42BidsJan 17, 2025 to Sep 18, 2026
7Wins (low bidder)
16.7%Win rate
$10,150,838Total won
| Let date | Contract | Project | Rank | Their bid | Low bid | vs low |
|---|---|---|---|---|---|---|
| Sep 18, 2026 | 80C95 | 2025-2129-RS,SWWill · District 1 | 3 of 5 | $1,127,910 | $1,094,428Gallagher Asphalt Corporati… | +3.1% |
| Jun 12, 2026 | 62L30 | 2020-142-C&DRCook · District 1 | 5 of 6 | $16,772,291 | $13,940,412D. Construction, Inc. | +20.3% |
| Jun 12, 2026 | 66C06 | (G)RS-6&(F)RS-3Grundy · District 3 | 4 of 4 | $5,645,311 | $4,185,244D. Construction, Inc. | +34.9% |
| Apr 24, 2026 | 62V71 | FAP 0577 23 SMARTWill · District 1 | 2 of 6 | $2,846,617 | $2,821,627D. Construction, Inc. | +0.9% |
| Apr 24, 2026 | 80B05 | 2025-2018-RS,SWWill · District 1 | 4 of 5 | $1,743,861 | $1,433,491D. Construction, Inc. | +21.7% |
| Apr 24, 2026 | 80B30 | 2025-2011-RSCook · District 1 | 4 of 5 | $4,724,351 | $4,118,431K-Five Construction Corpora… | +14.7% |
| Apr 24, 2026 | 80B31 | 2025-2012-RSWill · District 1 | 1 of 4 | $2,127,428 | $2,127,428 | Won |
| Apr 24, 2026 | 80C49 | 2025-2106-RSCook · District 1 | 3 of 5 | $4,531,713 | $4,164,775K-Five Construction Corpora… | +8.8% |
| Apr 24, 2026 | 80B07 | 2025-1095-RSDupage · District 1 | 4 of 5 | $1,774,227 | $1,578,728Builders Paving, LLC | +12.4% |
| Apr 24, 2026 | 87907 | 24-00019-00-SWGrundy · District 3 | 4 of 4 | $223,387 | $163,783D. Construction, Inc. | +36.4% |
| Feb 27, 2026 | 62P01 | 2021-064-CRWill · District 1 | 3 of 4 | $5,612,641 | $4,980,727Austin Tyler Construction, … | +12.7% |
| Feb 27, 2026 | 80B13 | 2025-1086-RSWill · District 1 | 1 of 5 | $1,424,777 | $1,424,777 | Won |
| Jan 16, 2026 | 80B11 | 2025-1099-RSWill · District 1 | 3 of 3 | $1,560,604 | $1,297,699Iroquois Paving Corporation | +20.3% |
| Jan 16, 2026 | 61L81 | 25-00080-00-RSWill · District 1 | 3 of 6 | $614,124 | $596,750K-Five Construction Corpora… | +2.9% |
| Jan 16, 2026 | 61L99 | 05-00017-00-LSWill, Cook · District 1 | 4 of 6 | $2,337,303 | $1,829,797Iroquois Paving Corporation | +27.7% |
| Jan 16, 2026 | 80B14 | 2025-1087-RSWill · District 1 | 2 of 4 | $2,049,298 | $2,039,223D. Construction, Inc. | +0.5% |
| Jan 16, 2026 | 80B34 | 2025-2004-RSWill · District 1 | 3 of 6 | $1,069,082 | $977,777Gallagher Asphalt Corporati… | +9.3% |
| Jan 16, 2026 | 80B36 | 2025-1088-RSWill · District 1 | 4 of 6 | $3,427,677 | $3,250,096D. Construction, Inc. | +5.5% |
| Nov 7, 2025 | 61L73 | 21-P4015-00-BTWill · District 1 | 4 of 6 | $461,168 | $352,856D. Construction, Inc. | +30.7% |
| Nov 7, 2025 | 62R51 | FAP 0350 22 ILWill · District 1 | 3 of 4 | $3,413,216 | $3,192,530Iroquois Paving Corporation | +6.9% |
| Sep 19, 2025 | 61L72 | 24-00060-00-RSCook · District 1 | 1 of 6 | $1,092,187 | $1,092,187 | Won |
| Sep 19, 2025 | 62X01 | 2024-981-RSWill · District 1 | 5 of 6 | $8,834,677 | $7,332,294Iroquois Paving Corporation | +20.5% |
| Aug 1, 2025 | 62X86 | 2024-1047-RSWill · District 1 | 3 of 4 | $268,363 | $250,346D. Construction, Inc. | +7.2% |
| Aug 1, 2025 | 62V12 | FAU 297 23 OVERLAYCook · District 1 | 5 of 6 | $696,909 | $664,171Austin Tyler Construction, … | +4.9% |
| Aug 1, 2025 | 62X50 | 2024-1012-SW,RSWill · District 1 | 3 of 5 | $1,007,849 | $975,357Gallagher Asphalt Corporati… | +3.3% |
| Jun 13, 2025 | 62G52 | 2018-039-RSWill · District 1 | 5 of 6 | $4,293,213 | $3,382,064K-Five Construction Corpora… | +26.9% |
| Jun 13, 2025 | 62X34 | 2024-1000-RS,SWWill · District 1 | 5 of 5 | $1,648,804 | $1,353,712Iroquois Paving Corporation | +21.8% |
| Jun 13, 2025 | 87860 | 18-00042-03-RSKankakee · District 3 | 2 of 2 | $619,448 | $580,188Kankakee Valley Constructio… | +6.8% |
| Apr 25, 2025 | 62X85 | 2024-1044-RSWill · District 1 | 1 of 4 | $410,872 | $410,872 | Won |
| Apr 25, 2025 | 66A85 | (109,110)RS-3Kankakee · District 3 | 3 of 3 | $4,243,617 | $3,511,811Kankakee Valley Constructio… | +20.8% |
| Apr 25, 2025 | 66R31 | (7X-3,7R-2,6R-2)RS-1 & 92RS-3Grundy, Livingston · District 3 | 4 of 4 | $4,624,834 | $3,397,233D. Construction, Inc. | +36.1% |
| Apr 25, 2025 | 46940 | GLP 2025Grundy · District 3 | 3 of 3 | $2,258,305 | $1,889,874D. Construction, Inc. | +19.5% |
| Apr 25, 2025 | 62V35 | FAP 0112 23 SMARTWill · District 1 | 4 of 5 | $859,711 | $731,556Builders Paving, LLC | +17.5% |
| Mar 7, 2025 | 61L12 | 23-00068-00-RSCook · District 1 | 2 of 5 | $826,420 | $824,771Gallagher Asphalt Corporati… | +0.2% |
| Mar 7, 2025 | 61L15 | 21-00067-00-RSCook · District 1 | 1 of 5 | $899,917 | $899,917 | Won |
| Mar 7, 2025 | 62G55 | 2018-036-RS-SWWill · District 1 | 3 of 6 | $1,490,945 | $1,427,655Gallagher Asphalt Corporati… | +4.4% |
| Mar 7, 2025 | 61L02 | 20-00019-00-BTWill · District 1 | 3 of 6 | $499,926 | $398,891D. Construction, Inc. | +25.3% |
| Mar 7, 2025 | 61L13 | 24-00078-00-RSWill · District 1 | 1 of 7 | $392,397 | $392,397 | Won |
| Mar 7, 2025 | 62U89 | FAI 80 23 DEMOWill · District 1 | 2 of 4 | $736,294 | $498,400Scanlon Excavating & Concre… | +47.7% |
| Mar 7, 2025 | 66P51 | (92)RS-4Grundy · District 3 | 3 of 4 | $864,641 | $680,856D. Construction, Inc. | +27.0% |
| Jan 17, 2025 | 61K81 | 18-00515-01-WRWill · District 1 | 4 of 4 | $3,224,648 | $2,764,372Austin Tyler Construction, … | +16.7% |
| Jan 17, 2025 | 61J25 | 08-00044-00-WRWill · District 1 | 1 of 4 | $3,803,259 | $3,803,259 | Won |
Subcontracts on active jobs 0