Bid tab 62X86

Let Aug 1, 2025 · District 1 · Will

‹ Aug 2025 results

2024-1047-RS

Let date
Friday, August 1, 2025
Contract
62X86 · job page
District
District 1
County
Will
Highway
Limits
(3,435-Ft) Design and Standard Overlay consists of asphalt surface removal, pavement patching, (Hot Mix Asphalt) binder course, polymerized binder course and surface course, thermoplastic pavement markings. Located on Illinois Route FAU 388, I-55 Frontage Road NB in the Village of Channahon in Will County.
Classification
Asphalt surface removal, pavement patching, (Hot Mix Asphalt) binder course, polymerized binder course and sur ·
Project number

Bidders 4

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 D. Construction, Inc. Low bidder $250,346
2 Austin Tyler Construction, Inc. $257,411 +2.8%
3 P. T. Ferro Construction Co. $268,363 +7.2%
4 Gallagher Asphalt Corporation $282,101 +12.7%

Bid tab: unit prices 24 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 D. Construction…#2 Austin Tyler Co…#3 P. T. Ferro Con…#4 Gallagher Aspha…
1X2020110 GRADING & SHAP SHLDRS70UNIT $75.00 $90.00 $0.0100 $96.00
2X6700407 ENGRS FLD OFC TY A D16CAL MO $4,000.00 $4,000.00 $0.0100 $500.00
3X7200061 TEMP INFO SIGNING51.4SQ FT $30.00 $15.00 $15.00 $22.00
440600290 BIT MATLS TACK CT5,780POUND $0.0100 $0.0100 $0.0100 $0.0100
540600370 LONG JOINT SEALANT3,450FOOT $4.93 $4.15 $5.60 $5.00
640600400 MIX CR JTS FLANGEWYS15TON $0.0100 $150.00 $0.0100 $0.0100
740600982 HMA SURF REM BUTT JT50SQ YD $0.0100 $15.00 $0.0100 $0.0100
840602985 HMA BC IL-9.5 N70560TON $93.64 $81.00 $85.00 $100.00
940604062 HMA SC IL-9.5 D N70840TON $95.95 $82.00 $90.00 $100.00
1040605015 P HMA BC SMA 12.5 N80160TON $0.0100 $0.0100 $115.00 $0.0100
1144000153 HMA SURF REM 18,560SQ YD $1.73 $2.00 $3.00 $3.35
1244201717 CL D PATCH T2 650SQ YD $59.00 $93.00 $80.00 $204.80
1344201721 CL D PATCH T3 650SQ YD $59.00 $90.00 $80.00 $195.70
1444201723 CL D PATCH T4 6200SQ YD $59.00 $86.00 $85.00 $104.90
1548102100 AGG WEDGE SHLD TYPE B118TON $45.00 $75.00 $75.00 $127.00
1667100100 MOBILIZATION1L SUM $14,170.65 $12,000.00 $15,000.00 $13,500.00
1770102620 TR CONT & PROT 7015011L SUM $5,000.00 $3,000.00 $15,000.00 $4,000.00
1870300100 SHORT TERM PAVT MKING2,520FOOT $0.0100 $3.00 $0.0100 $0.0100
1970300150 SHRT TRM PAVT MK REM210SQ FT $0.0100 $5.00 $0.0100 $0.0100
2070300221 TEMP PVT MK LINE 4 - PAINT6,900FOOT $0.0100 $0.3500 $0.3500 $0.0100
2170307120 TEMP PVT MK L4 T4 TAPE630FOOT $0.0100 $1.45 $3.00 $0.0100
2278000200 THPL PVT MK LINE 46,900FOOT $0.9900 $1.10 $1.00 $1.00
2378100100 RAISED REFL PAVT MKR90EACH $53.90 $80.00 $65.00 $53.00
2478300200 RAISED REF PVT MK REM45EACH $15.00 $15.00 $0.0100 $0.0100