FAI 55 22 BRIDGE REHAB
- Let date
- Friday, January 16, 2026
- Contract
- 62R76 · job page
- District
- District 1
- County
- Will
- Highway
- Limits
- (290-Ft) Bridge Deck Overlay, (SN 099-0210) over I-55. The project consists of reconstruction of the expansion joints with strip seals, hydro scarification (3/4-), deck and approach slab repairs, latex concrete overlay (2¼-) with diamond grinding and longitudinal grooving, application of a protective coat, and substructure concrete repair. Roadway improvements include HMA on each side of the bridge. I-55 at Caton Farm Road (3 miles north of US 52) in the Village of Plainfield.
- Classification
- Reconstruction of the expansion joints with strip seals, hydro scarification (3/4-), deck and approach slab re ·
- Project number
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $647,187 | ||
| 2 | ERA-Valdivia Contractors, Inc. | $759,676 | +17.4% | |
| 3 | Martam Construction Incorporated | $827,016 | +27.8% | |
| 4 | Areatha Construction Co., Inc. | $942,204 | +45.6% | |
| 5 | Herlihy Mid-Continent Company | $968,132 | +49.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 ERA-Valdivia Co… | #3 Martam Construc… | #4 Areatha Constru… | #5 Herlihy Mid-Con… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X4400503 | CC&G RMVL REPL > 10FT | 160 | FOOT | $50.00 | $125.00 | $85.00 | $230.20 | $95.00 | |
| 2 | X5030250 | BR DECK GROOVING LONG | 914 | SQ YD | $9.00 | $15.00 | $10.00 | $7.85 | $9.74 | |
| 3 | X6700407 | ENGRS FLD OFC TY A D1 | 12 | CAL MO | $5,000.00 | $2,200.00 | $4,500.00 | $2,500.00 | $4,710.00 | |
| 4 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $53,100.00 | $23,000.00 | $96,000.00 | $19,426.00 | $78,635.00 | |
| 5 | X7011015 | TR C-PROT EXPRESSWAYS | 1 | L SUM | $0.0100 | $26,000.00 | $40,000.00 | $10,000.00 | $100,000.00 | |
| 6 | X7200061 | TEMP INFO SIGNING | 102.8 | SQ FT | $30.00 | $17.00 | $13.00 | $102.80 | $17.00 | |
| 7 | Z0001800 | APPR SLAB REPAIR (PD) | 14 | SQ YD | $750.00 | $850.00 | $750.00 | $915.80 | $1,950.00 | |
| 8 | Z0006014 | BR DK LTX C OLY 2 1/2 | 997 | SQ YD | $125.00 | $155.00 | $163.00 | $209.00 | $195.00 | |
| 9 | Z0012130 | BR DECK SCAR 3/4 | 997 | SQ YD | $60.00 | $75.23 | $65.00 | $110.00 | $93.00 | |
| 10 | Z0012754 | STR REP CON DP = < 5 | 166 | SQ FT | $150.00 | $195.00 | $275.00 | $201.60 | $220.00 | |
| 11 | Z0012755 | STR REP CON DP OVER 5 | 8 | SQ FT | $300.00 | $350.00 | $285.00 | $243.40 | $660.00 | |
| 12 | Z0029090 | DIAMOND GRIND BR SEC | 914 | SQ YD | $12.00 | $22.00 | $11.00 | $16.65 | $15.09 | |
| 13 | 40600290 | BIT MATLS TACK CT | 212 | POUND | $0.0100 | $1.00 | $5.00 | $0.1000 | $0.0100 | |
| 14 | 40600982 | HMA SURF REM BUTT JT | 306 | SQ YD | $0.0100 | $1.25 | $16.00 | $1.00 | $83.76 | |
| 15 | 40604062 | HMA SC IL-9.5 D N70 | 54 | TON | $200.00 | $550.00 | $560.00 | $500.00 | $613.48 | |
| 16 | 50102400 | CONC REM | 15 | CU YD | $2,500.00 | $3,000.00 | $2,400.00 | $2,398.70 | $2,250.00 | |
| 17 | 50157300 | PROTECTIVE SHIELD | 162 | SQ YD | $100.00 | $125.00 | $85.00 | $567.00 | $250.00 | |
| 18 | 50300255 | CONC SUP-STR | 17 | CU YD | $3,000.00 | $3,200.00 | $3,200.00 | $4,365.25 | $2,350.00 | |
| 19 | 50300300 | PROTECTIVE COAT | 1,115 | SQ YD | $1.00 | $2.00 | $1.00 | $4.00 | $1.70 | |
| 20 | 50800205 | REINF BARS, EPOXY CTD | 2,580 | POUND | $3.50 | $5.75 | $4.00 | $4.70 | $2.25 | |
| 21 | 50800515 | BAR SPLICERS | 24 | EACH | $50.00 | $90.00 | $65.00 | $82.90 | $46.00 | |
| 22 | 52000110 | PREF JT STRIP SEAL | 102 | FOOT | $275.00 | $390.00 | $285.00 | $407.45 | $228.00 | |
| 23 | 60260100 | INLETS ADJUST | 4 | EACH | $1,000.00 | $750.00 | $800.00 | $850.00 | $650.00 | |
| 24 | 63100085 | TRAF BAR TERM T6 | 1 | EACH | $5,390.00 | $10,000.00 | $5,800.00 | $5,438.00 | $5,438.00 | |
| 25 | 63200310 | GUARDRAIL REMOV | 37.5 | FOOT | $25.00 | $17.50 | $20.00 | $17.00 | $17.00 | |
| 26 | 67100100 | MOBILIZATION | 1 | L SUM | $38,800.00 | $30,000.00 | $49,000.00 | $55,894.00 | $58,000.00 | |
| 27 | 70107025 | CHANGEABLE MESSAGE SN | 120 | CAL DA | $75.00 | $35.00 | $30.00 | $30.00 | $35.00 | |
| 28 | 70300150 | SHRT TRM PAVT MK REM | 3,263 | SQ FT | $0.0100 | $1.00 | $0.5000 | $1.50 | $0.3900 | |
| 29 | 70307120 | TEMP PVT MK L4 T4 TAPE | 9,790 | FOOT | $0.0100 | $1.50 | $1.40 | $1.20 | $1.35 | |
| 30 | 70400100 | TEMP CONC BARRIER | 614 | FOOT | $35.00 | $39.00 | $40.00 | $53.90 | $19.00 | |
| 31 | 70400200 | REL TEMP CONC BARRIER | 614 | FOOT | $15.00 | $12.00 | $6.00 | $11.90 | $7.00 | |
| 32 | 70600241 | IMP ATTN TEMP NRN TL2 | 2 | EACH | $6,500.00 | $6,500.00 | $3,300.00 | $3,300.00 | $2,900.00 | |
| 33 | 70600340 | IMP ATTN REL NRD TL2 | 2 | EACH | $2,500.00 | $1,800.00 | $660.00 | $1,760.00 | $1,500.00 | |
| 34 | 78000200 | THPL PVT MK LINE 4 | 3,163 | FOOT | $1.65 | $2.50 | $2.50 | $2.30 | $2.30 | |
| 35 | 78000600 | THPL PVT MK LINE 12 | 35 | FOOT | $4.95 | $3.50 | $5.00 | $4.45 | $4.45 | |
| 36 | 78004635 | PREF PL PM TD STD L 7 | 48 | FOOT | $33.00 | $60.00 | $50.00 | $45.00 | $45.00 | |
| 37 | 78009004 | MOD URETH PM LINE 4 | 380 | FOOT | $8.80 | $13.00 | $9.00 | $8.40 | $8.40 | |
| 38 | 78009012 | MOD URETH PM LINE 12 | 35 | FOOT | $27.50 | $15.00 | $25.00 | $22.00 | $22.00 | |
| 39 | 78011040 | GRV RCSD PVT MRKG 8 | 48 | FOOT | $44.00 | $70.00 | $20.00 | $18.50 | $18.50 | |
| 40 | 78200005 | GRDRAIL REF TYPE A | 84 | EACH | $22.00 | $55.00 | $13.00 | $12.00 | $12.00 | |
| 41 | 78200011 | BARR WALL REF TYPE C | 32 | EACH | $15.00 | $16.00 | $10.00 | $25.00 | $10.00 | |
| 42 | 78300200 | RAISED REF PVT MK REM | 12 | EACH | $25.00 | $55.00 | $30.00 | $25.00 | $50.00 | |
| 43 | 78300202 | PVT MKG REM WTR BLAST | 558 | SQ FT | $6.60 | $7.00 | $6.00 | $8.10 | $10.00 |