19-00630-00-BR
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Civil Constructors, Inc. d/b/a/ Helm Civil Low bidder | $1,393,880 | ||
| 2 | Sjostrom & Sons, Inc. | $1,433,597 | +2.8% | |
| 3 | Martin & Company Excavating | $1,440,489 | +3.3% | |
| 4 | Alliance Contractors, Inc. | $1,560,562 | +12.0% | |
| 5 | Copenhaver Construction, Inc. | $1,766,449 | +26.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Civil Construct… | #2 Sjostrom & Sons… | #3 Martin & Compan… | #4 Alliance Contra… | #5 Copenhaver Cons… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0322463 | CONN TO EXIST SEWER | 1 | EACH | $1,064.59 | $1,500.00 | $880.00 | $1,750.00 | $1,200.00 | |
| 2 | X0326806 | WASHOUT BASIN | 1 | L SUM | $478.00 | $1,128.74 | $790.00 | $750.00 | $900.00 | |
| 3 | X2130010 | EXPLOR TRENCH SPL | 100 | FOOT | $5.00 | $1.00 | $5.00 | $1.00 | $9.00 | |
| 4 | X4022000 | TEMP ACCESS- COM ENT | 5 | EACH | $1,198.22 | $950.00 | $400.00 | $315.00 | $750.00 | |
| 5 | X6024242 | INLETS SPL N1 | 4 | EACH | $4,395.48 | $3,500.00 | $4,230.00 | $7,500.00 | $5,600.00 | |
| 6 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $7,500.00 | $7,500.00 | $9,000.00 | $12,300.00 | $112,000.00 | |
| 7 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $7,200.00 | $6,500.00 | $4,800.00 | $4,400.00 | $19,000.00 | |
| 8 | Z0030850 | TEMP INFO SIGNING | 52 | SQ FT | $28.00 | $28.00 | $32.00 | $14.00 | $28.00 | |
| 9 | Z0046304 | P UNDR FOR STRUCT 4 | 204 | FOOT | $16.65 | $15.18 | $17.10 | $25.00 | $31.00 | |
| 10 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $2,900.00 | $5,500.00 | $10,000.00 | $1,000.00 | $12,000.00 | |
| 11 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 12 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | |
| 13 | 20200100 | EARTH EXCAVATION | 640 | CU YD | $32.00 | $36.00 | $21.30 | $10.00 | $28.00 | |
| 14 | 20201200 | REM & DISP UNS MATL | 534 | CU YD | $20.55 | $26.00 | $20.00 | $10.00 | $25.00 | |
| 15 | 21101615 | TOPSOIL F & P 4 | 105 | SQ YD | $11.00 | $16.26 | $14.00 | $11.00 | $17.00 | |
| 16 | 25000210 | SEEDING CL 2A | 0.1 | ACRE | $8,500.00 | $4,423.70 | $12,000.00 | $8,500.00 | $10,000.00 | |
| 17 | 28000510 | INLET FILTERS | 4 | EACH | $190.00 | $36.01 | $190.00 | $190.00 | $120.00 | |
| 18 | 28100107 | STONE RIPRAP CL A4 | 340 | SQ YD | $52.00 | $70.00 | $51.00 | $60.00 | $77.00 | |
| 19 | 28200200 | FILTER FABRIC | 355 | SQ YD | $4.00 | $5.00 | $3.50 | $1.00 | $2.00 | |
| 20 | 30300112 | AGG SUBGRADE IMPR 12 | 1,370 | SQ YD | $6.00 | $11.50 | $7.93 | $12.00 | $9.00 | |
| 21 | 31101400 | SUB GRAN MAT B 6 | 2,185 | SQ YD | $2.75 | $5.75 | $3.44 | $0.0100 | $5.00 | |
| 22 | 35101800 | AGG BASE CSE B 6 | 1,370 | SQ YD | $2.75 | $6.75 | $3.42 | $6.00 | $5.00 | |
| 23 | 40600275 | BIT MATLS PR CT | 4,380 | POUND | $0.0100 | $0.0100 | $0.0500 | $0.0100 | $1.00 | |
| 24 | 40600290 | BIT MATLS TACK CT | 880 | POUND | $0.0100 | $0.0100 | $0.5000 | $0.0100 | $1.00 | |
| 25 | 40701841 | HMA PAVT FD 8 | 1,370 | SQ YD | $37.00 | $37.00 | $41.23 | $37.00 | $39.50 | |
| 26 | 42000070 | PVT CON HMA BR APP SL | 118 | SQ YD | $59.00 | $59.00 | $97.46 | $59.00 | $111.00 | |
| 27 | 42001300 | PROTECTIVE COAT | 970 | SQ YD | $1.80 | $2.26 | $2.40 | $0.0100 | $9.00 | |
| 28 | 42300400 | PCC DRIVEWAY PAVT 8 | 738 | SQ YD | $67.70 | $53.38 | $78.00 | $82.75 | $75.00 | |
| 29 | 42400200 | PC CONC SIDEWALK 5 | 660 | SQ FT | $7.05 | $6.33 | $9.05 | $5.65 | $11.00 | |
| 30 | 44000100 | PAVEMENT REM | 2,001 | SQ YD | $8.00 | $7.00 | $7.35 | $15.00 | $11.00 | |
| 31 | 44000200 | DRIVE PAVEMENT REM | 533 | SQ YD | $10.00 | $6.00 | $9.10 | $15.00 | $14.00 | |
| 32 | 44000500 | COMB CURB GUTTER REM | 582 | FOOT | $7.00 | $3.00 | $5.30 | $10.00 | $8.00 | |
| 33 | 44000600 | SIDEWALK REM | 2,608 | SQ FT | $3.00 | $0.5000 | $3.00 | $2.00 | $4.00 | |
| 34 | 50100100 | REM EXIST STRUCT | 1 | EACH | $60,000.00 | $41,520.00 | $35,100.00 | $89,035.00 | $60,000.00 | |
| 35 | 50200100 | STRUCTURE EXCAVATION | 370 | CU YD | $37.00 | $48.00 | $42.00 | $10.00 | $39.00 | |
| 36 | 50300225 | CONC STRUCT | 88.3 | CU YD | $600.00 | $694.00 | $630.00 | $830.00 | $1,000.00 | |
| 37 | 50300255 | CONC SUP-STR | 218.5 | CU YD | $950.00 | $1,158.31 | $842.90 | $1,310.00 | $1,050.00 | |
| 38 | 50300260 | BR DECK GROOVING | 646 | SQ YD | $8.32 | $10.09 | $14.01 | $10.65 | $12.00 | |
| 39 | 50301350 | CONC SUPSTR APP SLAB | 115.8 | CU YD | $340.00 | $386.91 | $485.00 | $270.00 | $550.00 | |
| 40 | 50401325 | F&E PP CON BEAM IL45N | 553.5 | FOOT | $520.00 | $418.96 | $493.00 | $552.00 | $455.00 | |
| 41 | 50800205 | REINF BARS, EPOXY CTD | 107,070 | POUND | $1.20 | $1.66 | $1.67 | $1.37 | $2.00 | |
| 42 | 50900105 | ALUM RAILING TY L | 170 | FOOT | $131.33 | $126.80 | $166.80 | $126.80 | $194.00 | |
| 43 | 51200959 | FUR M S PILE 14X0.312 | 562 | FOOT | $85.00 | $105.45 | $85.00 | $105.00 | $95.00 | |
| 44 | 51202305 | DRIVING PILES | 562 | FOOT | $0.0100 | $0.0100 | $1.00 | $1.00 | $1.00 | |
| 45 | 51203200 | TEST PILE MET SHELLS | 1 | EACH | $7,000.00 | $11,424.49 | $8,075.00 | $12,500.00 | $9,000.00 | |
| 46 | 51204650 | PILE SHOES | 12 | EACH | $330.00 | $275.00 | $350.00 | $300.00 | $220.00 | |
| 47 | 51500100 | NAME PLATES | 1 | EACH | $450.00 | $542.43 | $650.00 | $750.00 | $1,000.00 | |
| 48 | 54213660 | PRC FLAR END SEC 15 | 1 | EACH | $811.56 | $950.00 | $750.00 | $1,035.00 | $1,100.00 | |
| 49 | 54213666 | PRC FLAR END SEC 21 | 1 | EACH | $907.06 | $1,100.00 | $950.00 | $1,315.00 | $1,400.00 | |
| 50 | 54248510 | CONCRETE COLLAR | 0.7 | CU YD | $2,100.00 | $1,500.00 | $1,650.00 | $1,000.00 | $2,600.00 | |
| 51 | 550A0340 | STORM SEW CL A 2 12 | 151 | FOOT | $65.77 | $70.00 | $63.00 | $120.00 | $74.00 | |
| 52 | 550A0360 | STORM SEW CL A 2 15 | 58 | FOOT | $93.34 | $75.00 | $81.00 | $124.00 | $100.00 | |
| 53 | 550A0400 | STORM SEW CL A 2 21 | 34 | FOOT | $149.44 | $85.00 | $133.00 | $134.00 | $152.00 | |
| 54 | 55100500 | STORM SEWER REM 12 | 85 | FOOT | $41.31 | $10.00 | $25.00 | $20.00 | $44.00 | |
| 55 | 55100700 | STORM SEWER REM 15 | 33 | FOOT | $48.22 | $10.00 | $26.00 | $20.00 | $49.00 | |
| 56 | 55100900 | STORM SEWER REM 18 | 16 | FOOT | $67.02 | $10.00 | $35.00 | $25.00 | $69.00 | |
| 57 | 55101100 | STORM SEWER REM 21 | 15 | FOOT | $72.47 | $10.00 | $50.00 | $25.00 | $90.00 | |
| 58 | 56500600 | DOM WAT SER BOX ADJ | 2 | EACH | $354.42 | $750.00 | $400.00 | $75.00 | $500.00 | |
| 59 | 58600101 | GRANULAR BACKFILL STR | 145 | CU YD | $45.00 | $30.00 | $46.00 | $35.00 | $40.00 | |
| 60 | 59100100 | GEOCOMPOSITE WALL DR | 80 | SQ YD | $22.00 | $31.21 | $23.00 | $35.00 | $36.00 | |
| 61 | 60108204 | PIPE UNDERDR T 2 4 | 42 | FOOT | $41.39 | $57.48 | $51.00 | $25.00 | $44.00 | |
| 62 | 60200305 | CB TA 4 DIA T3F&G | 1 | EACH | $3,427.06 | $3,000.00 | $3,000.00 | $2,750.00 | $3,900.00 | |
| 63 | 60265700 | VV ADJUST | 5 | EACH | $1,149.09 | $1,250.00 | $1,150.00 | $295.00 | $1,300.00 | |
| 64 | 60266600 | VALVE BOX ADJ | 1 | EACH | $397.70 | $750.00 | $450.00 | $125.00 | $450.00 | |
| 65 | 60500040 | REMOV MANHOLES | 4 | EACH | $245.43 | $500.00 | $300.00 | $200.00 | $400.00 | |
| 66 | 60604400 | COMB CC&G TB6.18 | 678 | FOOT | $30.95 | $32.38 | $35.95 | $30.55 | $34.00 | |
| 67 | 63000001 | SPBGR TY A 6FT POSTS | 53 | FOOT | $62.10 | $62.10 | $75.00 | $62.10 | $70.00 | |
| 68 | 66900200 | NON SPL WASTE DISPOSL | 1,010 | CU YD | $30.00 | $18.90 | $43.65 | $26.50 | $37.00 | |
| 69 | 66900530 | SOIL DISPOSAL ANALY | 2 | EACH | $500.00 | $1,050.00 | $1,250.00 | $1,050.00 | $950.00 | |
| 70 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,199.70 | $2,200.00 | $2,500.00 | $2,200.00 | $2,700.00 | |
| 71 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $1,799.75 | $1,800.00 | $2,000.00 | $1,800.00 | $2,350.00 | |
| 72 | 66901006 | REG SUB MON | 15 | CAL DA | $619.90 | $620.00 | $820.00 | $62.00 | $850.00 | |
| 73 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $2,840.00 | $1,868.17 | $1,500.00 | $500.00 | $500.00 | |
| 74 | 67100100 | MOBILIZATION | 1 | L SUM | $83,632.77 | $86,013.45 | $80,000.00 | $93,000.00 | $100,000.00 | |
| 75 | 70107025 | CHANGEABLE MESSAGE SN | 200 | CAL DA | $35.00 | $35.00 | $40.00 | $25.00 | $29.00 | |
| 76 | 78000200 | THPL PVT MK LINE 4 | 9,800 | FOOT | $0.6000 | $0.6500 | $0.7000 | $0.6000 | $1.10 |