$11.32Avg low bid / SQ FT
$12.97Avg of all bids
—Avg engineer's estimate
34Jobs · 185,423.5 SQ FT
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 16 | 55,931.5 | $12.93 | $14.40 |
| 2025 | 18 | 129,492 | $10.63 | $12.41 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jul 31, 2026 | 61K19 | CookDistrict 1 | 2,087 SQ FT | $13.83 | R. W. Dunteman Company |
| Jun 12, 2026 | 62U72 | MchenryDistrict 1 | 923 SQ FT | $38.00 | Martam Construction Incorporated |
| Apr 24, 2026 | 80B27 | CookDistrict 1 | 217 SQ FT | $13.00 | Plote Construction, Inc. |
| Apr 24, 2026 | 80B39 | CookDistrict 1 | 174.5 SQ FT | $16.79 | K-Five Construction Corporation |
| Apr 24, 2026 | 80C85 | MchenryDistrict 1 | 2,503 SQ FT | $21.25 | Berger Excavating Contractors, Inc. d/b/a Berger Contractors, Inc. |
| Apr 24, 2026 | 61M37 | DupageDistrict 1 | 18,825 SQ FT | $8.40 | R. W. Dunteman Company |
| Feb 27, 2026 | 61M32 | CookDistrict 1 | 6,445 SQ FT | $8.75 | A Lamp Concrete Contractors, Inc. |
| Feb 27, 2026 | 61L39 | KaneDistrict 1 | 3,702 SQ FT | $10.10 | Geneva Construction Company LLC. |
| Feb 27, 2026 | 61M31 | CookDistrict 1 | 8,307 SQ FT | $9.35 | A Lamp Concrete Contractors, Inc. |
| Feb 27, 2026 | 62X88 | CookDistrict 1 | 87 SQ FT | $20.00 | Peter Baker & Son Co. |
| Feb 27, 2026 | 85769 | WinnebagoDistrict 2 | 8,575 SQ FT | $20.00 | N-Trak Group LLC |
| Feb 27, 2026 | 80B08 | DupageDistrict 1 | 13 SQ FT | $82.00 | Builders Paving, LLC |
| Jan 16, 2026 | 61L94 | MchenryDistrict 1 | 1,803 SQ FT | $11.43 | Geske and Sons, Inc. |
| Jan 16, 2026 | 61M09 | CookDistrict 1 | 154 SQ FT | $27.00 | Martam Construction Incorporated |
| Jan 16, 2026 | 85787 | BooneDistrict 2 | 1,367 SQ FT | $17.00 | Fischer Excavating, Inc. |
| Jan 16, 2026 | 97876 | MadisonDistrict 8 | 749 SQ FT | $64.71 | Hank's Excavating & Landscaping, Inc. |
| Sep 19, 2025 | 62Y13 | CookDistrict 1 | 350 SQ FT | $32.00 | Martam Construction Incorporated |
| Aug 1, 2025 | 62X50 | WillDistrict 1 | 13,985 SQ FT | $11.40 | Gallagher Asphalt Corporation |
| Aug 1, 2025 | 61L47 | DupageDistrict 1 | 3,349 SQ FT | $14.00 | Everlast Blacktop Inc. |
| Jun 13, 2025 | 78A25 | JohnsonDistrict 9 | 2,797 SQ FT | $40.00 | Samron Midwest Contracting, Inc. |
| Jun 13, 2025 | 62V14 | CookDistrict 1 | 30 SQ FT | $18.00 | MAT Construction Leasing, Inc. |
| Jun 13, 2025 | 61L34 | CookDistrict 1 | 2,450 SQ FT | $15.40 | Alliance Contractors, Inc. |
| Apr 25, 2025 | 61L32 | LakeDistrict 1 | 8,446 SQ FT | $11.00 | Peter Baker & Son Co. |
| Apr 25, 2025 | 61L41 | CookDistrict 1 | 225 SQ FT | $20.00 | Triggi Construction, Inc. |
| Apr 25, 2025 | 61L29 | DupageDistrict 1 | 7,400 SQ FT | $8.75 | Builders Paving, LLC |
| Mar 7, 2025 | 61L05 | LakeDistrict 1 | 11,094 SQ FT | $12.00 | D'Land Construction, LLC |
| Mar 7, 2025 | 61L23 | CookDistrict 1 | 30,045 SQ FT | $8.35 | A Lamp Concrete Contractors, Inc. |
| Mar 7, 2025 | 87875 | DekalbDistrict 3 | 2,356 SQ FT | $12.00 | Fischer Excavating, Inc. |
| Jan 17, 2025 | 61K86 | CookDistrict 1 | 750 SQ FT | $33.90 | Schroeder Asphalt Services, Inc. |
| Jan 17, 2025 | 61K68 | KaneDistrict 1 | 3,259 SQ FT | $19.24 | Martam Construction Incorporated |
| Jan 17, 2025 | 61K98 | KaneDistrict 1 | 15,155 SQ FT | $6.50 | Triggi Construction, Inc. |
| Jan 17, 2025 | 61L07 | CookDistrict 1 | 1,417 SQ FT | $17.00 | Plote Construction, Inc. |
| Jan 17, 2025 | 61L08 | CookDistrict 1 | 9,604 SQ FT | $11.00 | Plote Construction, Inc. |
| Jan 17, 2025 | 97853 | MadisonDistrict 8 | 16,780 SQ FT | $7.00 | Keller Construction, Inc. |