | $8.00 | $6.00 | |
| 31 | 67100100 | MOBILIZATION | 1 | L SUM | $31,900.00 | $33,364.31 | $30,000.00 | $23,150.00 | $43,125.43 | $30,000.00 | $130,775.28 | |
| 32 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $35.00 | $160.00 | $40.00 | $37.00 | $35.00 | $40.00 | $45.00 |