(1313VB-VC-WPGM) BDR,BJR 25
- Let date
- Friday, July 31, 2026
- Contract
- 80B44 · job page
- District
- District 1
- County
- Cook
- Highway
- Limits
- (2,800-Ft) Bridge Overlay includes HMA resurfacing and patching consists of bridge deck scarification and latex concrete overlay, transverse joint repair at the north and south abutments, concrete pier repair, cleaning and adjusting deck drains, road surface removal, HMA overlay and paving, pavement patching, removal and replacement of combination curb and gutter, removal and replacement of guardrail, pavement markings. Located in the Village of Alsip, Cook County.
- Classification
- Bridge deck scarification and latex concrete overlay, transverse joint repair at the north and south abutments ·
- Project number
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $2,052,202 | ||
| 2 | Martam Construction Incorporated | $2,383,504 | +16.1% | |
| 3 | Gallagher Asphalt Corporation | $2,389,284 | +16.4% | |
| 4 | Lorig Construction Company | $2,651,556 | +29.2% | |
| 5 | MYS, Incorporated | $2,651,845 | +29.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 Martam Construc… | #3 Gallagher Aspha… | #4 Lorig Construct… | #5 MYS, Incorporat… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $15,000.00 | $12,000.00 | $22,000.00 | $100.00 | $27,672.01 | |
| 2 | X0326766 | CLEAN RESEAL RLF JNT | 150 | FOOT | $80.00 | $89.00 | $121.00 | $60.00 | $61.56 | |
| 3 | X4400221 | CURB REM & REPLACEMT < = 10FT | 100 | FOOT | $107.10 | $95.00 | $77.00 | $170.00 | $112.90 | |
| 4 | X4400223 | CURB REM&REPL > 10FT | 100 | FOOT | $85.05 | $72.00 | $62.00 | $140.00 | $89.66 | |
| 5 | X5030250 | BR DECK GROOVING LONG | 1,175 | SQ YD | $8.74 | $8.00 | $7.00 | $9.00 | $6.64 | |
| 6 | X5230154 | CLN BRDG SCUPS/DNSPTS | 8 | EACH | $500.00 | $600.00 | $1,150.00 | $1,200.00 | $120.00 | |
| 7 | X5230170 | DRAINAGE SCUPPERS SPL | 1 | EACH | $4,500.00 | $3,200.00 | $2,850.00 | $2,000.00 | $5,141.46 | |
| 8 | X5230172 | DRAINAGE SCUPPERS ADJ | 8 | EACH | $1,500.00 | $1,600.00 | $1,750.00 | $1,000.00 | $1,043.96 | |
| 9 | X5537800 | SS CLEANED 12 | 2,800 | FOOT | $2.20 | $3.00 | $3.00 | $12.00 | $2.21 | |
| 10 | X6030310 | FR & LIDS ADJUST SPL | 6 | EACH | $1,000.00 | $1,600.00 | $1,500.00 | $2,200.00 | $1,660.32 | |
| 11 | X6700407 | ENGRS FLD OFC TY A D1 | 12 | CAL MO | $5,000.00 | $4,200.00 | $3,250.00 | $2,700.00 | $3,158.44 | |
| 12 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $84,965.00 | $170,000.00 | $93,000.00 | $300,000.00 | $62,870.81 | |
| 13 | X7200061 | TEMP INFO SIGNING | 267 | SQ FT | $30.00 | $16.00 | $16.00 | $15.00 | $19.92 | |
| 14 | X7830050 | RRPM REFLECTOR REMOVL | 12 | EACH | $20.00 | $15.00 | $60.00 | $35.00 | $27.67 | |
| 15 | X7830052 | RRPM REFLECTOR REPLAC | 12 | EACH | $24.20 | $25.00 | $85.00 | $30.00 | $27.67 | |
| 16 | X8860105 | DET LOOP REPL | 300 | FOOT | $38.23 | $38.00 | $37.00 | $36.00 | $38.46 | |
| 17 | X8900104 | TEMP TR SIGNAL TIMING | 1 | EACH | $302.50 | $300.00 | $300.00 | $300.00 | $304.39 | |
| 18 | Z0012800 | CONC PAVT SCAR | 348 | SQ YD | $30.00 | $18.00 | $15.50 | $73.00 | $44.51 | |
| 19 | Z0015550 | DEBRIS REMOVAL | 10 | CU YD | $250.00 | $165.00 | $650.00 | $150.00 | $288.06 | |
| 20 | Z0018400 | DRAINAGE STR ADJ | 4 | EACH | $600.00 | $600.00 | $750.00 | $1,600.00 | $664.13 | |
| 21 | Z0018500 | DRAINAGE STR CLEANED | 25 | EACH | $385.00 | $400.00 | $450.00 | $350.00 | $387.41 | |
| 22 | Z0029090 | DIAMOND GRIND BR SEC | 1,123 | SQ YD | $12.57 | $10.00 | $12.00 | $10.50 | $17.71 | |
| 23 | Z0041895 | POLYMER CONCRETE | 21 | CU FT | $1,250.00 | $1,050.00 | $1,800.00 | $1,100.00 | $966.65 | |
| 24 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $4,400.00 | $12,000.00 | $13,550.00 | $7,000.00 | $17,151.11 | |
| 25 | Z0062456 | TEMP PAVEMENT | 476 | SQ YD | $60.00 | $68.00 | $90.00 | $110.00 | $86.92 | |
| 26 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 27 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | |
| 28 | 20200100 | EARTH EXCAVATION | 480 | CU YD | $45.00 | $45.00 | $135.00 | $72.00 | $92.74 | |
| 29 | 20201200 | REM & DISP UNS MATL | 62 | CU YD | $50.00 | $45.00 | $140.00 | $85.00 | $62.26 | |
| 30 | 21001000 | GEOTECH FAB F/GR STAB | 186 | SQ YD | $5.00 | $5.00 | $2.50 | $4.00 | $11.11 | |
| 31 | 30300001 | AGG SUBGRADE IMPROVE | 62 | CU YD | $60.00 | $76.00 | $90.00 | $110.00 | $119.79 | |
| 32 | 30300112 | AGG SUBGRADE IMPR 12 | 741 | SQ YD | $24.00 | $25.00 | $40.00 | $44.00 | $31.73 | |
| 33 | 35501324 | HMA BASE CSE 10 | 657 | SQ YD | $60.00 | $120.00 | $78.00 | $137.00 | $121.76 | |
| 34 | 40600275 | BIT MATLS PR CT | 2,633 | POUND | $0.0100 | $0.1000 | $0.0100 | $0.0100 | $0.0100 | |
| 35 | 40600290 | BIT MATLS TACK CT | 13,032 | POUND | $0.0100 | $0.1000 | $0.0100 | $0.0100 | $0.0100 | |
| 36 | 40600370 | LONG JOINT SEALANT | 5,136 | FOOT | $3.74 | $4.40 | $4.50 | $4.50 | $4.52 | |
| 37 | 40600982 | HMA SURF REM BUTT JT | 878 | SQ YD | $0.0100 | $12.00 | $25.00 | $27.00 | $11.07 | |
| 38 | 40603200 | P HMA BC IL-4.75 N50 | 778 | TON | $105.00 | $145.00 | $135.00 | $190.00 | $154.96 | |
| 39 | 40605026 | P HMA SC SMA 9.5 F N80 | 1,622 | TON | $128.00 | $165.00 | $152.00 | $167.00 | $177.10 | |
| 40 | 42101300 | PROTECTIVE COAT | 759 | SQ YD | $2.10 | $1.00 | $1.00 | $1.80 | $2.21 | |
| 41 | 44000100 | PAVEMENT REM | 1,133 | SQ YD | $20.00 | $27.00 | $16.00 | $30.00 | $43.67 | |
| 42 | 44000161 | HMA SURF REM 3 | 12,794 | SQ YD | $3.24 | $9.00 | $4.60 | $5.50 | $8.86 | |
| 43 | 44000500 | COMB CURB GUTTER REM | 677 | FOOT | $10.00 | $12.00 | $21.00 | $21.00 | $26.25 | |
| 44 | 44003100 | MEDIAN REMOVAL | 5,722 | SQ FT | $4.00 | $7.00 | $5.50 | $6.00 | $10.98 | |
| 45 | 44004250 | PAVED SHLD REMOVAL | 502 | SQ YD | $15.00 | $25.00 | $28.00 | $19.00 | $42.53 | |
| 46 | 44201761 | CL D PATCH T1 10 | 256 | SQ YD | $105.00 | $41.00 | $40.00 | $100.00 | $116.22 | |
| 47 | 44201765 | CL D PATCH T2 10 | 256 | SQ YD | $105.00 | $41.00 | $40.00 | $100.00 | $116.22 | |
| 48 | 44201769 | CL D PATCH T3 10 | 256 | SQ YD | $105.00 | $41.00 | $35.00 | $100.00 | $116.22 | |
| 49 | 44201771 | CL D PATCH T4 10 | 256 | SQ YD | $105.00 | $41.00 | $35.00 | $100.00 | $116.22 | |
| 50 | 48203021 | HMA SHOULDERS 6 | 1,377 | SQ YD | $28.50 | $54.00 | $45.00 | $51.00 | $57.93 | |
| 51 | 48203100 | HMA SHOULDERS | 19 | TON | $190.00 | $165.00 | $190.00 | $230.00 | $166.03 | |
| 52 | 50102400 | CONC REM | 0.8 | CU YD | $6,000.00 | $6,500.00 | $12,500.00 | $9,000.00 | $3,666.45 | |
| 53 | 50157300 | PROTECTIVE SHIELD | 893 | SQ YD | $80.00 | $54.00 | $95.00 | $1.00 | $120.26 | |
| 54 | 50300300 | PROTECTIVE COAT | 1,784 | SQ YD | $1.00 | $1.00 | $6.00 | $1.75 | $4.90 | |
| 55 | 53101002 | BR DECK SCAR 3/4 | 1,227 | SQ YD | $59.00 | $52.00 | $105.00 | $76.00 | $61.04 | |
| 56 | 53101410 | BR DK LTX C OLY 2 3/4 | 1,227 | SQ YD | $125.00 | $132.00 | $220.00 | $135.00 | $159.14 | |
| 57 | 53212754 | STR REP CON DP = < 5 | 320 | SQ FT | $175.00 | $195.00 | $295.00 | $335.00 | $193.70 | |
| 58 | 58700300 | CONCRETE SEALER | 320 | SQ FT | $1.50 | $4.00 | $11.00 | $3.50 | $3.69 | |
| 59 | 59200101 | BRIDGE WASHING N1 | 1 | EACH | $43,706.30 | $44,000.00 | $43,750.00 | $35,000.00 | $43,979.68 | |
| 60 | 60603800 | COMB CC&G TB6.12 | 212 | FOOT | $51.45 | $54.00 | $35.00 | $101.00 | $54.24 | |
| 61 | 60605000 | COMB CC&G TY B-6.24 | 465 | FOOT | $61.95 | $63.00 | $55.00 | $105.00 | $65.31 | |
| 62 | 60624600 | CORRUGATED MED | 5,722 | SQ FT | $19.95 | $25.00 | $17.00 | $23.00 | $21.03 | |
| 63 | 63000007 | SPBGR TY B 6FT POSTS | 1,700 | FOOT | $53.55 | $66.00 | $53.40 | $54.00 | $59.77 | |
| 64 | 63100045 | TRAF BAR TERM T2 | 1 | EACH | $2,100.00 | $2,000.00 | $2,750.00 | $2,700.00 | $2,767.20 | |
| 65 | 63100089 | TRAF BAR TERM T6B | 4 | EACH | $5,355.00 | $4,800.00 | $4,900.00 | $4,900.00 | $5,977.15 | |
| 66 | 63100167 | TR BAR TRM T1 SPL TAN | 2 | EACH | $4,410.00 | $4,200.00 | $3,900.00 | $4,000.00 | $5,091.65 | |
| 67 | 63200310 | GUARDRAIL REMOV | 1,925 | FOOT | $12.60 | $10.00 | $6.50 | $6.50 | $15.50 | |
| 68 | 66900200 | NON SPL WASTE DISPOSL | 542 | CU YD | $90.00 | $73.00 | $0.0100 | $70.00 | $64.22 | |
| 69 | 66900530 | SOIL DISPOSAL ANALY | 4 | EACH | $1,750.00 | $1,500.00 | $950.00 | $1,500.00 | $1,604.98 | |
| 70 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,500.00 | $5,500.00 | $5,200.00 | $3,200.00 | $3,431.33 | |
| 71 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,500.00 | $1,500.00 | $500.00 | $1,300.00 | $1,328.26 | |
| 72 | 66901006 | REG SUB MON | 10 | CAL DA | $1,000.00 | $800.00 | $715.00 | $800.00 | $752.68 | |
| 73 | 67100100 | MOBILIZATION | 1 | L SUM | $123,000.00 | $140,000.00 | $142,800.00 | $135,000.00 | $208,964.43 | |
| 74 | 70103815 | TR CONT SURVEILLANCE | 60 | CAL DA | $0.0100 | $220.00 | $77.00 | $75.00 | $27.67 | |
| 75 | 70107025 | CHANGEABLE MESSAGE SN | 120 | CAL DA | $50.00 | $33.00 | $30.00 | $30.00 | $33.21 | |
| 76 | 70300100 | SHORT TERM PAVT MKING | 5,036 | FOOT | $0.5000 | $1.00 | $0.0100 | $1.25 | $2.77 | |
| 77 | 70300150 | SHRT TRM PAVT MK REM | 5,753 | SQ FT | $2.00 | $1.00 | $0.0100 | $1.25 | $0.4400 | |
| 78 | 70307120 | TEMP PVT MK L4 T4 TAPE | 14,940 | FOOT | $1.20 | $1.30 | $1.00 | $1.30 | $1.38 | |
| 79 | 70307130 | TEMP PVT MK L6 T4 TAPE | 1,434 | FOOT | $1.75 | $2.00 | $3.00 | $3.00 | $2.21 | |
| 80 | 70307160 | TEMP PVT MK L12 T4 TAPE | 56 | FOOT | $5.00 | $4.00 | $6.00 | $6.00 | $4.43 | |
| 81 | 70400100 | TEMP CONC BARRIER | 712.5 | FOOT | $40.00 | $32.00 | $59.00 | $31.00 | $45.38 | |
| 82 | 70400200 | REL TEMP CONC BARRIER | 662.5 | FOOT | $20.00 | $12.00 | $16.00 | $7.00 | $6.64 | |
| 83 | 70600255 | IMP ATTN TEMP FRN TL2 | 2 | EACH | $6,500.00 | $6,000.00 | $6,500.00 | $6,400.00 | $5,534.40 | |
| 84 | 70600322 | IMP ATTN REL FRN TL2 | 2 | EACH | $2,500.00 | $4,000.00 | $1,550.00 | $1,500.00 | $2,213.76 | |
| 85 | 78000100 | THPL PVT MK LTR & SYM | 255 | SQ FT | $6.33 | $6.00 | $6.00 | $6.00 | $5.65 | |
| 86 | 78000200 | THPL PVT MK LINE 4 | 12,158 | FOOT | $1.05 | $1.00 | $0.7000 | $1.00 | $0.9700 | |
| 87 | 78000400 | THPL PVT MK LINE 6 | 442 | FOOT | $1.89 | $1.80 | $1.00 | $1.80 | $1.27 | |
| 88 | 78000500 | THPL PVT MK LINE 8 | 129 | FOOT | $2.15 | $2.00 | $1.75 | $2.00 | $1.94 | |
| 89 | 78000600 | THPL PVT MK LINE 12 | 48 | FOOT | $3.65 | $3.50 | $3.00 | $3.50 | $3.27 | |
| 90 | 78004635 | PREF PL PM TD STD L 7 | 118 | FOOT | $18.15 | $18.00 | $14.00 | $16.50 | $37.08 | |
| 91 | 78009004 | MOD URETH PM LINE 4 | 938 | FOOT | $5.50 | $5.50 | $3.75 | $5.00 | $4.54 | |
| 92 | 78011040 | GRV RCSD PVT MRKG 8 | 118 | FOOT | $6.05 | $6.00 | $12.00 | $5.50 | $18.82 | |
| 93 | 78100100 | RAISED REFL PAVT MKR | 170 | EACH | $49.50 | $48.00 | $45.00 | $45.00 | $48.70 | |
| 94 | 78300200 | RAISED REF PVT MK REM | 170 | EACH | $10.00 | $20.00 | $0.0100 | $15.00 | $48.70 | |
| 95 | 78300202 | PVT MKG REM WTR BLAST | 2,891 | SQ FT | $3.30 | $4.00 | $1.00 | $1.25 | $0.1100 |