22-00112-00-BR
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Otto Baum Company, Inc. Low bidder | $898,500 | ||
| 2 | Illinois Civil Contractors, Inc. | $918,425 | +2.2% | |
| 3 | Stark Excavating, Inc. | $968,386 | +7.8% | |
| 4 | Knapp Concrete Contractors, Inc. | $997,319 | +11.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Otto Baum Compa… | #2 Illinois Civil … | #3 Stark Excavatin… | #4 Knapp Concrete … |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X2130010 | EXPLOR TRENCH SPL | 50 | FOOT | $70.94 | $49.81 | $23.00 | $63.60 | |
| 2 | X4024000 | TEMP ACCESS- FLD ENT | 2 | EACH | $2,555.38 | $1,131.30 | $1,790.00 | $2,650.00 | |
| 3 | X5021507 | DEWATERING | 1 | L SUM | $16,256.61 | $14,767.57 | $16,000.00 | $15,900.00 | |
| 4 | X5810103 | MEMB WTRPRF SYS B STR | 137 | SQ YD | $31.57 | $68.73 | $51.00 | $50.88 | |
| 5 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $17,420.97 | $21,892.89 | $12,400.00 | $21,200.00 | |
| 6 | X7010237 | CHANGE MESSAGE SN SPL | 108 | CAL DA | $26.81 | $109.74 | $26.00 | $90.10 | |
| 7 | X7200061 | TEMP INFO SIGNING | 50 | SQ FT | $21.45 | $53.77 | $21.00 | $53.00 | |
| 8 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $9,865.01 | $10,095.97 | $5,010.00 | $9,752.00 | |
| 9 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 10 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 11 | 20200100 | EARTH EXCAVATION | 873 | CU YD | $39.44 | $51.62 | $30.00 | $42.40 | |
| 12 | 20201200 | REM & DISP UNS MATL | 80 | CU YD | $43.70 | $49.81 | $39.00 | $180.20 | |
| 13 | 20700220 | POROUS GRAN EMBANK | 484 | CU YD | $103.44 | $83.50 | $110.00 | $97.52 | |
| 14 | 21001000 | GEOTECH FAB F/GR STAB | 478 | SQ YD | $2.51 | $2.43 | $2.40 | $5.51 | |
| 15 | 21101615 | TOPSOIL F & P 4 | 3,593 | SQ YD | $5.90 | $10.17 | $4.25 | $5.83 | |
| 16 | 25000210 | SEEDING CL 2A | 0.75 | ACRE | $4,289.15 | $4,696.83 | $2,800.00 | $4,240.00 | |
| 17 | 25000400 | NITROGEN FERT NUTR | 67 | POUND | $5.36 | $5.49 | $2.55 | $5.30 | |
| 18 | 25000500 | PHOSPHORUS FERT NUTR | 67 | POUND | $5.36 | $5.49 | $2.55 | $5.30 | |
| 19 | 25000600 | POTASSIUM FERT NUTR | 67 | POUND | $5.36 | $5.49 | $2.55 | $5.30 | |
| 20 | 25100630 | EROSION CONTR BLANKET | 3,593 | SQ YD | $1.61 | $1.65 | $1.22 | $1.59 | |
| 21 | 28000400 | PERIMETER EROS BAR | 900 | FOOT | $3.75 | $5.48 | $2.90 | $3.71 | |
| 22 | 28000500 | INLET & PIPE PROTECT | 2 | EACH | $268.08 | $260.44 | $165.00 | $265.00 | |
| 23 | 28100107 | STONE RIPRAP CL A4 | 250 | SQ YD | $90.11 | $145.96 | $112.00 | $90.10 | |
| 24 | 28200200 | FILTER FABRIC | 702 | SQ YD | $4.76 | $3.49 | $5.00 | $6.47 | |
| 25 | 28300400 | AGGREGATE DITCH | 265 | TON | $99.29 | $116.42 | $111.00 | $54.06 | |
| 26 | 30300001 | AGG SUBGRADE IMPROVE | 80 | CU YD | $107.59 | $65.57 | $85.00 | $84.80 | |
| 27 | 30300112 | AGG SUBGRADE IMPR 12 | 1,289 | SQ YD | $17.72 | $20.55 | $37.00 | $29.68 | |
| 28 | 40200900 | AGG SURF CSE B | 27 | CU YD | $193.06 | $86.90 | $130.00 | $84.80 | |
| 29 | 40600275 | BIT MATLS PR CT | 2,800 | POUND | $1.61 | $1.10 | $1.05 | $1.06 | |
| 30 | 40600290 | BIT MATLS TACK CT | 840 | POUND | $2.68 | $1.76 | $1.70 | $1.70 | |
| 31 | 40603080 | HMA BC IL-19.0 N50 | 419 | TON | $160.84 | $195.98 | $180.00 | $189.74 | |
| 32 | 40604060 | HMA SC IL-9.5 D N50 | 140 | TON | $214.46 | $247.68 | $228.00 | $239.56 | |
| 33 | 44000100 | PAVEMENT REM | 1,022 | SQ YD | $11.99 | $25.12 | $10.00 | $21.20 | |
| 34 | 44004000 | PAVED DITCH REMOVAL | 268 | FOOT | $29.82 | $19.26 | $12.00 | $12.72 | |
| 35 | 50100100 | REM EXIST STRUCT | 1 | EACH | $24,763.14 | $34,201.95 | $57,085.00 | $13,780.00 | |
| 36 | 50105220 | PIPE CULVERT REMOV | 44 | FOOT | $49.41 | $35.94 | $16.00 | $42.40 | |
| 37 | 50200100 | STRUCTURE EXCAVATION | 580 | CU YD | $30.32 | $47.11 | $23.00 | $42.40 | |
| 38 | 50800105 | REINFORCEMENT BARS | 59,180 | POUND | $1.58 | $1.55 | $1.80 | $2.10 | |
| 39 | 51500100 | NAME PLATES | 1 | EACH | $1,718.28 | $1,475.51 | $1,500.00 | $1,017.60 | |
| 40 | 54003000 | CONC BOX CUL | 209 | CU YD | $1,106.71 | $874.88 | $1,320.00 | $1,404.50 | |
| 41 | 542A0223 | P CUL CL A 1 18 | 56 | FOOT | $139.60 | $96.94 | $95.00 | $121.90 | |
| 42 | 54213663 | PRC FLAR END SEC 18 | 4 | EACH | $1,593.11 | $1,862.37 | $1,200.00 | $1,817.90 | |
| 43 | 59100100 | GEOCOMPOSITE WALL DR | 137 | SQ YD | $29.86 | $23.13 | $26.75 | $42.93 | |
| 44 | 61100605 | MISC CONCRETE | 10 | CU YD | $1,348.95 | $594.75 | $182.00 | $508.80 | |
| 45 | 61133100 | FLD TILE JUN VAULT 2D | 2 | EACH | $2,350.86 | $1,838.54 | $2,230.00 | $2,111.52 | |
| 46 | 61139800 | STORM SEWER SPEC 4 | 20 | FOOT | $100.33 | $23.11 | $40.15 | $63.60 | |
| 47 | 61139900 | STORM SEWER SPEC 6 | 20 | FOOT | $119.60 | $46.57 | $74.70 | $68.90 | |
| 48 | 61140000 | STORM SEWER SPEC 8 | 20 | FOOT | $140.27 | $58.15 | $80.30 | $74.20 | |
| 49 | 67100100 | MOBILIZATION | 1 | L SUM | $55,336.16 | $45,921.22 | $58,000.00 | $21,200.00 | |
| 50 | 72400100 | REMOV SIN PAN ASSY TA | 3 | EACH | $187.65 | $119.72 | $175.00 | $848.00 | |
| 51 | 78009004 | MOD URETH PM LINE 4 | 1,000 | FOOT | $7.51 | $7.68 | $7.05 | $11.66 | |
| 52 | 78011025 | GRV RCSD PVT MRKG 5 | 1,000 | FOOT | $6.43 | $6.58 | $6.05 | $11.66 |