2025-2010-RS
- Let date
- Friday, January 16, 2026
- Contract
- 80B29 · job page
- District
- District 1
- County
- Lake
- Highway
- Limits
- (0.46-mile) Designed Overlay consisting of hot-mix asphalt surface removal, depth patches (Class D), curb and gutter spot repairs (removal and replacement) hot-mix asphalt resurfacing (cold milling and inlay), new thermoplastic pavement markings. Located on US 45 (Lake Street) from north of Tempel Drive to Ramp to IL 137 within the Village of Libertyville.
- Classification
- ·
- Project number
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Peter Baker & Son Co. Low bidder | $1,013,752 | ||
| 2 | Payne & Dolan, Inc. | $1,049,780 | +3.6% | |
| 3 | Builders Paving, LLC | $1,134,808 | +11.9% | |
| 4 | Curran Contracting Company | $1,294,618 | +27.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Peter Baker & S… | #2 Payne & Dolan, … | #3 Builders Paving… | #4 Curran Contract… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X2020110 | GRADING & SHAP SHLDRS | 15 | UNIT | $75.00 | $221.72 | $200.00 | $200.00 | |
| 2 | X4060995 | TEMPORARY RAMP SPL | 502 | SQ YD | $5.00 | $12.69 | $5.00 | $25.00 | |
| 3 | X4400100 | PCC SURF REM VAR DP | 93 | SQ YD | $49.50 | $11.18 | $50.00 | $50.00 | |
| 4 | X4400501 | CC&G RMVL REPL < = 10 | 534 | FOOT | $55.00 | $55.00 | $81.90 | $55.00 | |
| 5 | X4400503 | CC&G RMVL REPL > 10FT | 200 | FOOT | $55.00 | $55.00 | $73.90 | $55.00 | |
| 6 | X5537800 | SS CLEANED 12 | 103 | FOOT | $1.50 | $10.00 | $1.50 | $1.50 | |
| 7 | X6030310 | FR & LIDS ADJUST SPL | 5 | EACH | $1,300.00 | $1,850.00 | $1,300.00 | $1,300.00 | |
| 8 | X6700407 | ENGRS FLD OFC TY A D1 | 12 | CAL MO | $500.00 | $2,025.00 | $3,000.00 | $3,250.00 | |
| 9 | X7010808 | TRAF CONT-PROT TC8 | 4 | EACH | $750.00 | $1,000.00 | $750.00 | $750.00 | |
| 10 | X7200061 | TEMP INFO SIGNING | 102.8 | SQ FT | $15.00 | $18.00 | $15.00 | $15.00 | |
| 11 | X8860105 | DET LOOP REPL | 370 | FOOT | $34.37 | $34.81 | $34.37 | $34.37 | |
| 12 | X8891009 | VID VEH DET SYS SN AP | 1 | EACH | $11,347.00 | $14,087.71 | $11,347.00 | $11,347.00 | |
| 13 | Z0018500 | DRAINAGE STR CLEANED | 7 | EACH | $375.00 | $500.00 | $375.00 | $375.00 | |
| 14 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $1,235.00 | $3,850.00 | $3,500.00 | $7,500.00 | |
| 15 | 21101615 | TOPSOIL F & P 4 | 62 | SQ YD | $1.00 | $28.00 | $1.00 | $28.00 | |
| 16 | 25200110 | SODDING SALT TOLERANT | 62 | SQ YD | $80.00 | $90.00 | $80.00 | $90.00 | |
| 17 | 35400400 | PCC BASE CSE W 9 | 71 | SQ YD | $126.00 | $126.00 | $118.25 | $126.00 | |
| 18 | 35800100 | PREPARATION OF BASE | 291 | SQ YD | $5.00 | $5.00 | $2.00 | $5.00 | |
| 19 | 35800200 | AGG BASE REPAIR | 2 | TON | $10.00 | $10.00 | $300.00 | $10.00 | |
| 20 | 40600290 | BIT MATLS TACK CT | 13,147 | POUND | $0.0100 | $0.1000 | $0.0100 | $1.50 | |
| 21 | 40600370 | LONG JOINT SEALANT | 6,458 | FOOT | $3.85 | $2.87 | $3.36 | $3.50 | |
| 22 | 40600400 | MIX CR JTS FLANGEWYS | 30 | TON | $250.00 | $138.00 | $535.00 | $450.00 | |
| 23 | 40600982 | HMA SURF REM BUTT JT | 225 | SQ YD | $1.00 | $45.00 | $5.00 | $25.00 | |
| 24 | 40602985 | HMA BC IL-9.5 N70 | 2,144 | TON | $89.00 | $89.00 | $100.00 | $107.00 | |
| 25 | 40604072 | HMA SC IL-9.5 E N70 | 1,909 | TON | $105.80 | $110.00 | $120.00 | $122.00 | |
| 26 | 42001300 | PROTECTIVE COAT | 238 | SQ YD | $0.0100 | $0.1000 | $1.35 | $0.0100 | |
| 27 | 44000100 | PAVEMENT REM | 71 | SQ YD | $27.00 | $27.00 | $25.00 | $27.00 | |
| 28 | 44000164 | HMA SURF REM 3 3/4 | 19,355 | SQ YD | $5.35 | $5.25 | $11.00 | $5.75 | |
| 29 | 44003100 | MEDIAN REMOVAL | 1,978 | SQ FT | $17.50 | $17.50 | $8.70 | $17.50 | |
| 30 | 44201789 | CL D PATCH T2 12 | 828 | SQ YD | $50.00 | $71.00 | $65.00 | $155.00 | |
| 31 | 44201794 | CL D PATCH T3 12 | 497 | SQ YD | $50.00 | $76.00 | $60.00 | $150.00 | |
| 32 | 44201796 | CL D PATCH T4 12 | 331 | SQ YD | $50.00 | $88.00 | $55.00 | $125.00 | |
| 33 | 48102100 | AGG WEDGE SHLD TYPE B | 57 | TON | $109.30 | $115.00 | $125.00 | $150.00 | |
| 34 | 60300105 | FR & GRATES ADJUST | 5 | EACH | $600.00 | $685.00 | $600.00 | $600.00 | |
| 35 | 60300305 | FR & LIDS ADJUST | 1 | EACH | $600.00 | $880.00 | $600.00 | $600.00 | |
| 36 | 60619600 | CONC MED TSB6.12 | 1,478 | SQ FT | $20.00 | $20.00 | $25.70 | $20.00 | |
| 37 | 67100100 | MOBILIZATION | 1 | L SUM | $77,000.00 | $120,000.00 | $74,732.85 | $115,000.00 | |
| 38 | 70100420 | TRAF CONT-PROT 701411 | 1 | EACH | $450.00 | $1.00 | $1,958.00 | $450.00 | |
| 39 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $1,958.00 | $1.00 | $1,958.00 | $15,000.00 | |
| 40 | 70102622 | TR CONT & PROT 701502 | 1 | L SUM | $1,958.00 | $1.00 | $1,958.00 | $1,958.00 | |
| 41 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $106,867.00 | $8,900.00 | $1,958.00 | $1,958.00 | |
| 42 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1,958.00 | $1.00 | $450.00 | $1,958.00 | |
| 43 | 70300100 | SHORT TERM PAVT MKING | 1,352 | FOOT | $0.0100 | $0.1000 | $0.0100 | $1.00 | |
| 44 | 70300150 | SHRT TRM PAVT MK REM | 226 | SQ FT | $0.0100 | $12.50 | $0.0100 | $12.50 | |
| 45 | 70300211 | TEMP PVT MK LTR & SYM PAINT | 219 | SQ FT | $0.0100 | $2.00 | $0.0100 | $1.75 | |
| 46 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 14,376 | FOOT | $0.0100 | $0.3500 | $0.0100 | $0.3500 | |
| 47 | 70300241 | TEMP PVT MK LINE 6 - PAINT | 1,152 | FOOT | $0.0100 | $0.5300 | $0.0100 | $0.5300 | |
| 48 | 70300251 | TEMP PVT MK LINE 8 - PAINT | 576 | FOOT | $0.0100 | $0.7000 | $0.0100 | $0.7000 | |
| 49 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 624 | FOOT | $0.0100 | $1.05 | $0.0100 | $1.06 | |
| 50 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 444 | FOOT | $0.0100 | $2.10 | $0.0100 | $1.60 | |
| 51 | 70307120 | TEMP PVT MK L4 T4 TAPE | 676 | FOOT | $0.0100 | $6.00 | $0.0100 | $1.20 | |
| 52 | 78000100 | THPL PVT MK LTR & SYM | 73 | SQ FT | $6.00 | $6.00 | $8.50 | $5.75 | |
| 53 | 78000200 | THPL PVT MK LINE 4 | 5,029 | FOOT | $1.20 | $1.20 | $0.9800 | $0.8600 | |
| 54 | 78000400 | THPL PVT MK LINE 6 | 399 | FOOT | $1.75 | $1.75 | $1.47 | $1.35 | |
| 55 | 78000500 | THPL PVT MK LINE 8 | 513 | FOOT | $1.85 | $1.85 | $2.75 | $1.75 | |
| 56 | 78000600 | THPL PVT MK LINE 12 | 248 | FOOT | $3.00 | $3.00 | $4.25 | $2.75 | |
| 57 | 78000650 | THPL PVT MK LINE 24 | 148 | FOOT | $6.00 | $6.00 | $8.50 | $5.75 | |
| 58 | 78100100 | RAISED REFL PAVT MKR | 172 | EACH | $49.50 | $49.50 | $62.50 | $51.25 | |
| 59 | 78300200 | RAISED REF PVT MK REM | 146 | EACH | $26.00 | $9.10 | $5.00 | $30.00 | |
| 60 | 85000200 | MAIN EX TR SIG INSTAL | 1 | EACH | $3,500.00 | $2,134.24 | $3,500.00 | $3,500.00 | |
| 61 | 89502300 | REM ELCBL FR CON | 266 | FOOT | $1.65 | $4.01 | $1.65 | $1.65 | |
| 62 | 89502375 | REMOV EX TS EQUIP | 1 | EACH | $410.00 | $204.53 | $410.00 | $410.00 |