20-00243-00-BR
- Let date
- Friday, January 16, 2026
- Contract
- 61L19 · job page
- District
- District 1
- County
- Lake
- Highway
- Limits
- Construction of a single-span PPC IL-beam bridge with intgral abutments carrying Greenwood Avenue over the Union Pacific Railroad in Waukegan. Additional work includes MSE retaining walls, HMA approach roadways, guardrail, and lighting.
- Classification
- ·
- Project number
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Dunnet Bay Construction Company Low bidder | $7,980,812 | ||
| 2 | Lorig Construction Company | $7,989,739 | +0.1% | |
| 3 | Rausch Infrastructure, LLC | $8,234,574 | +3.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Dunnet Bay Cons… | #2 Lorig Construct… | #3 Rausch Infrastr… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2010400 | STUMP REMOVAL ONLY | 186 | UNIT | $10.00 | $5.00 | $5.80 | |
| 2 | X2010510 | CLEARING & GRUBBING | 1 | L SUM | $4,500.00 | $6,500.00 | $7,572.50 | |
| 3 | X2130010 | EXPLOR TRENCH SPL | 100 | FOOT | $85.00 | $125.00 | $58.20 | |
| 4 | X5080530 | BAR TERMINATORS | 608 | EACH | $51.03 | $35.00 | $42.80 | |
| 5 | X5091755 | PARAPET RAILING SPL | 291 | FOOT | $339.91 | $345.00 | $339.91 | |
| 6 | X6028000 | MAN RECONST SPL | 1 | EACH | $10,000.00 | $7,000.00 | $9,217.40 | |
| 7 | X6050188 | PLUG PIPE PENETRATION | 1 | EACH | $2,100.00 | $2,600.00 | $1,903.60 | |
| 8 | X6330725 | SPBGR (SHORT RADIUS) | 175 | FOOT | $35.50 | $36.00 | $41.30 | |
| 9 | X6431120 | REM IMP ATTEN SM | 2 | EACH | $2,000.00 | $1,200.00 | $873.70 | |
| 10 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $25,000.00 | $400,000.00 | $29,125.00 | |
| 11 | X7040650 | REM TEMP CONC BARRIER | 401 | FOOT | $20.00 | $12.00 | $19.80 | |
| 12 | X7200061 | TEMP INFO SIGNING | 75 | SQ FT | $18.00 | $20.00 | $16.30 | |
| 13 | X8900106 | TEMP TR SIGNAL TIMING SPL | 2 | EACH | $720.00 | $1,000.00 | $699.00 | |
| 14 | Z0004552 | APPROACH SLAB REM | 392 | SQ YD | $63.48 | $59.00 | $49.70 | |
| 15 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $8,705.40 | $235,000.00 | $33,202.50 | |
| 16 | Z0043900 | PREF JOINT FILLER | 98 | FOOT | $15.00 | $22.00 | $16.20 | |
| 17 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $22,000.00 | $16,000.00 | $9,320.00 | |
| 18 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 19 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | $15.00 | |
| 20 | 20100110 | TREE REMOV 6-15 | 157 | UNIT | $35.00 | $25.00 | $29.10 | |
| 21 | 20100210 | TREE REMOV OVER 15 | 18 | UNIT | $55.00 | $32.00 | $37.20 | |
| 22 | 20101000 | TEMPORARY FENCE | 1,561 | FOOT | $2.98 | $3.00 | $3.40 | |
| 23 | 20200100 | EARTH EXCAVATION | 1,695 | CU YD | $30.00 | $20.00 | $60.00 | |
| 24 | 20201200 | REM & DISP UNS MATL | 2,120 | CU YD | $0.0100 | $24.00 | $42.00 | |
| 25 | 20400800 | FURNISHED EXCAVATION | 1,075 | CU YD | $25.00 | $65.00 | $72.00 | |
| 26 | 21001000 | GEOTECH FAB F/GR STAB | 1,252 | SQ YD | $2.25 | $3.00 | $3.50 | |
| 27 | 21101625 | TOPSOIL F & P 6 | 1,095 | SQ YD | $11.50 | $10.00 | $11.50 | |
| 28 | 25000210 | SEEDING CL 2A | 0.25 | ACRE | $2,750.00 | $3,500.00 | $2,750.00 | |
| 29 | 25000320 | SEEDING CL 5 | 1 | ACRE | $4,531.00 | $6,000.00 | $4,531.00 | |
| 30 | 25000400 | NITROGEN FERT NUTR | 23 | POUND | $3.00 | $3.00 | $3.00 | |
| 31 | 25000600 | POTASSIUM FERT NUTR | 23 | POUND | $3.00 | $3.00 | $3.00 | |
| 32 | 25100630 | EROSION CONTR BLANKET | 4,658 | SQ YD | $1.41 | $1.50 | $1.41 | |
| 33 | 28000250 | TEMP EROS CONTR SEED | 102 | POUND | $4.00 | $4.00 | $4.00 | |
| 34 | 28000400 | PERIMETER EROS BAR | 1,610 | FOOT | $3.65 | $2.25 | $3.65 | |
| 35 | 28000510 | INLET FILTERS | 3 | EACH | $295.00 | $250.00 | $295.00 | |
| 36 | 28001100 | TEMP EROS CONTR BLANK | 4,653 | SQ YD | $0.9700 | $1.30 | $0.9700 | |
| 37 | 30300001 | AGG SUBGRADE IMPROVE | 1,252 | CU YD | $50.00 | $40.00 | $85.00 | |
| 38 | 30300112 | AGG SUBGRADE IMPR 12 | 6,273 | SQ YD | $42.00 | $28.00 | $35.00 | |
| 39 | 31200500 | STAB SUBBASE HMA 4 | 247 | SQ YD | $56.60 | $61.00 | $65.90 | |
| 40 | 35101800 | AGG BASE CSE B 6 | 46 | SQ YD | $33.00 | $33.00 | $84.50 | |
| 41 | 35501309 | HMA BASE CSE 6 1/4 | 5,008 | SQ YD | $34.55 | $39.00 | $34.55 | |
| 42 | 40600290 | BIT MATLS TACK CT | 4,508 | POUND | $0.0100 | $0.0100 | $0.0100 | |
| 43 | 40603080 | HMA BC IL-19.0 N50 | 632 | TON | $91.75 | $97.00 | $91.75 | |
| 44 | 40604060 | HMA SC IL-9.5 D N50 | 421 | TON | $102.00 | $110.00 | $102.00 | |
| 45 | 42000060 | WELDED WIRE REINF | 247 | SQ YD | $44.57 | $18.00 | $8.00 | |
| 46 | 42000080 | PVT CON PCC BR APP SL | 247 | SQ YD | $200.00 | $183.00 | $165.36 | |
| 47 | 42400200 | PC CONC SIDEWALK 5 | 1,981 | SQ FT | $12.00 | $15.00 | $12.31 | |
| 48 | 44000100 | PAVEMENT REM | 4,893 | SQ YD | $21.50 | $51.50 | $32.60 | |
| 49 | 44000500 | COMB CURB GUTTER REM | 2,167 | FOOT | $10.00 | $10.00 | $11.80 | |
| 50 | 44000600 | SIDEWALK REM | 1,622 | SQ FT | $3.00 | $4.00 | $3.20 | |
| 51 | 44003100 | MEDIAN REMOVAL | 3,804 | SQ FT | $8.00 | $2.00 | $8.10 | |
| 52 | 48101500 | AGGREGATE SHLDS B 6 | 81 | SQ YD | $39.00 | $41.00 | $102.60 | |
| 53 | 50100100 | REM EXIST STRUCT | 1 | EACH | $627,000.00 | $1,400,000.00 | $1,000,000.00 | |
| 54 | 50104650 | SLOPE WALL REMOV | 1,108 | SQ YD | $27.57 | $16.00 | $27.80 | |
| 55 | 50157300 | PROTECTIVE SHIELD | 683 | SQ YD | $0.0100 | $1.00 | $145.00 | |
| 56 | 50200100 | STRUCTURE EXCAVATION | 5,548 | CU YD | $120.00 | $50.00 | $23.00 | |
| 57 | 50300225 | CONC STRUCT | 250.5 | CU YD | $600.00 | $1,000.00 | $625.00 | |
| 58 | 50300255 | CONC SUP-STR | 502.1 | CU YD | $1,400.00 | $825.00 | $925.00 | |
| 59 | 50300260 | BR DECK GROOVING | 1,114 | SQ YD | $8.30 | $7.00 | $9.10 | |
| 60 | 50300300 | PROTECTIVE COAT | 1,748 | SQ YD | $3.58 | $1.75 | $2.90 | |
| 61 | 50301350 | CONC SUPSTR APP SLAB | 231.5 | CU YD | $700.00 | $625.00 | $515.00 | |
| 62 | 50401320 | F&E PP CON BEAMS IL45 | 1,491 | FOOT | $700.00 | $660.00 | $690.00 | |
| 63 | 50800205 | REINF BARS, EPOXY CTD | 203,800 | POUND | $1.69 | $1.65 | $1.65 | |
| 64 | 51200963 | FUR M S PILE 16X0.375 | 780 | FOOT | $179.00 | $100.00 | $220.00 | |
| 65 | 51202305 | DRIVING PILES | 780 | FOOT | $0.0100 | $1.00 | $1.00 | |
| 66 | 51203200 | TEST PILE MET SHELLS | 2 | EACH | $20,000.00 | $2,000.00 | $10,000.00 | |
| 67 | 51204650 | PILE SHOES | 13 | EACH | $470.00 | $500.00 | $470.00 | |
| 68 | 51500100 | NAME PLATES | 1 | EACH | $1,000.00 | $800.00 | $1,747.50 | |
| 69 | 52100010 | ELAST BEARING ASSY T1 | 13 | EACH | $2,281.00 | $2,300.00 | $3,528.50 | |
| 70 | 52100520 | ANCHOR BOLTS 1 | 26 | EACH | $200.00 | $200.00 | $183.00 | |
| 71 | 52200500 | MECH ST EARTH RET WL | 7,884 | SQ FT | $155.00 | $100.00 | $192.80 | |
| 72 | 55100500 | STORM SEWER REM 12 | 24 | FOOT | $81.00 | $75.00 | $125.80 | |
| 73 | 60254100 | CB RECON NEW T11F&G | 3 | EACH | $3,500.00 | $4,100.00 | $9,217.40 | |
| 74 | 60500050 | REMOV CATCH BAS | 1 | EACH | $1,800.00 | $2,100.00 | $2,625.90 | |
| 75 | 60605000 | COMB CC&G TY B-6.24 | 1,219 | FOOT | $70.65 | $56.00 | $45.25 | |
| 76 | 60618300 | CONC MEDIAN SURF 4 | 368 | SQ FT | $18.95 | $8.00 | $12.87 | |
| 77 | 60619600 | CONC MED TSB6.12 | 466 | SQ FT | $10.30 | $25.00 | $18.52 | |
| 78 | 63000001 | SPBGR TY A 6FT POSTS | 650 | FOOT | $44.06 | $30.00 | $29.38 | |
| 79 | 63100045 | TRAF BAR TERM T2 | 6 | EACH | $1,519.00 | $1,550.00 | $1,519.00 | |
| 80 | 63100070 | TRAF BAR TERM T5 | 1 | EACH | $1,289.60 | $1,200.00 | $1,108.00 | |
| 81 | 63100085 | TRAF BAR TERM T6 | 3 | EACH | $4,176.05 | $3,900.00 | $3,861.20 | |
| 82 | 63200310 | GUARDRAIL REMOV | 1,067 | FOOT | $6.90 | $7.00 | $8.00 | |
| 83 | 66900200 | NON SPL WASTE DISPOSL | 9,165 | CU YD | $65.00 | $40.00 | $70.00 | |
| 84 | 66900530 | SOIL DISPOSAL ANALY | 4 | EACH | $850.00 | $1,500.00 | $1,689.20 | |
| 85 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $5,800.00 | $3,100.00 | $3,611.50 | |
| 86 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $500.00 | $1,200.00 | $1,398.00 | |
| 87 | 66901006 | REG SUB MON | 30 | CAL DA | $715.00 | $2,200.00 | $792.20 | |
| 88 | 67000400 | ENGR FIELD OFFICE A | 15 | CAL MO | $4,566.21 | $3,900.00 | $4,000.00 | |
| 89 | 67100100 | MOBILIZATION | 1 | L SUM | $478,848.74 | $425,000.00 | $492,619.87 | |
| 90 | 70107025 | CHANGEABLE MESSAGE SN | 150 | CAL DA | $30.00 | $30.00 | $31.40 | |
| 91 | 70300150 | SHRT TRM PAVT MK REM | 178 | SQ FT | $3.00 | $11.00 | $0.7000 | |
| 92 | 70307120 | TEMP PVT MK L4 T4 TAPE | 440 | FOOT | $2.25 | $2.25 | $1.30 | |
| 93 | 70307210 | TEMP PVT MK L24 T4 TAPE | 16 | FOOT | $15.00 | $15.00 | $8.40 | |
| 94 | 72000100 | SIGN PANEL T1 | 51 | SQ FT | $30.00 | $30.00 | $34.90 | |
| 95 | 72400100 | REMOV SIN PAN ASSY TA | 8 | EACH | $100.00 | $10.00 | $58.20 | |
| 96 | 72800100 | TELES STL SIN SUPPORT | 56 | FOOT | $20.00 | $20.00 | $25.60 | |
| 97 | 73100100 | BASE TEL STL SIN SUPP | 4 | EACH | $250.00 | $250.00 | $407.70 | |
| 98 | 78000100 | THPL PVT MK LTR & SYM | 52 | SQ FT | $5.75 | $5.75 | $9.00 | |
| 99 | 78000200 | THPL PVT MK LINE 4 | 2,970 | FOOT | $1.45 | $1.50 | $1.50 | |
| 100 | 78000400 | THPL PVT MK LINE 6 | 165 | FOOT | $1.72 | $2.00 | $2.25 | |
| 101 | 78000500 | THPL PVT MK LINE 8 | 450 | FOOT | $1.95 | $2.00 | $3.00 | |
| 102 | 78000600 | THPL PVT MK LINE 12 | 782 | FOOT | $3.32 | $3.50 | $4.50 | |
| 103 | 78000650 | THPL PVT MK LINE 24 | 73 | FOOT | $5.75 | $6.00 | $9.00 | |
| 104 | 78008300 | POLYUREA PM T2 LTR-SY | 58 | SQ FT | $14.50 | $14.50 | $42.00 | |
| 105 | 78008310 | POLYUREA PM T2 LN 4 | 762 | FOOT | $5.80 | $6.00 | $7.00 | |
| 106 | 78008330 | POLYUREA PM T2 LN 6 | 180 | FOOT | $7.80 | $8.00 | $10.50 | |
| 107 | 78008340 | POLYUREA PM T2 LN 8 | 22 | FOOT | $10.60 | $11.00 | $14.00 | |
| 108 | 78008350 | POLYUREA PM T2 LN 12 | 74 | FOOT | $14.95 | $15.00 | $21.00 | |
| 109 | 78100100 | RAISED REFL PAVT MKR | 6 | EACH | $750.00 | $750.00 | $1,250.00 | |
| 110 | 78200005 | GRDRAIL REF TYPE A | 28 | EACH | $11.00 | $11.00 | $12.80 | |
| 111 | 78300200 | RAISED REF PVT MK REM | 6 | EACH | $11.62 | $25.00 | $97.00 | |
| 112 | 80400100 | ELECT SERV INSTALL | 1 | EACH | $5,513.40 | $5,700.00 | $5,513.40 | |
| 113 | 80400200 | ELECT UTIL SERV CONN | 1 | L SUM | $5,000.00 | $5,000.00 | $5,000.00 | |
| 114 | 81028190 | UNDRGRD C GALVS 1 1/2 | 500 | FOOT | $31.60 | $32.00 | $31.60 | |
| 115 | 81028220 | UNDRGRD C GALVS 3 | 100 | FOOT | $91.30 | $92.00 | $91.30 | |
| 116 | 81028320 | UNDRGRD C PVC 1 | 110 | FOOT | $42.10 | $44.00 | $42.10 | |
| 117 | 81100320 | CON AT ST 1 PVC GS | 280 | FOOT | $70.80 | $72.00 | $70.80 | |
| 118 | 81300550 | JUN BX SS AS 12X12X6 | 1 | EACH | $1,695.20 | $1,800.00 | $1,695.20 | |
| 119 | 81702110 | EC C XLP USE 1C 10 | 1,320 | FOOT | $3.90 | $4.00 | $3.90 | |
| 120 | 81702140 | EC C XLP USE 1C 4 | 1,300 | FOOT | $7.60 | $8.00 | $7.60 | |
| 121 | 82110008 | LUM LED RDWY H | 2 | EACH | $1,183.10 | $1,200.00 | $1,183.10 | |
| 122 | 82110027 | LUM LED UP SUS E | 4 | EACH | $5,128.40 | $5,200.00 | $5,128.40 | |
| 123 | 82500350 | LT CONT BASEM 240V100 | 1 | EACH | $24,340.20 | $25,000.00 | $24,340.20 | |
| 124 | 83050810 | LT P A 47.5MH 15MA | 2 | EACH | $7,589.30 | $7,700.00 | $7,589.30 | |
| 125 | 83600200 | LIGHT POLE FDN 24D | 20 | FOOT | $476.50 | $500.00 | $476.50 |