25-00038-00-RS
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $692,262 | ||
| 2 | Builders Paving, LLC | $703,188 | +1.6% | |
| 3 | Geneva Construction Company LLC. | $765,897 | +10.6% | |
| 4 | Curran Contracting Company | $874,971 | +26.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 Builders Paving… | #3 Geneva Construc… | #4 Curran Contract… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | K1004595 | PRUN SAFETY/EQUIP CLR | 1 | L SUM | $6,270.00 | $3,500.00 | $3,500.00 | $5,700.00 | |
| 2 | X4400196 | HMA SURF REM SPL | 94 | SQ YD | $20.00 | $15.00 | $15.00 | $20.00 | |
| 3 | X7010238 | CHANGE MESSAGE SN SPL | 12 | CAL MO | $1,500.00 | $1,200.00 | $900.00 | $1,200.00 | |
| 4 | X7200061 | TEMP INFO SIGNING | 52 | SQ FT | $30.00 | $20.00 | $18.00 | $20.00 | |
| 5 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $2,500.00 | $6,500.00 | $1,000.00 | $2,500.00 | |
| 6 | 28000510 | INLET FILTERS | 2 | EACH | $300.00 | $50.00 | $250.00 | $300.00 | |
| 7 | 40600290 | BIT MATLS TACK CT | 17,531 | POUND | $0.0100 | $0.0100 | $0.0100 | $1.00 | |
| 8 | 40600370 | LONG JOINT SEALANT | 9,494 | FOOT | $2.81 | $2.95 | $2.60 | $2.50 | |
| 9 | 40600400 | MIX CR JTS FLANGEWYS | 20 | TON | $0.0100 | $680.00 | $150.00 | $300.00 | |
| 10 | 40600982 | HMA SURF REM BUTT JT | 55 | SQ YD | $25.00 | $15.00 | $13.00 | $20.00 | |
| 11 | 40603080 | HMA BC IL-19.0 N50 | 3,273 | TON | $72.00 | $72.00 | $83.75 | $77.00 | |
| 12 | 40604060 | HMA SC IL-9.5 D N50 | 2,182 | TON | $77.00 | $75.00 | $88.75 | $87.00 | |
| 13 | 40800029 | BIT MATLS TACK CT | 258 | POUND | $0.0100 | $0.0100 | $0.0100 | $1.00 | |
| 14 | 40800050 | INCIDENTAL HMA SURF | 38 | TON | $100.00 | $225.00 | $155.00 | $300.00 | |
| 15 | 44000163 | HMA SURF REM 3 1/2 | 25,856 | SQ YD | $2.80 | $3.50 | $3.95 | $5.15 | |
| 16 | 44201713 | CL D PATCH T1 6 | 150 | SQ YD | $67.00 | $60.00 | $56.00 | $265.00 | |
| 17 | 44201717 | CL D PATCH T2 6 | 150 | SQ YD | $67.00 | $60.00 | $56.00 | $155.00 | |
| 18 | 44201721 | CL D PATCH T3 6 | 150 | SQ YD | $62.00 | $60.00 | $56.00 | $115.00 | |
| 19 | 48101200 | AGGREGATE SHLDS B | 681 | TON | $32.00 | $38.00 | $38.00 | $40.00 | |
| 20 | 67100100 | MOBILIZATION | 1 | L SUM | $41,000.00 | $43,202.52 | $45,000.00 | $50,000.00 | |
| 21 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $0.0100 | $100.00 | $2,173.00 | $100.00 | |
| 22 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $0.0100 | $5,000.00 | $2,173.00 | $10,000.00 | |
| 23 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $0.0100 | $100.00 | $2,173.00 | $100.00 | |
| 24 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $26,750.00 | $100.00 | $2,173.00 | $100.00 | |
| 25 | 70300100 | SHORT TERM PAVT MKING | 2,849 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.5000 | |
| 26 | 70300150 | SHRT TRM PAVT MK REM | 1,417 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $4.25 | |
| 27 | 70307120 | TEMP PVT MK L4 T4 TAPE | 4,763 | FOOT | $0.0100 | $0.0100 | $1.25 | $1.30 | |
| 28 | 78000200 | THPL PVT MK LINE 4 | 26,044 | FOOT | $0.8100 | $0.7400 | $0.7400 | $0.7400 | |
| 29 | 78000650 | THPL PVT MK LINE 24 | 37 | FOOT | $7.15 | $6.50 | $5.25 | $6.50 | |
| 30 | 78011025 | GRV RCSD PVT MRKG 5 | 4,088 | FOOT | $0.6400 | $0.5800 | $1.25 | $0.5800 | |
| 31 | 78100100 | RAISED REFL PAVT MKR | 142 | EACH | $64.85 | $58.95 | $49.00 | $58.95 | |
| 32 | 78300200 | RAISED REF PVT MK REM | 142 | EACH | $8.00 | $25.00 | $7.64 | $15.00 |