Filtered by: County: Madison Clear all
| Let date | Contract / PPS | County / Division | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| Dec 13, 2024 | 76U07 | MadisonDistrict 8 | Bridge joint replacement/repairs and bridge deck overlay on SN 060-0014 and 060-0015 carrying I-55/70 over Beltline Road. | — | Executed | Keeley & Sons, Inc. $2,833,156 · | ||
| Jan 17, 2025 | 76L46 | MadisonDistrict 8 | 0.8 miles of patching, resurfacing and installing bus pads on IL 140 from 0.15 miles east of IL 111 to Sanders Street in Bethalto. | — | Executed | Charles E. Mahoney Co. $619,161 · | ||
| Jan 17, 2025 | 76R13 | MadisonDistrict 8 | Bridge deck sealing on the McKinley Bridge (SN 060-6002) over the Mississippi River. | — | Executed | M & M Concrete, Inc. $64,938 · | ||
| Jan 17, 2025 | 76T49 | MadisonDistrict 8 | Traffic signal modernization at 3 intersections: IL 203 at Johnson/Fehling Road; IL 3 at Hawthorne Street; IL 111 at Horseshoe Lake Road. | — | Executed | Electrico, Inc. $1,030,879 · | ||
| Jan 17, 2025 | 76T87 | MadisonDistrict 8 | Bridge deck sealing at various locations in Madison County. | — | Executed | All States Painting, Inc. $581,300 · | ||
| Jan 17, 2025 | 97789 | MadisonDistrict 8 | Sidewalk construction along Pearl Street and a new pedestrian crossing at the Union Pacific and Kansas City Southern Railroads in Godfrey. | — | Executed | Stutz Excavating, Inc. $116,495 · | ||
| Jan 17, 2025 | 97843 | MadisonDistrict 8 | HMA resurfacing on Cougar Drive from Junction Drive tot Illini Drive, and HMA resurfacing and reconstruction on Junction Drive from Cougar to Troy Road in Glen Carbon. | — | Executed | Keller Construction, Inc. $949,494 · | ||
| Jan 17, 2025 | 97847 | MadisonDistrict 8 | Resurfacing Erwin Plegge Boulevard from Bethalto Road to Prairie Steet in Bethalto | — | Executed | Charles E. Mahoney Co. $670,202 · | ||
| Jan 17, 2025 | 97849 | MadisonDistrict 8 | Construct a single span 54" plate girder structure with concrete deck to carry Lee Road over Sugar Creek. | — | Executed | C-Hill Civil Contractors, Inc. $1,092,439 · | ||
| Jan 17, 2025 | 97853 | MadisonDistrict 8 | Construct a shared-use path along IL 157 from West Schwarz Street to Enclave Boulevard in Edwardsville. | — | Executed | Keller Construction, Inc. $531,755 · | ||
| Mar 7, 2025 | 76U15 | MadisonDistrict 8 | 0.8 miles of patching and resurfacing on IL 162 from 0.4 miles west of I-255 to 0.4 miles east of I-255. | — | Executed | The Kilian Corporation $564,097 · | ||
| Mar 7, 2025 | 76U20 | MadisonDistrict 8 | 0.7 miles of chip seal on West Delmar Avenue from State Street in Alton to IL 3 in Godfrey. | — | Rejected | DMS Contracting, Inc. $107,062 · | ||
| Mar 7, 2025 | 97793 | MadisonDistrict 8 | Reconstruction of the IL 159 and Glen Carbon Road Intersection in Glen Carbon to create North and East Bound Right Turn Lanes. | — | Executed | Keller Construction, Inc. $1,439,471 · | ||
| Mar 7, 2025 | 97856 | MadisonDistrict 8 | Construction of a Shared-Use Path along Glen Carbon Road from Lakewood Drive to Oakdale Lake Drive in Glen Carbon. | — | Executed | Baxmeyer Construction, Inc. $954,648 · | ||
| Apr 25, 2025 | 76T07 | MadisonDistrict 8 | Bridge painting on I-55 under Goshen Road (SN 060-0178). | — | Executed | ERA-Valdivia Contractors, Inc. $278,460 · | ||
| Apr 25, 2025 | 76U26 | MadisonDistrict 8 | 6.5 miles of resurfacing on IL 3 (Main Street) from Northgate Industrial Drive to the McKinley Bridge approach. | — | Executed | Charles E. Mahoney Co. $25,874,598 · | ||
| Apr 25, 2025 | 76U27 | MadisonDistrict 8 | 1.3 miles of resurfacing with guardrail upgrades on IL 143 from Kendall Drive to 0.1 miles west of Oasis Drive. | — | Executed | Charles E. Mahoney Co. $1,613,743 · | ||
| Apr 25, 2025 | 97839 | MadisonDistrict 8 | HMA resurfacing on Esic Drive from University Drive to IL 157 in Edwardsville. Includes; ADA improvements, storm sewer, and signage. | — | Executed | Charles E. Mahoney Co. $615,086 · | ||
| Apr 25, 2025 | 97862 | MadisonDistrict 8 | Pavement reconstruction, sidewalk, curb and gutter on Pierce Lane from north of Stamper Lane to Stamper lane in Godfrey. | — | Executed | Keller Construction, Inc. $1,917,545 · | ||
| Jun 13, 2025 | 76F82 | MadisonSt. ClairDistrict 8 | Force main cleaning at the Missouri Avenue pump station in East St. Louis, the 25th Street pump station in East St. Louis and the Venice pump station in Venice. | — | Executed | Haier Plumbing and Heating, Inc. $614,950 · | ||
| Jun 13, 2025 | 76T77 | MadisonDistrict 8 | Traffic signal replacement at the intersection of IL 111/140 at Thelma Avenue / Franklin Avenue in Cottage Hills. | — | Executed | Gerstner Electric, Inc. $678,250 · | ||
| Jun 13, 2025 | 76U25 | ClintonMadisonSt. ClairDistrict 8 | Traffic signal modernization at various locations throughout District 8. | — | Executed | Gerstner Electric, Inc. $669,700 · | ||
| Jun 13, 2025 | 76U37 | MadisonMarionSt. ClairDistrict 8 | Pump repairs at the Bowman Pump Station in East St. Louis, Grey's Pump Station in Pontoon Beach, Venice Pump Station in Venice, 9th Street Pump Station in East St. Louis and Centralia Pump Station in Centralia. | — | Rejected | Davinroy Mechanical Contractor, Inc. $1,593,635 · | ||
| Jun 13, 2025 | 97870 | MadisonDistrict 8 | Construction of an HMA multi-use path on a lime-modified subgrade adjacent to US 40 from South Main Street to Creekside Drive in Troy. | — | Executed | Stutz Excavating, Inc. $683,304 · | ||
| Aug 1, 2025 | 76U65 | MadisonDistrict 8 | 1.4 miles of slurry seal on IL 159 from Clay Street to Kinloch Avenue in Collinsville. | — | Executed | Microsurfacing Contractors, LLC, a Division of Byrne and Jones Holding Company $537,958 · | ||
| Aug 1, 2025 | 97826 | MadisonDistrict 8 | HMA resurfacing with driveways, and curb and gutter on Keebler Road from Sher Nan Drive to West Main Street in Maryville. | — | Executed | Stutz Excavating, Inc. $829,420 · | ||
| Sep 19, 2025 | 76F84 | MadisonDistrict 8 | Intersection reconstruction on IL 3 at Delmar Avenue and at Pierce Lane, both in Godfrey. | — | Executed | Stutz Excavating, Inc. $10,524,883 · | ||
| Sep 19, 2025 | 97833 | MadisonDistrict 8 | Reconstruction of Summit Avenue with a shared-use path from Notting Hill Court to Dooner Drive in Collinsville. | — | Executed | Keller Construction, Inc. $2,218,364 · | ||
| Sep 19, 2025 | 97868 | MadisonDistrict 8 | Contruction of a new sidewalk and shared-use path from Pontoon Road to Raes Creek Drive in Granite City. | — | Executed | Kinney Contractors, Inc. $612,809 · | ||
| Sep 19, 2025 | 97869 | MadisonDistrict 8 | Resurfacing on Madison Avenue from 14th Street to 3rd Street in Madison. | — | Executed | Stutz Excavating, Inc. $3,789,307 · | ||
| Sep 19, 2025 | 97874 | MadisonDistrict 8 | Reconstruction of C Street from West 7th Street to 1st Street, and the reconstruction of West 7th Street from C Street to D Street within America's Central Post District. | — | Executed | RCS Construction, Inc. $2,566,151 · | ||
| Jan 16, 2026 | 76A46 | MadisonDistrict 8 | Intersection improvements with signals and bridge replacement on IL 162/IL 157 in Glen Carbon. | — | Executed | Keller Construction, Inc. $17,570,642 · | ||
| Jan 16, 2026 | 76E84 | MadisonSt. ClairDistrict 8 | 6.4 miles of resurfacing and bridge repairs along I-55/I-70 from the I-64 (Tri-Level) interchange to 0.5 miles west of Black Lane. Includes lighting work from east of I-64 (Tri-Level) in East St. Louis to east of IL 203 in Fairmont City. | — | Executed | The Kilian Corporation & Christ Brothers Asphalt & Keeley & Sons, Inc. tri-venture $99,865,324 · | ||
| Jan 16, 2026 | 76N65 | MadisonDistrict 8 | Bridge superstructure replacement on IL 3 (Cedar Street) over the rail yard, south of Niedringhaus Avenue in Granite City. (SN 060-0202) | — | Executed | Plocher Construction Company, Inc. $17,564,000 · | ||
| Jan 16, 2026 | 76U88 | MadisonSt. ClairDistrict 8 | Well treatment at various locations in District 8. | — | Executed | Layne Christensen Company $853,559 · | ||
| Jan 16, 2026 | 97851 | MadisonDistrict 8 | Resurfacing on South University Drive from University Park Drive to 0.1 mile south of Stadium Drive. | — | Executed | The Kilian Corporation $982,094 · | ||
| Jan 16, 2026 | 97876 | MadisonDistrict 8 | Intersection resurfacing and sidewalk replacement on Clay Street between Seminary Street and Morrison Avenue in Collinsville. | — | Executed | Hank's Excavating & Landscaping, Inc. $790,083 · | ||
| Jan 16, 2026 | 97881 | MadisonDistrict 8 | HMA resurfacing on St. Louis Avenue from West Main Street to Cotter Avenue in East Alton. Includes; pavement patching, milling, sidewalk, curb and gutter. | — | Executed | Stutz Excavating, Inc. $1,254,922 · | ||
| Jan 16, 2026 | 97883 | MadisonDistrict 8 | Construct a shared-use path adjacent to St. Louis Steet from West Street to 2nd Street in Edwardsville. Includes; HMA milling and overlay, sidewalk, barrier curb and pavement markings. | — | Executed | Stutz Excavating, Inc. $1,135,167 · | ||
| Feb 27, 2026 | 76U42 | MadisonDistrict 8 | 7 miles of microsurfacing on I-255 from the St. Clair County line to I-270. | — | Executed | Microsurfacing Contractors, LLC, a Division of Byrne and Jones Holding Company $6,640,925 · | ||
| Feb 27, 2026 | 76U43 | MadisonDistrict 8 | 3.9 miles of resurfacing on IL 255 from 0.1 miles north of Seminary Road to US 67 in Godfrey. | — | Executed | Charles E. Mahoney Co. $7,764,431 · | ||
| Feb 27, 2026 | 76U78 | MadisonDistrict 8 | 2.3 miles of patching on IL 203 from the I-270 westbound ramps to Branding Avenue in Granite City. | — | Executed | G. M. Sipes Construction, Inc. $898,651 · | ||
| Feb 27, 2026 | 76V04 | JerseyMadisonDistrict 8 | Weed control at various locations in Madison and Jersey Counties. | — | Executed | The Daltons Inc. $414,310 · | ||
| Feb 27, 2026 | 97882 | MadisonDistrict 8 | HMA resurfacing, curb and gutter replacement, sidewalk replacement, pavement markings, and pedestrian traffic signal improvements on Madison Avenue from 27th St. to 23rd St. in Granite City. | — | Executed | Stutz Excavating, Inc. $2,795,529 · | ||
| Apr 24, 2026 | 46670 | JerseyMadisonSt. ClairDistrict 8 | Pavement marking replacement at various locations in Jersey, Madison and St. Clair Counties. | — | Executed | A. C. Pavement Striping Co. $202,951 · | ||
| Apr 24, 2026 | 76U66 | MadisonDistrict 8 | 21.4 miles of underdrain cleaning and headwall replacement on IL 255 from I-270 to US 67 in Godfrey. | — | Rejected | |||
| Apr 24, 2026 | 76U84 | MadisonDistrict 8 | Bridge painting on SN 060-0215 carrying Fairmont Avenue over I-255. | — | Executed | ERA-Valdivia Contractors, Inc. $461,190 · | ||
| Apr 24, 2026 | 76U85 | MadisonDistrict 8 | Bridge painting on SN 060-0213 carrying IL 3 over IL 140 in Alton. | — | Executed | ERA-Valdivia Contractors, Inc. $578,070 · | ||
| Apr 24, 2026 | 76U87 | MadisonDistrict 8 | Bridge painting on SN 060-0073 carrying IL 140 over I-55 in Hamel and SN 060-0077 carrying US 40 over Silver Creek near Troy. | — | Executed | ERA-Valdivia Contractors, Inc. $956,121 · | ||
| Apr 24, 2026 | 97840 | MadisonDistrict 8 | HMA resurfacing, patching, sidewalks, curb and gutter on Wood River Avenue from Ferguson Avenue to the north city limits of Wood River. | — | Executed | Christ Bros. Asphalt, Inc. $1,584,636 · | ||
| Jun 12, 2026 | 76R32 | MadisonDistrict 8 | New bridge deck on SN 060-0120 carrying IL 111 / IL 3 over Rodgers Avenue and Bloomer Drive in Alton. | — | Executed | Stutz Excavating, Inc. $4,611,184 · | ||
| Jun 12, 2026 | 76U38 | MadisonSt. ClairDistrict 8 | Traffic signal replacement at various locations in Madison and St. Clair Counties. | — | Executed | Gerstner Electric, Inc. $2,898,157 · | ||
| Jun 12, 2026 | 76U81 | MadisonSt. ClairDistrict 8 | Bridge cleaning at various locations in Madison and St. Clair counties. | — | Executed | M & M Concrete, Inc. $560,000 · | ||
| Jun 12, 2026 | 76U86 | MadisonDistrict 8 | Bridge painting on IL 3 over NS Railroad in Granite City. (SN 060-0193 and 060-0194) | — | Executed | Eagle Painting & Maintenance Company, Inc. $314,406 · | ||
| Jun 12, 2026 | 76V03 | MadisonDistrict 8 | Bridge painting on SN 060-0350 and 060-0351 carrying I-270 over the Mississippi River. | — | Executed | Capital Industrial Services, LLC $2,933,300 · | ||
| Jun 12, 2026 | 76V06 | JerseyMadisonDistrict 8 | 40.25 miles of tree removal at various locations in Madison and Jersey Counties. | — | Executed | Homer Tree Service, Inc. $762,370 · | ||
| Jun 12, 2026 | 76V17 | MadisonDistrict 8 | 10.4 miles of bridge repairs and resurfacing on I-55/I-70/US 40 from 0.5 miles west of Black Lane to 0.4 miles east of IL 159. | — | Executed | The Kilian Corporation & Christ Brothers Asphalt & Keeley & Sons, Inc. tri-venture $24,110,330 · | ||
| Jun 12, 2026 | 97884 | MadisonDistrict 8 | Resurfacing North Alby Street from Humbert Road to Wesley Way in the village of Godfrey. | — | Executed | Stutz Excavating, Inc. $1,096,234 · | ||
| Jun 12, 2026 | 97896 | MadisonDistrict 8 | Sidewalk construction along various streets in the village of Worden. | — | Executed | Stutz Excavating, Inc. $295,673 · | ||
| Jun 12, 2026 | 97903 | MadisonDistrict 8 | Traffic signal installation at the intersection of Horseshoe Lake Road and McDonough Lake Road in the city of Collinsville. | — | Executed | Gerstner Electric, Inc. $361,779 · | ||
| Jul 31, 2026 | 76V11 | MadisonDistrict 8 | 13 miles of pavement patching on IL 140 from Hamel to Alhambra and on IL 4 from IL 143 to south of US 40. | — | Executed | Kinney Contractors, Inc. $951,953 · | ||
| Jul 31, 2026 | 76V22 | MadisonSt. ClairDistrict 8 | 2 miles of chip seal on IL 111 / Collinsville Road from 0.1 miles west of Roselake Drive to a joint east of Jondro Avenue in Fairmont City. | — | Executed | DMS Contracting, Inc. $899,907 · | ||
| Sep 18, 2026 | 97908 | MadisonDistrict 8 | Replacement of PPC Deck Beams on SN 060-6113 carrying Pebble Creek Drive over Black Creek in Alton. Includes concrete wearing surface, HMA approach pavement, and drainage improvements. | — | Awarded |
1–63 of 63
Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.