[(Z-D-SB)BR]BJR,BP
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Stark Excavating, Inc. Low bidder | $878,313 | ||
| 2 | Otto Baum Company, Inc. | $1,070,700 | +21.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Stark Excavatin… | #2 Otto Baum Compa… |
|---|---|---|---|---|---|---|---|
| 1 | X0324966 | CONC HEALER SEALER | 1,265 | SQ YD | $27.00 | $58.14 | |
| 2 | X0326444 | SURFACE FILLER SPL | 0.6 | GALLON | $2,301.00 | $2,317.43 | |
| 3 | X5030550 | PROTECTIVE COAT SPL | 513 | SQ YD | $52.00 | $108.37 | |
| 4 | X5060601 | C&D N-LEAD PT C RS N1 | 1 | L SUM | $94,600.00 | $94,600.00 | |
| 5 | X5110312 | SLOPEWALL SLUR PUMPNG | 10 | CU YD | $950.00 | $956.68 | |
| 6 | Z0010501 | CLEAN & PT STL BR N1 | 1 | L SUM | $280,000.00 | $378,400.00 | |
| 7 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $5,000.00 | $3,840.91 | |
| 8 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $4,000.00 | $54,746.79 | |
| 9 | 21400100 | GRADING & SHAP DITCH | 40 | FOOT | $33.00 | $152.24 | |
| 10 | 28100125 | STONE RIPRAP CL B3 | 172 | SQ YD | $67.00 | $84.27 | |
| 11 | 28200200 | FILTER FABRIC | 72 | SQ YD | $1.75 | $27.00 | |
| 12 | 44000300 | CURB REM | 17 | FOOT | $160.00 | $152.84 | |
| 13 | 50102400 | CONC REM | 14.2 | CU YD | $4,100.00 | $5,132.60 | |
| 14 | 50300255 | CONC SUP-STR | 14.4 | CU YD | $4,500.00 | $4,897.95 | |
| 15 | 50800205 | REINF BARS, EPOXY CTD | 1,540 | POUND | $5.00 | $4.64 | |
| 16 | 50800515 | BAR SPLICERS | 24 | EACH | $55.00 | $90.67 | |
| 17 | 52000110 | PREF JT STRIP SEAL | 88 | FOOT | $295.00 | $248.34 | |
| 18 | 60260100 | INLETS ADJUST | 1 | EACH | $1,250.00 | $1,924.93 | |
| 19 | 60600605 | CONC CURB TB | 17 | FOOT | $250.00 | $443.27 | |
| 20 | 67100100 | MOBILIZATION | 1 | L SUM | $125,250.00 | $74,200.25 | |
| 21 | 70100405 | TRAF CONT-PROT 701321 | 1 | EACH | $4,500.00 | $13,000.00 | |
| 22 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $825.00 | $700.00 | |
| 23 | 70106500 | TEMP BR TRAF SIGNALS | 1 | EACH | $25,000.00 | $20,843.14 | |
| 24 | 70106700 | TEMP RUMBLE STRIPS | 6 | EACH | $760.00 | $1,425.00 | |
| 25 | 70107005 | PAVT MK BLKOUT TAPE 5 | 2,277 | FOOT | $2.50 | $2.95 | |
| 26 | 70300150 | SHRT TRM PAVT MK REM | 2,013 | SQ FT | $0.2600 | $1.50 | |
| 27 | 70307120 | TEMP PVT MK L4 T4 TAPE | 3,192 | FOOT | $1.75 | $1.95 | |
| 28 | 70400100 | TEMP CONC BARRIER | 650 | FOOT | $60.00 | $40.94 | |
| 29 | 70400200 | REL TEMP CONC BARRIER | 625 | FOOT | $15.00 | $11.19 | |
| 30 | 70600250 | IMP ATTN TEMP NRD TL3 | 2 | EACH | $4,900.00 | $5,089.55 | |
| 31 | 70600350 | IMP ATTN REL NRD TL3 | 2 | EACH | $850.00 | $500.00 | |
| 32 | 78009004 | MOD URETH PM LINE 4 | 800 | FOOT | $4.00 | $3.80 | |
| 33 | 78009006 | MOD URETH PM LINE 6 | 800 | FOOT | $5.00 | $5.00 | |
| 34 | 78011025 | GRV RCSD PVT MRKG 5 | 800 | FOOT | $2.00 | $2.00 | |
| 35 | 78011035 | GRV RCSD PVT MRKG 7 | 800 | FOOT | $4.00 | $3.95 |