2025-2014-RS
- Let date
- Friday, June 12, 2026
- Contract
- 80B33 · job page
- District
- District 1
- County
- Cook
- Highway
- Limits
- (5,764-Ft) Design Overlay, ADA Improvements consists of (HMA) surface removal, pavement patching, (HMA) shoulders, resurfacing with (HMA) binder and surface course, concrete curb and gutter removal and replacement, pedestrian curb ramps (ADA) improvements, raised reflective pavement markers, thermoplastic pavement marking. The project is located within the City of Harvey in Cook County.
- Classification
- (HMA) surface removal, pavement patching, (HMA) shoulders, resurfacing with (HMA) binder and surface course, c ·
- Project number
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $933,943 | ||
| 2 | Gallagher Asphalt Corporation | $986,378 | +5.6% | |
| 3 | K-Five Construction Corporation | $989,462 | +5.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 Gallagher Aspha… | #3 K-Five Construc… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $10,000.00 | $4,200.00 | $7,500.00 | |
| 2 | X2020110 | GRADING & SHAP SHLDRS | 55.2 | UNIT | $125.00 | $527.00 | $100.00 | |
| 3 | X4022000 | TEMP ACCESS- COM ENT | 3 | EACH | $55.00 | $686.00 | $50.00 | |
| 4 | X4400501 | CC&G RMVL REPL < = 10 | 56 | FOOT | $71.50 | $69.00 | $75.00 | |
| 5 | X4400503 | CC&G RMVL REPL > 10FT | 322 | FOOT | $60.50 | $69.00 | $57.45 | |
| 6 | X5537800 | SS CLEANED 12 | 150 | FOOT | $6.60 | $3.00 | $10.00 | |
| 7 | X6030310 | FR & LIDS ADJUST SPL | 9 | EACH | $1,000.00 | $1,300.00 | $1,985.00 | |
| 8 | X6700407 | ENGRS FLD OFC TY A D1 | 12 | CAL MO | $4,500.00 | $500.00 | $3,500.00 | |
| 9 | X7200061 | TEMP INFO SIGNING | 184 | SQ FT | $30.00 | $30.00 | $30.00 | |
| 10 | X8860105 | DET LOOP REPL | 237 | FOOT | $40.37 | $36.70 | $36.70 | |
| 11 | Z0018500 | DRAINAGE STR CLEANED | 10 | EACH | $462.00 | $450.00 | $500.00 | |
| 12 | 20200100 | EARTH EXCAVATION | 750 | CU YD | $45.00 | $60.00 | $80.00 | |
| 13 | 20201200 | REM & DISP UNS MATL | 83 | CU YD | $40.00 | $65.00 | $55.00 | |
| 14 | 21001000 | GEOTECH FAB F/GR STAB | 249 | SQ YD | $5.00 | $2.00 | $5.00 | |
| 15 | 21101600 | TOPSOIL F & P VAR DP | 513 | SQ YD | $11.00 | $12.50 | $10.00 | |
| 16 | 25200110 | SODDING SALT TOLERANT | 513 | SQ YD | $33.00 | $12.50 | $30.00 | |
| 17 | 25200200 | SUPPLE WATERING | 7.7 | UNIT | $55.00 | $446.00 | $50.00 | |
| 18 | 30300001 | AGG SUBGRADE IMPROVE | 83 | CU YD | $60.00 | $79.40 | $75.00 | |
| 19 | 30300112 | AGG SUBGRADE IMPR 12 | 994 | SQ YD | $26.00 | $28.55 | $55.00 | |
| 20 | 31101200 | SUB GRAN MAT B 4 | 108 | SQ YD | $19.80 | $13.60 | $12.00 | |
| 21 | 35501308 | HMA BASE CSE 6 | 14 | SQ YD | $100.00 | $120.65 | $250.00 | |
| 22 | 35600704 | HMA BC WID 7 | 994 | SQ YD | $46.00 | $48.30 | $42.20 | |
| 23 | 40600275 | BIT MATLS PR CT | 2,236 | POUND | $0.0100 | $0.0100 | $0.0100 | |
| 24 | 40600290 | BIT MATLS TACK CT | 12,746 | POUND | $0.0100 | $0.0100 | $0.0100 | |
| 25 | 40600370 | LONG JOINT SEALANT | 5,662 | FOOT | $3.99 | $3.80 | $3.25 | |
| 26 | 40600400 | MIX CR JTS FLANGEWYS | 27 | TON | $0.0100 | $239.35 | $50.00 | |
| 27 | 40600982 | HMA SURF REM BUTT JT | 57 | SQ YD | $25.00 | $0.0100 | $25.00 | |
| 28 | 40601005 | HMA REPL OVER PATCH | 43 | TON | $0.0100 | $186.00 | $245.00 | |
| 29 | 40603200 | P HMA BC IL-4.75 N50 | 1,039 | TON | $103.00 | $127.00 | $105.00 | |
| 30 | 40604060 | HMA SC IL-9.5 D N50 | 2 | TON | $0.0100 | $367.00 | $775.00 | |
| 31 | 40604062 | HMA SC IL-9.5 D N70 | 2,115 | TON | $83.50 | $94.00 | $90.00 | |
| 32 | 42001300 | PROTECTIVE COAT | 788 | SQ YD | $1.10 | $1.15 | $0.0100 | |
| 33 | 42300400 | PCC DRIVEWAY PAVT 8 | 108 | SQ YD | $148.50 | $83.00 | $91.25 | |
| 34 | 42400200 | PC CONC SIDEWALK 5 | 5,362 | SQ FT | $11.00 | $7.10 | $9.25 | |
| 35 | 42400800 | DETECTABLE WARNINGS | 203 | SQ FT | $33.00 | $20.00 | $25.50 | |
| 36 | 44000161 | HMA SURF REM 3 | 17,889 | SQ YD | $2.75 | $5.50 | $3.25 | |
| 37 | 44000600 | SIDEWALK REM | 5,437 | SQ FT | $2.75 | $2.70 | $2.75 | |
| 38 | 44002212 | HMA RM OV PATCH 3 | 252 | SQ YD | $0.0100 | $55.00 | $1.50 | |
| 39 | 44201753 | CL D PATCH T2 9 | 80 | SQ YD | $90.00 | $100.00 | $124.00 | |
| 40 | 44201757 | CL D PATCH T3 9 | 48 | SQ YD | $90.00 | $100.00 | $124.00 | |
| 41 | 44201759 | CL D PATCH T4 9 | 95 | SQ YD | $90.00 | $100.00 | $124.00 | |
| 42 | 48102100 | AGG WEDGE SHLD TYPE B | 157 | TON | $40.00 | $65.00 | $85.00 | |
| 43 | 60250200 | CB ADJUST | 6 | EACH | $750.00 | $615.00 | $550.00 | |
| 44 | 60252800 | CB RECONST | 1 | EACH | $1,500.00 | $1,400.00 | $1,850.00 | |
| 45 | 60300105 | FR & GRATES ADJUST | 2 | EACH | $800.00 | $345.00 | $550.00 | |
| 46 | 60300305 | FR & LIDS ADJUST | 2 | EACH | $800.00 | $345.00 | $850.00 | |
| 47 | 60406000 | FR & LIDS T1 OL | 3 | EACH | $600.00 | $360.00 | $685.00 | |
| 48 | 60920012 | PIPE CULV CLEANED 12 | 60 | FOOT | $13.20 | $3.00 | $10.00 | |
| 49 | 66900200 | NON SPL WASTE DISPOSL | 750 | CU YD | $80.00 | $71.75 | $85.00 | |
| 50 | 66900530 | SOIL DISPOSAL ANALY | 4 | EACH | $1,650.00 | $975.00 | $975.00 | |
| 51 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,250.00 | $5,300.00 | $5,300.00 | |
| 52 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,250.00 | $500.00 | $500.00 | |
| 53 | 66901006 | REG SUB MON | 4 | CAL DA | $1,000.00 | $715.00 | $715.00 | |
| 54 | 67100100 | MOBILIZATION | 1 | L SUM | $37,200.00 | $59,175.50 | $38,450.00 | |
| 55 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $42,170.00 | $3,500.00 | $3,500.00 | |
| 56 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $0.0100 | $50.00 | $50.00 | |
| 57 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $0.0100 | $50.00 | $50.00 | |
| 58 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $0.0100 | $500.00 | $500.00 | |
| 59 | 70300100 | SHORT TERM PAVT MKING | 1,540 | FOOT | $0.0100 | $0.0100 | $1.00 | |
| 60 | 70300150 | SHRT TRM PAVT MK REM | 129 | SQ FT | $0.0100 | $0.0100 | $2.00 | |
| 61 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 23,958 | FOOT | $0.0100 | $0.0100 | $0.4000 | |
| 62 | 70300251 | TEMP PVT MK LINE 8 - PAINT | 230 | FOOT | $0.0100 | $0.0100 | $0.4000 | |
| 63 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 1,060 | FOOT | $0.0100 | $0.0100 | $1.50 | |
| 64 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 216 | FOOT | $0.0100 | $0.0100 | $2.00 | |
| 65 | 70307120 | TEMP PVT MK L4 T4 TAPE | 385 | FOOT | $0.0100 | $0.0100 | $1.40 | |
| 66 | 72400310 | REMOV SIGN PANEL T1 | 13 | SQ FT | $25.00 | $50.00 | $50.00 | |
| 67 | 78000200 | THPL PVT MK LINE 4 | 11,979 | FOOT | $0.8800 | $0.7500 | $0.7500 | |
| 68 | 78000500 | THPL PVT MK LINE 8 | 115 | FOOT | $1.65 | $1.55 | $1.55 | |
| 69 | 78000600 | THPL PVT MK LINE 12 | 530 | FOOT | $2.75 | $2.50 | $2.50 | |
| 70 | 78000650 | THPL PVT MK LINE 24 | 108 | FOOT | $5.50 | $5.00 | $5.00 | |
| 71 | 78100100 | RAISED REFL PAVT MKR | 128 | EACH | $52.80 | $50.00 | $50.00 | |
| 72 | 78300200 | RAISED REF PVT MK REM | 128 | EACH | $8.00 | $0.0100 | $40.00 |