16-11107-01-BR
- Let date
- Friday, February 27, 2026
- Contract
- 61M25 · job page
- District
- District 1
- County
- Will
- Highway
- Limits
- Rehabilitate of three-span RC channel beam bridge carrying Smith Road over Long Run Creek between W. 138th Street and W. 135th Street in Will County. Work includes replacement of existing channel beams with steel tub girder and concrete deck superstructure, substructure repair, pavement widening, HMA resurfacing and other required work.
- Classification
- ·
- Project number
Bidders 7
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $1,561,361 | ||
| 2 | Austin Tyler Construction, Inc. | $1,757,816 | +12.6% | |
| 3 | MYS, Incorporated | $1,866,929 | +19.6% | |
| 4 | Herlihy Mid-Continent Company | $1,944,577 | +24.5% | |
| 5 | Lorig Construction Company | $2,025,700 | +29.7% | |
| 6 | Areatha Construction Co., Inc. | $2,133,324 | +36.6% | |
| 7 | Rausch Infrastructure, LLC | $2,235,707 | +43.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 Austin Tyler Co… | #3 MYS, Incorporat… | #4 Herlihy Mid-Con… | #5 Lorig Construct… | #6 Areatha Constru… | #7 Rausch Infrastr… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | XX008195 | EXPLOR EXC UTILITY | 50 | FOOT | $0.0100 | $36.00 | $110.37 | $98.00 | $80.00 | $31.95 | $50.00 | |
| 2 | XX009569 | PRESS BRK STL TUB GIR | 3,427 | SQ FT | $139.50 | $144.00 | $144.25 | $185.00 | $145.00 | $137.25 | $175.00 | |
| 3 | X0326806 | WASHOUT BASIN | 1 | L SUM | $4,000.00 | $500.00 | $2,150.16 | $1,400.00 | $100.00 | $1,450.25 | $1,500.00 | |
| 4 | X2030300 | CHANNEL EXCAV SPL | 390 | CU YD | $50.00 | $58.00 | $96.16 | $75.00 | $75.00 | $133.00 | $200.00 | |
| 5 | X4021000 | TEMP ACCESS- PRIV ENT | 1 | EACH | $1,000.00 | $750.00 | $1,163.61 | $800.00 | $1,100.00 | $2,064.50 | $1,500.00 | |
| 6 | X4401198 | HMA SURF REM VAR DP | 375 | SQ YD | $20.00 | $9.50 | $33.11 | $18.37 | $20.00 | $42.00 | $20.00 | |
| 7 | X6310164 | TRAF BAR TERM TY 1 | 1 | EACH | $2,802.80 | $2,548.00 | $2,812.30 | $2,548.00 | $1,700.00 | $2,548.00 | $3,200.00 | |
| 8 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $35,000.00 | $23,500.00 | $25,888.75 | $17,000.00 | $142,000.00 | $19,000.00 | $15,000.00 | |
| 9 | X7200061 | TEMP INFO SIGNING | 107 | SQ FT | $30.00 | $15.00 | $19.86 | $18.00 | $20.00 | $17.00 | $30.00 | |
| 10 | X7240205 | REMOV SIGN COMPLETE | 2 | EACH | $357.50 | $150.00 | $386.30 | $350.00 | $750.00 | $1,800.00 | $90.00 | |
| 11 | X8900104 | TEMP TR SIGNAL TIMING | 2 | EACH | $660.00 | $900.00 | $662.23 | $900.00 | $600.00 | $600.00 | $700.00 | |
| 12 | Z0001900 | ASB BEARING PAD REMOV | 40 | EACH | $75.00 | $185.00 | $220.75 | $23.00 | $375.00 | $250.00 | $1,300.00 | |
| 13 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $15,000.00 | $16,000.00 | $13,796.60 | $17,100.00 | $25,000.00 | $35,000.00 | $15,000.00 | |
| 14 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 15 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | |
| 16 | 20101000 | TEMPORARY FENCE | 80 | FOOT | $8.80 | $8.00 | $4.14 | $4.00 | $5.00 | $12.00 | $17.00 | |
| 17 | 20101200 | TREE ROOT PRUNING | 2 | EACH | $600.00 | $50.00 | $607.05 | $300.00 | $1,000.00 | $450.00 | $640.00 | |
| 18 | 20200100 | EARTH EXCAVATION | 176 | CU YD | $37.50 | $93.00 | $108.64 | $26.50 | $95.00 | $82.35 | $90.00 | |
| 19 | 20201200 | REM & DISP UNS MATL | 180 | CU YD | $50.00 | $41.00 | $92.25 | $45.00 | $75.00 | $107.25 | $80.00 | |
| 20 | 21001000 | GEOTECH FAB F/GR STAB | 225 | SQ YD | $5.00 | $4.00 | $10.86 | $2.00 | $4.00 | $7.35 | $15.00 | |
| 21 | 21101625 | TOPSOIL F & P 6 | 1,450 | SQ YD | $6.60 | $6.00 | $13.55 | $6.00 | $13.00 | $15.50 | $14.00 | |
| 22 | 25000110 | SEEDING CL 1A | 0.25 | ACRE | $2,662.00 | $2,420.00 | $2,483.39 | $2,420.00 | $2,500.00 | $5,800.00 | $2,600.00 | |
| 23 | 25000314 | SEEDING CL 4B | 0.25 | ACRE | $3,993.00 | $3,630.00 | $7,726.10 | $3,630.00 | $7,000.00 | $6,800.00 | $8,000.00 | |
| 24 | 25000324 | SEEDING CL 5B | 0.25 | ACRE | $3,993.00 | $3,630.00 | $7,726.10 | $3,630.00 | $7,000.00 | $4,700.00 | $8,000.00 | |
| 25 | 25000400 | NITROGEN FERT NUTR | 25 | POUND | $3.30 | $3.00 | $5.52 | $3.00 | $5.00 | $2.50 | $5.00 | |
| 26 | 25000600 | POTASSIUM FERT NUTR | 25 | POUND | $3.30 | $3.00 | $5.52 | $3.00 | $5.00 | $2.50 | $5.00 | |
| 27 | 25100645 | WILDLIFE FRIENDLY ECB | 1,450 | SQ YD | $5.50 | $5.00 | $2.10 | $5.00 | $2.00 | $2.00 | $2.00 | |
| 28 | 28000305 | TEMP DITCH CHECKS | 150 | FOOT | $16.50 | $15.00 | $13.24 | $15.00 | $12.00 | $15.00 | $14.00 | |
| 29 | 28000400 | PERIMETER EROS BAR | 950 | FOOT | $3.30 | $2.50 | $4.41 | $3.00 | $4.00 | $4.00 | $5.00 | |
| 30 | 28100107 | STONE RIPRAP CL A4 | 570 | SQ YD | $80.00 | $97.00 | $129.54 | $113.00 | $120.00 | $116.65 | $130.00 | |
| 31 | 28200200 | FILTER FABRIC | 570 | SQ YD | $5.00 | $4.00 | $3.31 | $3.00 | $3.00 | $8.05 | $5.00 | |
| 32 | 30300001 | AGG SUBGRADE IMPROVE | 10 | CU YD | $100.00 | $66.00 | $117.93 | $82.00 | $120.00 | $101.65 | $100.00 | |
| 33 | 30300112 | AGG SUBGRADE IMPR 12 | 85 | SQ YD | $40.00 | $34.00 | $72.36 | $56.00 | $50.00 | $70.75 | $85.00 | |
| 34 | 35101600 | AGG BASE CSE B 4 | 210 | SQ YD | $7.50 | $10.50 | $22.57 | $15.00 | $15.00 | $36.30 | $62.00 | |
| 35 | 35102000 | AGG BASE CSE B 8 | 105 | SQ YD | $18.00 | $19.50 | $63.32 | $26.50 | $32.00 | $48.40 | $125.00 | |
| 36 | 40600290 | BIT MATLS TACK CT | 200 | POUND | $10.00 | $0.0100 | $0.0100 | $0.0100 | $0.1000 | $0.1000 | $0.0100 | |
| 37 | 40600982 | HMA SURF REM BUTT JT | 25 | SQ YD | $22.50 | $0.0100 | $30.90 | $84.71 | $90.00 | $50.00 | $100.00 | |
| 38 | 40603080 | HMA BC IL-19.0 N50 | 18 | TON | $200.00 | $180.00 | $303.52 | $435.64 | $455.00 | $382.00 | $500.00 | |
| 39 | 40604060 | HMA SC IL-9.5 D N50 | 49 | TON | $200.00 | $114.00 | $320.08 | $270.37 | $280.00 | $385.00 | $300.00 | |
| 40 | 42000080 | PVT CON PCC BR APP SL | 155 | SQ YD | $240.00 | $219.00 | $226.09 | $250.00 | $230.00 | $225.60 | $300.00 | |
| 41 | 42300200 | PCC DRIVEWAY PAVT 6 | 55 | SQ YD | $80.00 | $116.00 | $144.67 | $99.00 | $111.00 | $187.10 | $175.00 | |
| 42 | 44000100 | PAVEMENT REM | 365 | SQ YD | $15.00 | $17.00 | $45.04 | $15.00 | $33.00 | $31.55 | $40.00 | |
| 43 | 44000200 | DRIVE PAVEMENT REM | 56 | SQ YD | $10.00 | $29.00 | $32.94 | $25.00 | $31.00 | $24.80 | $27.00 | |
| 44 | 44201737 | CL D PATCH T1 8 | 20 | SQ YD | $110.00 | $139.00 | $320.08 | $229.69 | $125.00 | $355.00 | $130.00 | |
| 45 | 44201741 | CL D PATCH T2 8 | 20 | SQ YD | $110.00 | $139.00 | $320.08 | $213.45 | $125.00 | $355.00 | $130.00 | |
| 46 | 44201745 | CL D PATCH T3 8 | 20 | SQ YD | $110.00 | $139.00 | $320.08 | $194.00 | $125.00 | $355.00 | $130.00 | |
| 47 | 48101500 | AGGREGATE SHLDS B 6 | 35 | SQ YD | $15.00 | $28.00 | $55.19 | $45.00 | $40.00 | $36.70 | $100.00 | |
| 48 | 48203013 | HMA SHOULDERS 4 | 95 | SQ YD | $29.00 | $60.00 | $104.85 | $94.39 | $100.00 | $112.75 | $100.00 | |
| 49 | 50101500 | REM EXIST SUP-STR | 1 | EACH | $35,000.00 | $55,000.00 | $86,982.93 | $180,250.45 | $225,000.00 | $239,329.00 | $315,000.00 | |
| 50 | 50102400 | CONC REM | 3.3 | CU YD | $3,000.00 | $2,400.00 | $1,473.06 | $1,250.00 | $4,000.00 | $1,490.80 | $2,000.00 | |
| 51 | 50200100 | STRUCTURE EXCAVATION | 74 | CU YD | $45.00 | $73.00 | $115.91 | $50.00 | $90.00 | $105.55 | $160.00 | |
| 52 | 50201121 | COFFERDAM TYP 2 LOC 1 | 2 | EACH | $25,000.00 | $32,000.00 | $18,270.86 | $25,500.00 | $1,000.00 | $40,000.00 | $14,268.00 | |
| 53 | 50300225 | CONC STRUCT | 34.5 | CU YD | $3,000.00 | $4,550.00 | $2,934.10 | $3,000.00 | $5,000.00 | $5,086.15 | $3,500.00 | |
| 54 | 50300255 | CONC SUP-STR | 138.8 | CU YD | $1,080.00 | $2,135.00 | $2,144.64 | $1,680.00 | $1,350.00 | $2,022.45 | $1,100.00 | |
| 55 | 50300260 | BR DECK GROOVING | 527 | SQ YD | $15.00 | $12.00 | $9.97 | $16.77 | $12.00 | $11.45 | $13.00 | |
| 56 | 50300300 | PROTECTIVE COAT | 868 | SQ YD | $1.00 | $3.00 | $2.73 | $3.00 | $2.00 | $2.25 | $4.00 | |
| 57 | 50301350 | CONC SUPSTR APP SLAB | 93.2 | CU YD | $550.00 | $829.00 | $740.12 | $950.00 | $600.00 | $607.25 | $800.00 | |
| 58 | 50800205 | REINF BARS, EPOXY CTD | 76,840 | POUND | $2.25 | $2.00 | $1.99 | $1.33 | $1.50 | $1.55 | $1.90 | |
| 59 | 51500100 | NAME PLATES | 1 | EACH | $1,500.00 | $750.00 | $936.46 | $800.00 | $1,100.00 | $1,479.85 | $1,000.00 | |
| 60 | 53212754 | STR REP CON DP = < 5 | 20 | SQ FT | $250.00 | $435.00 | $441.49 | $145.00 | $550.00 | $416.70 | $292.00 | |
| 61 | 53212755 | STR REP CON DP OVER 5 | 70 | SQ FT | $250.00 | $435.00 | $248.34 | $105.00 | $575.00 | $317.60 | $315.00 | |
| 62 | 58600101 | GRANULAR BACKFILL STR | 64 | CU YD | $60.00 | $91.00 | $104.01 | $92.00 | $150.00 | $88.80 | $168.00 | |
| 63 | 59000200 | EPOXY CRACK INJECTION | 98 | FOOT | $75.00 | $60.00 | $110.37 | $60.00 | $70.00 | $65.00 | $70.00 | |
| 64 | 59100100 | GEOCOMPOSITE WALL DR | 42 | SQ YD | $35.00 | $42.00 | $66.23 | $25.00 | $45.00 | $68.60 | $40.00 | |
| 65 | 60100060 | CONC HDWL FOR P DRAIN | 4 | EACH | $400.00 | $550.00 | $578.23 | $430.00 | $800.00 | $1,100.00 | $1,364.00 | |
| 66 | 60146304 | P UNDR FOR STRUCT 4 | 164 | FOOT | $27.50 | $21.00 | $82.78 | $25.00 | $42.00 | $35.00 | $20.00 | |
| 67 | 63000007 | SPBGR TY B 6FT POSTS | 82 | FOOT | $51.51 | $47.00 | $51.69 | $46.83 | $50.00 | $46.85 | $52.00 | |
| 68 | 63100070 | TRAF BAR TERM T5 | 2 | EACH | $1,376.10 | $1,251.00 | $1,380.76 | $1,251.00 | $1,300.00 | $1,251.00 | $1,600.00 | |
| 69 | 63100085 | TRAF BAR TERM T6 | 2 | EACH | $4,362.60 | $3,966.00 | $4,377.39 | $3,966.00 | $4,100.00 | $3,966.00 | $5,200.00 | |
| 70 | 63100167 | TR BAR TRM T1 SPL TAN | 3 | EACH | $3,928.10 | $3,571.00 | $3,941.41 | $3,571.00 | $3,700.00 | $3,571.00 | $4,200.00 | |
| 71 | 63200310 | GUARDRAIL REMOV | 240 | FOOT | $9.02 | $8.00 | $9.05 | $8.20 | $8.50 | $8.20 | $9.75 | |
| 72 | 67000500 | ENGR FIELD OFFICE B | 6 | CAL MO | $5,000.00 | $2,000.00 | $4,414.91 | $5,300.00 | $4,000.00 | $2,500.00 | $4,500.00 | |
| 73 | 67100100 | MOBILIZATION | 1 | L SUM | $88,500.00 | $39,400.00 | $63,350.14 | $120,000.00 | $100,000.00 | $130,000.00 | $130,000.00 | |
| 74 | 70107025 | CHANGEABLE MESSAGE SN | 370 | CAL DA | $50.00 | $30.00 | $22.07 | $20.00 | $30.00 | $30.00 | $46.00 | |
| 75 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $38.50 | $35.00 | $38.63 | $35.00 | $35.00 | $35.00 | $58.00 | |
| 76 | 78000200 | THPL PVT MK LINE 4 | 1,870 | FOOT | $2.75 | $2.50 | $3.15 | $2.85 | $3.50 | $3.25 | $3.00 | |
| 77 | 78005110 | EPOXY PVT MK LINE 4 | 825 | FOOT | $6.38 | $5.80 | $4.25 | $3.82 | $7.00 | $7.00 | $7.00 | |
| 78 | 78200005 | GRDRAIL REF TYPE A | 8 | EACH | $13.20 | $12.00 | $13.24 | $12.00 | $12.00 | $12.00 | $23.00 | |
| 79 | 78300202 | PVT MKG REM WTR BLAST | 100 | SQ FT | $33.00 | $45.00 | $22.07 | $20.00 | $25.00 | $25.00 | $35.00 |