(G)RS-6&(F)RS-3
- Let date
- Friday, June 12, 2026
- Contract
- 66C06 · job page
- District
- District 3
- County
- Grundy
- Highway
- Limits
- Milling and resurfacing 3 3/4 inches (designed overlay), class D patching, pipe culvert end section_replacements and cleaning, detector loop replacement, pavement marking, and raised reflective pavement markers on US 6 beginning at IL 47 in Morris, and ends 0.7 miles west of Nigas Road._Approximately 6.81 miles gross length.
- Classification
- ·
- Project number
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $4,185,244 | ||
| 2 | Gallagher Asphalt Corporation | $4,526,993 | +8.2% | |
| 3 | Austin Tyler Construction, Inc. | $5,439,250 | +30.0% | |
| 4 | P. T. Ferro Construction Co. | $5,645,311 | +34.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 Gallagher Aspha… | #3 Austin Tyler Co… | #4 P. T. Ferro Con… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0325451 | NON-SHRINK GROUT | 3 | CU FT | $1,000.00 | $95.00 | $115.00 | $500.00 | |
| 2 | X0325893 | CLEAN EX END SECTION | 1 | EACH | $550.00 | $495.00 | $2,400.00 | $2,500.00 | |
| 3 | X1200207 | REM & RELAY P C SPL | 8 | FOOT | $250.00 | $435.00 | $300.00 | $250.00 | |
| 4 | X2040805 | FURNISHED EXCAV SPL | 22 | CU YD | $100.00 | $130.00 | $425.00 | $150.00 | |
| 5 | X4401198 | HMA SURF REM VAR DP | 16,471 | SQ YD | $2.50 | $6.90 | $6.50 | $5.00 | |
| 6 | X5427601 | REM & RELAY END SECT | 1 | EACH | $1,000.00 | $1,450.00 | $2,400.00 | $2,500.00 | |
| 7 | X5427602 | REMOV EX FLAR END SEC | 2 | EACH | $500.00 | $490.00 | $1,200.00 | $1,000.00 | |
| 8 | X6110073 | EXIST FIELD TILE REM | 10 | FOOT | $50.00 | $90.00 | $225.00 | $100.00 | |
| 9 | X6350204 | LINEAR DELIN PANELS 4 | 82 | EACH | $60.50 | $55.00 | $52.00 | $55.00 | |
| 10 | X6350206 | LINEAR DELIN PANELS 6 | 18 | EACH | $71.50 | $65.00 | $74.00 | $65.00 | |
| 11 | X6670106 | FURN PERM SURV MKRS | 8 | EACH | $300.00 | $240.00 | $365.00 | $1,500.00 | |
| 12 | X7200061 | TEMP INFO SIGNING | 42 | SQ FT | $30.00 | $34.00 | $23.50 | $20.00 | |
| 13 | X8820014 | TS BKPLT LVRD FPL SPL | 46 | EACH | $755.70 | $650.00 | $745.00 | $687.00 | |
| 14 | X8860100 | LOOP DET TESTING | 3 | EACH | $2,200.00 | $1,950.00 | $2,170.00 | $2,000.00 | |
| 15 | Z0010615 | CLEAN EX INLETS | 1 | EACH | $550.00 | $485.00 | $540.00 | $2,500.00 | |
| 16 | Z0012500 | CONC CURB REPAIR | 46 | FOOT | $30.00 | $170.00 | $160.00 | $150.00 | |
| 17 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 18 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 19 | 20200100 | EARTH EXCAVATION | 5 | CU YD | $200.00 | $175.00 | $425.00 | $250.00 | |
| 20 | 21400100 | GRADING & SHAP DITCH | 1,075 | FOOT | $20.00 | $15.00 | $33.50 | $28.00 | |
| 21 | 25000210 | SEEDING CL 2A | 0.15 | ACRE | $5,234.00 | $6,500.00 | $60,000.00 | $4,840.00 | |
| 22 | 25000400 | NITROGEN FERT NUTR | 14 | POUND | $3.30 | $2.90 | $19.55 | $3.00 | |
| 23 | 25000500 | PHOSPHORUS FERT NUTR | 14 | POUND | $3.30 | $2.90 | $19.55 | $3.00 | |
| 24 | 25000600 | POTASSIUM FERT NUTR | 14 | POUND | $3.30 | $2.90 | $19.55 | $3.00 | |
| 25 | 25100630 | EROSION CONTR BLANKET | 716 | SQ YD | $16.50 | $1.00 | $13.00 | $15.00 | |
| 26 | 28100707 | STONE DUMP RIP CL A4 | 245 | SQ YD | $60.00 | $95.00 | $115.00 | $140.00 | |
| 27 | 28200200 | FILTER FABRIC | 245 | SQ YD | $5.00 | $4.00 | $5.50 | $5.00 | |
| 28 | 40200800 | AGG SURF COURSE TY B | 91 | TON | $50.00 | $122.00 | $125.00 | $50.00 | |
| 29 | 40600290 | BIT MATLS TACK CT | 127,119 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 30 | 40600370 | LONG JOINT SEALANT | 45,139 | FOOT | $2.59 | $2.50 | $2.60 | $2.65 | |
| 31 | 40600400 | MIX CR JTS FLANGEWYS | 40 | TON | $0.0100 | $450.00 | $300.00 | $500.00 | |
| 32 | 40600405 | MATL TRANSFER DEVICE | 27,967 | TON | $2.50 | $12.00 | $2.80 | $4.00 | |
| 33 | 40600990 | TEMPORARY RAMP | 890 | SQ YD | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 34 | 40603085 | HMA BC IL-19.0 N70 | 16,781 | TON | $65.00 | $67.00 | $85.50 | $85.00 | |
| 35 | 40604062 | HMA SC IL-9.5 D N70 | 8,046 | TON | $69.50 | $73.00 | $92.00 | $89.00 | |
| 36 | 40604162 | P HMA SC IL-9.5 D N70 | 3,140 | TON | $84.00 | $92.00 | $103.00 | $95.00 | |
| 37 | 40800050 | INCIDENTAL HMA SURF | 2,395 | TON | $105.00 | $111.00 | $110.00 | $115.00 | |
| 38 | 44000164 | HMA SURF REM 3 3/4 | 133,178 | SQ YD | $3.00 | $3.35 | $5.25 | $5.00 | |
| 39 | 44201827 | CL D PATCH T2 15 | 574 | SQ YD | $150.00 | $164.00 | $200.00 | $150.00 | |
| 40 | 44201831 | CL D PATCH T3 15 | 120 | SQ YD | $150.00 | $159.00 | $200.00 | $185.00 | |
| 41 | 44201833 | CL D PATCH T4 15 | 1,035 | SQ YD | $150.00 | $148.00 | $200.00 | $150.00 | |
| 42 | 48102100 | AGG WEDGE SHLD TYPE B | 2,953 | TON | $31.00 | $25.70 | $48.00 | $27.00 | |
| 43 | 50105220 | PIPE CULVERT REMOV | 24 | FOOT | $20.00 | $58.00 | $40.00 | $50.00 | |
| 44 | 542A0229 | P CUL CL A 1 24 | 24 | FOOT | $100.00 | $440.00 | $160.00 | $150.00 | |
| 45 | 54213669 | PRC FLAR END SEC 24 | 2 | EACH | $2,000.00 | $2,950.00 | $2,050.00 | $2,500.00 | |
| 46 | 60100915 | PIPE DRAINS 6 | 10 | FOOT | $100.00 | $150.00 | $240.00 | $150.00 | |
| 47 | 60905305 | BOX CUL TO BE CLEANED | 317 | FOOT | $33.00 | $29.00 | $130.00 | $220.00 | |
| 48 | 60920024 | PIPE CULV CLEANED 24 | 108 | FOOT | $27.50 | $25.00 | $54.00 | $50.00 | |
| 49 | 60920030 | PIPE CULV CLEANED 30 | 50 | FOOT | $22.00 | $20.00 | $70.00 | $50.00 | |
| 50 | 63500105 | DELINEATORS | 36 | EACH | $104.50 | $80.00 | $58.00 | $95.00 | |
| 51 | 66900200 | NON SPL WASTE DISPOSL | 154 | CU YD | $85.00 | $50.00 | $120.00 | $90.00 | |
| 52 | 66900530 | SOIL DISPOSAL ANALY | 4 | EACH | $1,650.00 | $850.00 | $950.00 | $875.00 | |
| 53 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,250.00 | $5,500.00 | $6,300.00 | $5,800.00 | |
| 54 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,250.00 | $450.00 | $545.00 | $500.00 | |
| 55 | 66901006 | REG SUB MON | 5 | CAL DA | $1,000.00 | $650.00 | $775.00 | $715.00 | |
| 56 | 67000400 | ENGR FIELD OFFICE A | 4 | CAL MO | $4,000.00 | $2,900.00 | $3,500.00 | $5,000.00 | |
| 57 | 67100100 | MOBILIZATION | 1 | L SUM | $157,000.00 | $247,777.00 | $325,000.00 | $300,000.00 | |
| 58 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $0.0100 | $49,777.00 | $8,500.00 | $500,000.00 | |
| 59 | 70100455 | TRAF CONT-PROT 701206 | 1 | L SUM | $0.0100 | $277.00 | $8,500.00 | $100.00 | |
| 60 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $173,275.00 | $7,977.00 | $8,500.00 | $100.00 | |
| 61 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $5,000.00 | $999.00 | $6,500.00 | $1.00 | |
| 62 | 70300100 | SHORT TERM PAVT MKING | 54,408 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 63 | 70300150 | SHRT TRM PAVT MK REM | 18,136 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 64 | 72000100 | SIGN PANEL T1 | 138 | SQ FT | $55.00 | $39.00 | $38.00 | $50.00 | |
| 65 | 72400310 | REMOV SIGN PANEL T1 | 138 | SQ FT | $27.50 | $19.50 | $8.60 | $25.00 | |
| 66 | 78004600 | PREF PL PM TD STD LTR/SYM | 1,513 | SQ FT | $51.98 | $9.50 | $32.50 | $30.00 | |
| 67 | 78004640 | PREF PL PM TD STD L 8 | 8,894 | FOOT | $8.09 | $7.00 | $9.75 | $9.00 | |
| 68 | 78004720 | PREF PL PM TD STD L24 | 608 | FOOT | $23.10 | $18.00 | $32.50 | $30.00 | |
| 69 | 78009004 | MOD URETH PM LINE 4 | 223,162 | FOOT | $0.5800 | $0.6500 | $0.6400 | $0.5900 | |
| 70 | 78009006 | MOD URETH PM LINE 6 | 14,362 | FOOT | $1.16 | $0.9000 | $1.05 | $1.00 | |
| 71 | 78009012 | MOD URETH PM LINE 12 | 4,345 | FOOT | $2.89 | $2.50 | $4.00 | $3.75 | |
| 72 | 78011000 | GRV RCSD PM LTR & SYM | 1,513 | SQ FT | $9.24 | $2.70 | $5.40 | $5.00 | |
| 73 | 78011045 | GRV RCSD PVT MRKG 9 | 8,894 | FOOT | $1.74 | $1.30 | $2.15 | $2.00 | |
| 74 | 78011125 | GRV RCSD PVT MRKG 25 | 608 | FOOT | $9.24 | $3.30 | $5.40 | $5.00 | |
| 75 | 78100100 | RAISED REFL PAVT MKR | 863 | EACH | $46.20 | $34.00 | $47.75 | $55.00 | |
| 76 | 78200020 | CURB REFLECTORS | 42 | EACH | $46.20 | $23.00 | $16.25 | $15.00 | |
| 77 | 78300200 | RAISED REF PVT MK REM | 863 | EACH | $8.00 | $0.0100 | $27.75 | $0.0100 | |
| 78 | 88600100 | DET LOOP T1 | 2,066 | FOOT | $38.50 | $34.00 | $38.00 | $35.00 |