((125)CR-2588,CR-2589)
- Let date
- Friday, June 12, 2026
- Contract
- 66M92 · job page
- District
- District 3
- County
- Livingston
- Highway
- Limits
- Culvert replacements (SN 053-2588 and -2589) over an Indian Creek Tributary 1 miles north of Ford County Line and 0.2 mile north of N200N Rd in Strawn.
- Classification
- ·
- Project number
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Iroquois Paving Corporation Low bidder | $705,367 | ||
| 2 | Riber Construction, Inc. | $793,348 | +12.5% | |
| 3 | Phoenix Corporation of the Quad Cities | $889,101 | +26.0% | |
| 4 | Cross Construction, Inc. | $999,324 | +41.7% | |
| 5 | Tobey's Construction & Cartage, Inc. | $1,017,028 | +44.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Iroquois Paving… | #2 Riber Construct… | #3 Phoenix Corpora… | #4 Cross Construct… | #5 Tobey's Constru… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X2130010 | EXPLOR TRENCH SPL | 400 | FOOT | $15.50 | $0.0100 | $18.00 | $22.00 | $25.00 | |
| 2 | X5810103 | MEMB WTRPRF SYS B STR | 113 | SQ YD | $70.00 | $37.00 | $42.00 | $30.00 | $49.00 | |
| 3 | X7200061 | TEMP INFO SIGNING | 84 | SQ FT | $31.50 | $30.00 | $45.00 | $45.00 | $30.00 | |
| 4 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $8,450.00 | $15,000.00 | $10,000.00 | $12,000.00 | $8,500.00 | |
| 5 | 20200100 | EARTH EXCAVATION | 516 | CU YD | $43.50 | $53.00 | $58.00 | $82.00 | $62.00 | |
| 6 | 20700220 | POROUS GRAN EMBANK | 214 | CU YD | $100.00 | $58.00 | $105.00 | $90.00 | $105.00 | |
| 7 | 25000210 | SEEDING CL 2A | 1 | ACRE | $2,325.00 | $2,200.00 | $6,000.00 | $3,300.00 | $2,200.00 | |
| 8 | 25000400 | NITROGEN FERT NUTR | 83 | POUND | $7.35 | $7.00 | $6.00 | $3.00 | $7.00 | |
| 9 | 25000500 | PHOSPHORUS FERT NUTR | 83 | POUND | $7.35 | $7.00 | $6.00 | $3.00 | $7.00 | |
| 10 | 25000600 | POTASSIUM FERT NUTR | 83 | POUND | $7.35 | $7.00 | $6.00 | $3.00 | $7.00 | |
| 11 | 25100630 | EROSION CONTR BLANKET | 4,316 | SQ YD | $1.75 | $1.65 | $3.00 | $5.00 | $1.65 | |
| 12 | 28000250 | TEMP EROS CONTR SEED | 268 | POUND | $0.0100 | $10.00 | $5.00 | $6.00 | $10.00 | |
| 13 | 28000305 | TEMP DITCH CHECKS | 80 | FOOT | $14.75 | $14.00 | $21.00 | $50.00 | $14.00 | |
| 14 | 28000400 | PERIMETER EROS BAR | 947 | FOOT | $2.20 | $1.00 | $6.25 | $6.75 | $2.10 | |
| 15 | 28000500 | INLET & PIPE PROTECT | 4 | EACH | $150.00 | $140.00 | $300.00 | $375.00 | $140.00 | |
| 16 | 31101200 | SUB GRAN MAT B 4 | 162 | SQ YD | $24.85 | $9.00 | $36.00 | $17.00 | $40.25 | |
| 17 | 35501316 | HMA BASE CSE 8 | 139 | SQ YD | $79.00 | $79.00 | $79.00 | $175.00 | $79.00 | |
| 18 | 40600290 | BIT MATLS TACK CT | 1,942 | POUND | $1.95 | $1.95 | $1.95 | $1.20 | $1.95 | |
| 19 | 40600990 | TEMPORARY RAMP | 80 | SQ YD | $0.0100 | $0.0100 | $0.0100 | $75.00 | $0.0100 | |
| 20 | 40602978 | HMA BC IL-9.5 N50 | 494 | TON | $128.00 | $128.00 | $128.00 | $163.00 | $128.00 | |
| 21 | 40604050 | HMA SC IL-9.5 C N50 | 202 | TON | $130.00 | $130.00 | $130.00 | $180.00 | $130.00 | |
| 22 | 44000100 | PAVEMENT REM | 140 | SQ YD | $83.60 | $85.00 | $38.00 | $60.00 | $45.00 | |
| 23 | 44000155 | HMA SURF REM 1 1/2 | 1,464 | SQ YD | $6.95 | $6.95 | $6.95 | $19.00 | $6.95 | |
| 24 | 44004250 | PAVED SHLD REMOVAL | 600 | SQ YD | $21.50 | $21.50 | $21.50 | $15.00 | $21.50 | |
| 25 | 48101500 | AGGREGATE SHLDS B 6 | 402 | SQ YD | $21.75 | $40.00 | $31.00 | $23.00 | $41.50 | |
| 26 | 48203029 | HMA SHOULDERS 8 | 800 | SQ YD | $60.00 | $60.00 | $60.00 | $70.00 | $73.75 | |
| 27 | 50100100 | REM EXIST STRUCT | 2 | EACH | $6,650.00 | $26,535.00 | $24,350.00 | $7,500.00 | $28,000.00 | |
| 28 | 51500100 | NAME PLATES | 2 | EACH | $1,420.00 | $500.00 | $1,875.00 | $1,200.00 | $1,045.00 | |
| 29 | 52200020 | TEMP SOIL RETEN SYSTM | 115 | SQ FT | $162.50 | $400.00 | $180.00 | $335.00 | $440.00 | |
| 30 | 54001001 | BOX CUL END SEC C1 | 2 | EACH | $16,175.00 | $16,000.00 | $21,800.00 | $15,000.00 | $30,850.00 | |
| 31 | 54001002 | BOX CUL END SEC C2 | 2 | EACH | $12,975.00 | $14,000.00 | $18,050.00 | $17,800.00 | $28,550.00 | |
| 32 | 54010604 | PCBC 6X4 | 54 | FOOT | $950.00 | $1,200.00 | $1,200.00 | $980.00 | $1,425.00 | |
| 33 | 54010802 | PCBC 8X2 | 38 | FOOT | $972.00 | $1,500.00 | $1,240.00 | $1,200.00 | $1,795.00 | |
| 34 | 54260315 | TRVRS PIPE GRT CON ES | 71 | FOOT | $158.00 | $175.00 | $189.00 | $300.00 | $160.00 | |
| 35 | 59100100 | GEOCOMPOSITE WALL DR | 113 | SQ YD | $38.00 | $20.00 | $35.00 | $25.00 | $45.00 | |
| 36 | 61100605 | MISC CONCRETE | 20 | CU YD | $536.00 | $0.0100 | $400.00 | $335.00 | $915.00 | |
| 37 | 61101013 | STORM SEW PROT A 12 | 100 | FOOT | $66.50 | $0.0100 | $98.00 | $105.00 | $102.00 | |
| 38 | 61101017 | STORM SEW PROT A 15 | 100 | FOOT | $76.50 | $0.0100 | $108.00 | $103.00 | $112.00 | |
| 39 | 61133100 | FLD TILE JUN VAULT 2D | 4 | EACH | $590.00 | $0.0100 | $2,325.00 | $9,500.00 | $1,500.00 | |
| 40 | 61140200 | STORM SEWER SPEC 12 | 100 | FOOT | $45.00 | $0.0100 | $67.00 | $110.00 | $82.00 | |
| 41 | 61140400 | STORM SEWER SPEC 15 | 100 | FOOT | $52.00 | $0.0100 | $72.00 | $118.00 | $88.00 | |
| 42 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $2,000.00 | $2,000.00 | $2,600.00 | $3,300.00 | $3,950.00 | |
| 43 | 67100100 | MOBILIZATION | 1 | L SUM | $21,000.00 | $47,600.00 | $73,000.00 | $30,000.00 | $60,000.00 | |
| 44 | 70100405 | TRAF CONT-PROT 701321 | 2 | EACH | $16,750.00 | $12,395.00 | $16,500.00 | $18,000.00 | $12,395.00 | |
| 45 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $100.00 | $100.00 | $750.00 | $12,000.00 | $100.00 | |
| 46 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $100.00 | $100.00 | $750.00 | $12,000.00 | $100.00 | |
| 47 | 70106500 | TEMP BR TRAF SIGNALS | 2 | EACH | $12,400.00 | $11,775.00 | $16,500.00 | $6,500.00 | $15,000.00 | |
| 48 | 70106700 | TEMP RUMBLE STRIPS | 24 | EACH | $1,265.00 | $1,200.00 | $1,100.00 | $1,500.00 | $1,200.00 | |
| 49 | 70300100 | SHORT TERM PAVT MKING | 424 | FOOT | $0.0100 | $2.00 | $2.50 | $2.00 | $2.50 | |
| 50 | 70300150 | SHRT TRM PAVT MK REM | 142 | SQ FT | $0.0100 | $2.00 | $7.75 | $14.00 | $30.00 | |
| 51 | 70307120 | TEMP PVT MK L4 T4 TAPE | 4,850 | FOOT | $0.0100 | $1.30 | $1.25 | $1.00 | $1.30 | |
| 52 | 70307210 | TEMP PVT MK L24 T4 TAPE | 96 | FOOT | $0.0100 | $7.80 | $12.00 | $8.00 | $7.80 | |
| 53 | 70400100 | TEMP CONC BARRIER | 350 | FOOT | $52.65 | $50.00 | $41.25 | $110.00 | $47.00 | |
| 54 | 70400125 | PIN TEMP CONC BARRIER | 336 | EACH | $0.0100 | $20.00 | $20.00 | $61.00 | $33.00 | |
| 55 | 70400200 | REL TEMP CONC BARRIER | 350 | FOOT | $7.00 | $20.00 | $13.50 | $40.00 | $12.75 | |
| 56 | 70600250 | IMP ATTN TEMP NRD TL3 | 4 | EACH | $4,225.00 | $4,000.00 | $2,950.00 | $2,200.00 | $5,150.00 | |
| 57 | 70600350 | IMP ATTN REL NRD TL3 | 4 | EACH | $1,325.00 | $1,250.00 | $1,100.00 | $1,700.00 | $850.00 | |
| 58 | 72400735 | REM & REL SIGN PANEL T1 | 10 | SQ FT | $52.75 | $50.00 | $12.50 | $67.00 | $50.00 | |
| 59 | 72400740 | REM & REL SIGN PANEL T2 | 10 | SQ FT | $58.00 | $55.00 | $80.00 | $67.00 | $55.00 | |
| 60 | 73000100 | WOOD SIN SUPPORT | 47 | FOOT | $26.50 | $25.00 | $27.50 | $35.00 | $25.00 | |
| 61 | 78001110 | PAINT PVT MK LINE 4 | 3,600 | FOOT | $3.00 | $1.23 | $1.23 | $1.30 | $1.23 | |
| 62 | 78001130 | PAINT PVT MK LINE 6 | 113 | FOOT | $4.00 | $1.85 | $1.85 | $2.00 | $1.85 | |
| 63 | 78100100 | RAISED REFL PAVT MKR | 11 | EACH | $475.00 | $451.00 | $451.00 | $475.00 | $451.00 | |
| 64 | 78300200 | RAISED REF PVT MK REM | 11 | EACH | $0.0100 | $10.00 | $30.00 | $115.00 | $25.00 | |
| 65 | 78300201 | PVT MKG REM GRINDING | 100 | SQ FT | $31.50 | $49.00 | $14.00 | $52.00 | $30.00 |