23-00057-00-RS
Bidders 7
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Builders Paving, LLC Low bidder | $895,259 | ||
| 2 | A Lamp Concrete Contractors, Inc. | $964,678 | +7.8% | |
| 3 | K-Five Construction Corporation | $1,014,502 | +13.3% | |
| 4 | Everlast Blacktop Inc. | $1,081,432 | +20.8% | |
| 5 | Plote Construction, Inc. | $1,096,181 | +22.4% | |
| 6 | Schroeder Asphalt Services, Inc. | $1,096,504 | +22.5% | |
| 7 | R. W. Dunteman Company | $1,173,591 | +31.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Builders Paving… | #2 A Lamp Concrete… | #3 K-Five Construc… | #4 Everlast Blackt… | #5 Plote Construct… | #6 Schroeder Aspha… | #7 R. W. Dunteman … |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X4022000 | TEMP ACCESS- COM ENT | 21 | EACH | $100.00 | $350.00 | $70.00 | $300.00 | $10.00 | $200.00 | $264.14 | |
| 2 | X4060286 | HMA DRIVEWAY PAVT 6 | 478 | SQ YD | $77.00 | $57.00 | $55.00 | $51.00 | $80.00 | $65.00 | $51.03 | |
| 3 | X4400221 | CURB REM & REPLACEMT < = 10FT | 120 | FOOT | $69.00 | $59.00 | $60.00 | $89.00 | $85.00 | $58.00 | $122.24 | |
| 4 | X4400503 | CC&G RMVL REPL > 10FT | 1,117 | FOOT | $69.00 | $45.00 | $47.00 | $58.00 | $60.00 | $57.00 | $78.14 | |
| 5 | X6026050 | SANITARY MANHOLE ADJ | 4 | EACH | $1,850.00 | $825.00 | $1,420.00 | $1,200.00 | $1,000.00 | $1,150.00 | $1,850.00 | |
| 6 | X6030310 | FR & LIDS ADJUST SPL | 11 | EACH | $1,250.00 | $665.00 | $1,250.00 | $1,200.00 | $1,450.00 | $1,650.00 | $1,250.00 | |
| 7 | X7200061 | TEMP INFO SIGNING | 104 | SQ FT | $15.00 | $25.00 | $15.00 | $18.00 | $15.00 | $18.00 | $15.00 | |
| 8 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $2,500.00 | $5,000.00 | $10,000.00 | $800.00 | $100.00 | $7,000.00 | $9,000.00 | |
| 9 | Z0017400 | DRAIN UTIL STR ADJ | 10 | EACH | $450.00 | $400.00 | $450.00 | $750.00 | $675.00 | $715.00 | $450.00 | |
| 10 | Z0017700 | DRAIN UTIL STR RECON | 2 | EACH | $1,650.00 | $2,000.00 | $1,325.00 | $1,250.00 | $1,600.00 | $1,750.00 | $1,650.00 | |
| 11 | 20201200 | REM & DISP UNS MATL | 176 | CU YD | $10.00 | $10.00 | $15.00 | $42.00 | $10.00 | $65.00 | $77.09 | |
| 12 | 21001000 | GEOTECH FAB F/GR STAB | 486 | SQ YD | $2.00 | $0.0100 | $0.0100 | $2.00 | $1.00 | $4.00 | $2.94 | |
| 13 | 21101615 | TOPSOIL F & P 4 | 249 | SQ YD | $3.75 | $8.00 | $1.00 | $5.10 | $3.75 | $5.00 | $1.00 | |
| 14 | 25200110 | SODDING SALT TOLERANT | 249 | SQ YD | $32.50 | $12.50 | $36.00 | $16.00 | $32.50 | $40.00 | $36.00 | |
| 15 | 25200200 | SUPPLE WATERING | 14 | UNIT | $1.00 | $1.00 | $130.00 | $1.00 | $1.00 | $5.00 | $130.00 | |
| 16 | 28000510 | INLET FILTERS | 51 | EACH | $185.00 | $15.00 | $185.00 | $160.00 | $150.00 | $175.00 | $185.00 | |
| 17 | 30300001 | AGG SUBGRADE IMPROVE | 148 | CU YD | $50.00 | $10.00 | $10.00 | $58.00 | $10.00 | $70.00 | $65.46 | |
| 18 | 35101600 | AGG BASE CSE B 4 | 269 | SQ YD | $8.00 | $11.00 | $4.00 | $6.60 | $7.00 | $9.00 | $12.82 | |
| 19 | 35102000 | AGG BASE CSE B 8 | 478 | SQ YD | $2.50 | $21.00 | $10.65 | $9.70 | $15.00 | $16.00 | $22.72 | |
| 20 | 40600290 | BIT MATLS TACK CT | 18,340 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.8800 | |
| 21 | 40600370 | LONG JOINT SEALANT | 8,034 | FOOT | $3.32 | $2.87 | $3.10 | $3.60 | $3.60 | $3.60 | $3.15 | |
| 22 | 40600400 | MIX CR JTS FLANGEWYS | 36 | TON | $765.00 | $100.00 | $50.00 | $265.00 | $150.00 | $350.00 | $417.17 | |
| 23 | 40600982 | HMA SURF REM BUTT JT | 250 | SQ YD | $15.00 | $10.25 | $20.00 | $49.00 | $40.00 | $18.00 | $26.23 | |
| 24 | 40603200 | P HMA BC IL-4.75 N50 | 1,121 | TON | $85.00 | $120.00 | $124.00 | $103.00 | $135.00 | $111.00 | $108.29 | |
| 25 | 40604062 | HMA SC IL-9.5 D N70 | 2,662 | TON | $78.00 | $95.00 | $90.00 | $91.00 | $95.00 | $94.50 | $93.09 | |
| 26 | 42300400 | PCC DRIVEWAY PAVT 8 | 269 | SQ YD | $108.00 | $110.00 | $119.44 | $114.00 | $105.00 | $140.00 | $101.72 | |
| 27 | 44000159 | HMA SURF REM 2 1/2 | 27,160 | SQ YD | $3.00 | $2.69 | $3.75 | $2.88 | $5.80 | $2.75 | $3.11 | |
| 28 | 44000200 | DRIVE PAVEMENT REM | 747 | SQ YD | $42.00 | $13.50 | $25.00 | $18.00 | $20.00 | $17.50 | $22.03 | |
| 29 | 44201765 | CL D PATCH T2 10 | 299 | SQ YD | $50.00 | $50.00 | $30.00 | $118.00 | $35.00 | $115.00 | $119.91 | |
| 30 | 44201769 | CL D PATCH T3 10 | 652 | SQ YD | $50.00 | $50.00 | $30.00 | $102.00 | $35.00 | $110.00 | $113.08 | |
| 31 | 44201771 | CL D PATCH T4 10 | 815 | SQ YD | $50.00 | $50.00 | $30.00 | $102.00 | $35.00 | $105.00 | $98.96 | |
| 32 | 66900200 | NON SPL WASTE DISPOSL | 176 | CU YD | $120.00 | $55.00 | $75.00 | $89.00 | $35.00 | $105.00 | $102.82 | |
| 33 | 66900530 | SOIL DISPOSAL ANALY | 4 | EACH | $1,450.00 | $1,050.00 | $1,300.00 | $1,600.00 | $1,450.00 | $1,565.00 | $1,050.00 | |
| 34 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $3,100.00 | $5,800.00 | $3,100.00 | $2,700.00 | $3,100.00 | $4,800.00 | $5,800.00 | |
| 35 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $1,200.00 | $500.00 | $1,200.00 | $2,500.00 | $1,200.00 | $600.00 | $500.00 | |
| 36 | 66901006 | REG SUB MON | 30 | CAL DA | $100.00 | $100.00 | $680.00 | $1,150.00 | $120.00 | $850.00 | $715.00 | |
| 37 | 67100100 | MOBILIZATION | 1 | L SUM | $54,038.83 | $57,000.00 | $55,000.00 | $51,779.15 | $64,000.00 | $24,000.00 | $69,696.56 | |
| 38 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $1.00 | $105,000.00 | $108,000.00 | $15,000.00 | $1.00 | $2,500.00 | $20,308.64 | |
| 39 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $6,000.00 | $1.00 | $1.00 | $2,000.00 | $102,900.00 | $2,500.00 | $1,513.00 | |
| 40 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $2,000.00 | $1.00 | $2,500.00 | $1,513.00 | |
| 41 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $2,000.00 | $1.00 | $2,500.00 | $1,513.00 | |
| 42 | 70300100 | SHORT TERM PAVT MKING | 8,034 | FOOT | $0.0100 | $0.0100 | $0.0100 | $1.00 | $0.1000 | $2.00 | $1.07 | |
| 43 | 70300150 | SHRT TRM PAVT MK REM | 2,680 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $2.00 | $0.1000 | $3.00 | $1.11 | |
| 44 | 70300211 | TEMP PVT MK LTR & SYM PAINT | 1,530 | SQ FT | $0.0100 | $0.0100 | $1.75 | $2.00 | $0.0100 | $2.00 | $1.75 | |
| 45 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 26,400 | FOOT | $0.0100 | $0.0100 | $0.3500 | $0.4500 | $0.0100 | $0.4200 | $0.3500 | |
| 46 | 70300241 | TEMP PVT MK LINE 6 - PAINT | 4,800 | FOOT | $0.0100 | $0.0100 | $0.5300 | $0.7000 | $0.0100 | $0.6500 | $0.5300 | |
| 47 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 273 | FOOT | $0.0100 | $0.0100 | $1.60 | $2.00 | $0.0100 | $1.85 | $1.60 | |
| 48 | 78000100 | THPL PVT MK LTR & SYM | 509 | SQ FT | $5.35 | $5.75 | $5.75 | $6.10 | $5.35 | $6.25 | $5.75 | |
| 49 | 78000200 | THPL PVT MK LINE 4 | 17,890 | FOOT | $0.7600 | $0.8000 | $0.8000 | $1.00 | $0.7600 | $0.9000 | $0.8000 | |
| 50 | 78000400 | THPL PVT MK LINE 6 | 1,599 | FOOT | $1.25 | $0.9500 | $0.9500 | $1.20 | $1.25 | $1.10 | $0.9500 | |
| 51 | 78000500 | THPL PVT MK LINE 8 | 138 | FOOT | $1.60 | $1.95 | $1.95 | $2.20 | $1.60 | $2.25 | $1.95 | |
| 52 | 78000600 | THPL PVT MK LINE 12 | 415 | FOOT | $2.50 | $3.32 | $3.32 | $3.45 | $2.50 | $3.80 | $3.32 | |
| 53 | 78000650 | THPL PVT MK LINE 24 | 91 | FOOT | $5.35 | $5.75 | $5.75 | $6.00 | $5.35 | $6.29 | $5.75 |