2024-1012-SW,RS
- Let date
- Friday, August 1, 2025
- Contract
- 62X50 · job page
- District
- District 1
- County
- Will
- Highway
- Limits
- (2,067-Ft) Designed Overlay, Curb Ramps improvements (ADA), Sidewalk Replacement consists of milling existing asphalt surface, pavement patching, HMA surface course and HMA binder course, sidewalk removal and replacement, drainage structures adjustments and cleaning, replacement of curb and gutter, longitudinal joint sealing, pavement markings, curb ramps for sidewalks, raised reflective pavement markers, Location: IL 53 (Baltimore Street), from Kankakee Street to West of Forked Creek within the
- Classification
- Milling existing asphalt surface, pavement patching, HMA surface course and HMA binder course, sidewalk remova ·
- Project number
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Gallagher Asphalt Corporation Low bidder | $975,357 | ||
| 2 | D. Construction, Inc. | $977,009 | +0.2% | |
| 3 | P. T. Ferro Construction Co. | $1,007,849 | +3.3% | |
| 4 | Austin Tyler Construction, Inc. | $1,067,594 | +9.5% | |
| 5 | M & J Underground Inc. | $1,619,466 | +66.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Gallagher Aspha… | #2 D. Construction… | #3 P. T. Ferro Con… | #4 Austin Tyler Co… | #5 M & J Undergrou… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X4060995 | TEMPORARY RAMP SPL | 80 | SQ YD | $38.00 | $0.0100 | $55.00 | $0.0100 | $45.00 | |
| 2 | X4240430 | PC CONC SIDEWALK 5 SP | 13,985 | SQ FT | $11.40 | $13.00 | $12.50 | $9.50 | $30.00 | |
| 3 | X4240460 | PC CONC SIDEWALK 8 SP | 1,540 | SQ FT | $17.70 | $16.00 | $19.00 | $14.50 | $32.00 | |
| 4 | X5537800 | SS CLEANED 12 | 45 | FOOT | $5.50 | $55.00 | $50.00 | $50.00 | $13.00 | |
| 5 | X6030310 | FR & LIDS ADJUST SPL | 3 | EACH | $1,400.00 | $1,000.00 | $1,200.00 | $1,200.00 | $2,500.00 | |
| 6 | X6060075 | COMB CC&G TM2.12 SPL | 1,110 | FOOT | $36.50 | $34.00 | $36.50 | $35.00 | $47.00 | |
| 7 | X6060086 | COMB CC&G TM4.12 SPL | 2,530 | FOOT | $36.50 | $35.00 | $38.00 | $40.00 | $49.00 | |
| 8 | X6700407 | ENGRS FLD OFC TY A D1 | 12 | CAL MO | $500.00 | $4,000.00 | $0.0100 | $3,000.00 | $6,000.00 | |
| 9 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $5,500.00 | $12,000.00 | $15,000.00 | $18,000.00 | $19,000.00 | |
| 10 | Z0018500 | DRAINAGE STR CLEANED | 3 | EACH | $1,000.00 | $2,200.00 | $2,000.00 | $350.00 | $407.00 | |
| 11 | Z0030850 | TEMP INFO SIGNING | 104 | SQ FT | $20.00 | $25.00 | $35.00 | $50.00 | $25.00 | |
| 12 | 20200100 | EARTH EXCAVATION | 200 | CU YD | $100.00 | $50.00 | $100.00 | $25.00 | $100.00 | |
| 13 | 20800150 | TRENCH BACKFILL | 15 | CU YD | $70.00 | $65.00 | $80.00 | $60.00 | $110.00 | |
| 14 | 21101615 | TOPSOIL F & P 4 | 270 | SQ YD | $20.00 | $7.70 | $7.00 | $17.00 | $7.00 | |
| 15 | 25200110 | SODDING SALT TOLERANT | 270 | SQ YD | $20.00 | $33.00 | $30.00 | $37.00 | $79.00 | |
| 16 | 35101500 | AGG BASE CSE B | 16 | CU YD | $46.00 | $60.00 | $115.00 | $165.00 | $120.00 | |
| 17 | 35101800 | AGG BASE CSE B 6 | 640 | SQ YD | $17.50 | $10.50 | $18.00 | $28.00 | $25.00 | |
| 18 | 35501308 | HMA BASE CSE 6 | 11 | SQ YD | $93.00 | $70.00 | $90.00 | $70.00 | $290.00 | |
| 19 | 35501316 | HMA BASE CSE 8 | 85 | SQ YD | $111.00 | $60.00 | $115.00 | $87.00 | $111.00 | |
| 20 | 40600290 | BIT MATLS TACK CT | 5,085 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 21 | 40600370 | LONG JOINT SEALANT | 2,070 | FOOT | $6.50 | $6.47 | $8.00 | $5.70 | $8.00 | |
| 22 | 40600400 | MIX CR JTS FLANGEWYS | 12 | TON | $100.00 | $300.00 | $0.0100 | $285.00 | $611.00 | |
| 23 | 40600982 | HMA SURF REM BUTT JT | 197 | SQ YD | $17.50 | $0.0100 | $0.0100 | $20.00 | $0.0100 | |
| 24 | 40602985 | HMA BC IL-9.5 N70 | 835 | TON | $107.00 | $80.00 | $98.00 | $83.00 | $145.00 | |
| 25 | 40604060 | HMA SC IL-9.5 D N50 | 5 | TON | $430.00 | $130.00 | $1,000.00 | $190.00 | $1,132.00 | |
| 26 | 40604172 | P HMA SC IL-9.5 E N70 | 735 | TON | $127.00 | $103.00 | $125.00 | $110.00 | $167.00 | |
| 27 | 42001300 | PROTECTIVE COAT | 2,390 | SQ YD | $1.00 | $1.00 | $0.0100 | $5.00 | $2.00 | |
| 28 | 42400800 | DETECTABLE WARNINGS | 350 | SQ FT | $23.00 | $40.00 | $20.00 | $40.00 | $30.00 | |
| 29 | 44000166 | HMA SURF REM 4 1/4 | 7,420 | SQ YD | $5.80 | $3.75 | $7.00 | $6.00 | $7.00 | |
| 30 | 44000200 | DRIVE PAVEMENT REM | 95 | SQ YD | $41.00 | $15.00 | $34.00 | $22.00 | $30.00 | |
| 31 | 44000300 | CURB REM | 3,190 | FOOT | $12.20 | $8.00 | $16.50 | $19.00 | $16.00 | |
| 32 | 44000600 | SIDEWALK REM | 15,525 | SQ FT | $2.50 | $3.00 | $2.50 | $3.50 | $5.00 | |
| 33 | 44201753 | CL D PATCH T2 9 | 40 | SQ YD | $180.00 | $90.00 | $125.00 | $130.00 | $134.00 | |
| 34 | 44201757 | CL D PATCH T3 9 | 120 | SQ YD | $130.00 | $90.00 | $110.00 | $125.00 | $134.00 | |
| 35 | 44201759 | CL D PATCH T4 9 | 270 | SQ YD | $120.00 | $90.00 | $88.00 | $110.00 | $134.00 | |
| 36 | 550A0050 | STORM SEW CL A 1 12 | 35 | FOOT | $148.00 | $200.00 | $160.00 | $82.00 | $160.00 | |
| 37 | 60206905 | CB TC T1F OL | 1 | EACH | $3,400.00 | $2,200.00 | $4,000.00 | $2,650.00 | $3,400.00 | |
| 38 | 60218400 | MAN TA 4 DIA T1F CL | 1 | EACH | $6,100.00 | $4,200.00 | $5,000.00 | $2,650.00 | $4,400.00 | |
| 39 | 60255500 | MAN ADJUST | 3 | EACH | $680.00 | $850.00 | $600.00 | $400.00 | $690.00 | |
| 40 | 60300105 | FR & GRATES ADJUST | 21 | EACH | $410.00 | $650.00 | $465.00 | $400.00 | $690.00 | |
| 41 | 66900200 | NON SPL WASTE DISPOSL | 200 | CU YD | $90.00 | $70.00 | $85.00 | $200.00 | $181.00 | |
| 42 | 66900530 | SOIL DISPOSAL ANALY | 3 | EACH | $1,800.00 | $1,650.00 | $1,785.00 | $1,785.00 | $1,600.00 | |
| 43 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,400.00 | $2,250.00 | $3,400.00 | $3,400.00 | $4,300.00 | |
| 44 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $500.00 | $2,250.00 | $500.00 | $500.00 | $1,700.00 | |
| 45 | 66901006 | REG SUB MON | 5 | CAL DA | $900.00 | $900.00 | $900.00 | $900.00 | $1,500.00 | |
| 46 | 67100100 | MOBILIZATION | 1 | L SUM | $58,000.00 | $56,200.00 | $55,000.00 | $56,000.00 | $25,000.00 | |
| 47 | 70102621 | TR CONT & PROT 701501 | 1 | EACH | $51,200.00 | $87,850.00 | $49,000.00 | $6,000.00 | $18,000.00 | |
| 48 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $100.00 | $0.0100 | $1,500.00 | $21,000.00 | $112.00 | |
| 49 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $100.00 | $0.0100 | $1,500.00 | $3,000.00 | $112.00 | |
| 50 | 70300100 | SHORT TERM PAVT MKING | 22,500 | FOOT | $0.0100 | $0.0100 | $0.0100 | $2.00 | $2.25 | |
| 51 | 70300150 | SHRT TRM PAVT MK REM | 1,875 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $2.50 | $3.00 | |
| 52 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 19,245 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.5000 | $1.25 | |
| 53 | 70300241 | TEMP PVT MK LINE 6 - PAINT | 1,815 | FOOT | $0.0100 | $0.0100 | $0.0100 | $1.25 | $1.50 | |
| 54 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 420 | FOOT | $0.0100 | $0.0100 | $0.0100 | $3.00 | $3.50 | |
| 55 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 195 | FOOT | $0.0100 | $0.0100 | $0.0100 | $6.00 | $6.75 | |
| 56 | 70307120 | TEMP PVT MK L4 T4 TAPE | 3,650 | FOOT | $1.40 | $0.0100 | $2.35 | $2.00 | $2.50 | |
| 57 | 78000200 | THPL PVT MK LINE 4 | 6,415 | FOOT | $1.00 | $1.09 | $0.9900 | $1.00 | $1.25 | |
| 58 | 78000400 | THPL PVT MK LINE 6 | 605 | FOOT | $1.45 | $1.60 | $1.45 | $4.00 | $4.50 | |
| 59 | 78000600 | THPL PVT MK LINE 12 | 140 | FOOT | $3.00 | $3.30 | $3.00 | $8.00 | $9.00 | |
| 60 | 78000650 | THPL PVT MK LINE 24 | 65 | FOOT | $6.00 | $6.60 | $6.00 | $16.00 | $18.00 | |
| 61 | 78100100 | RAISED REFL PAVT MKR | 100 | EACH | $50.00 | $55.00 | $50.00 | $80.00 | $150.00 | |
| 62 | 78300200 | RAISED REF PVT MK REM | 100 | EACH | $0.0100 | $10.00 | $0.0100 | $15.00 | $120.00 |