24-00019-00-SW
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $163,783 | ||
| 2 | Davis Concrete Construction Co. | $175,879 | +7.4% | |
| 3 | Gallagher Asphalt Corporation | $180,778 | +10.4% | |
| 4 | P. T. Ferro Construction Co. | $223,387 | +36.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 Davis Concrete … | #3 Gallagher Aspha… | #4 P. T. Ferro Con… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $10,000.00 | $2,000.00 | $3,780.00 | $10,000.00 | |
| 2 | 28000510 | INLET FILTERS | 11 | EACH | $300.00 | $10.00 | $200.00 | $0.0100 | |
| 3 | 35101600 | AGG BASE CSE B 4 | 1,143 | SQ YD | $7.25 | $0.1000 | $15.00 | $12.00 | |
| 4 | 42400200 | PC CONC SIDEWALK 5 | 9,149 | SQ FT | $9.25 | $14.00 | $10.75 | $15.00 | |
| 5 | 42400300 | PC CONC SIDEWALK 6 | 1,134 | SQ FT | $11.50 | $15.00 | $12.00 | $16.50 | |
| 6 | 42400800 | DETECTABLE WARNINGS | 295 | SQ FT | $30.00 | $25.00 | $22.00 | $20.00 | |
| 7 | 44000200 | DRIVE PAVEMENT REM | 131 | SQ YD | $14.00 | $20.00 | $31.25 | $25.00 | |
| 8 | 44000600 | SIDEWALK REM | 1,494 | SQ FT | $3.50 | $0.1000 | $3.60 | $2.50 | |
| 9 | 67100100 | MOBILIZATION | 1 | L SUM | $9,800.00 | $6,000.00 | $10,558.87 | $12,000.00 | |
| 10 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $0.0100 | $100.00 | $2,500.00 | $1.00 | |
| 11 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $10,000.00 | $3,500.00 | $7,500.00 | $10,000.00 | |
| 12 | 78000400 | THPL PVT MK LINE 6 | 747 | FOOT | $2.80 | $2.80 | $3.00 | $2.80 | |
| 13 | 78000600 | THPL PVT MK LINE 12 | 1,109 | FOOT | $4.80 | $4.80 | $5.00 | $4.80 | |
| 14 | 78000650 | THPL PVT MK LINE 24 | 132 | FOOT | $10.60 | $10.60 | $10.50 | $10.60 |