(103,104)BR-1
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Plocher Construction Company, Inc. Low bidder | $17,564,000 | ||
| 2 | Millstone Weber LLC | $17,966,964 | +2.3% | |
| 3 | Keeley & Sons, Inc. | $20,720,600 | +18.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Plocher Constru… | #2 Millstone Weber… | #3 Keeley & Sons, … |
|---|---|---|---|---|---|---|---|---|
| 1 | X4400110 | TEMP PAVT REMOVAL | 618 | SQ YD | $23.50 | $26.00 | $21.00 | |
| 2 | X4402400 | CURB REMOVAL SPL | 56 | FOOT | $27.50 | $28.75 | $57.35 | |
| 3 | X4402815 | ISLAND PAVT RM & REPL | 32 | SQ FT | $81.50 | $18.75 | $167.80 | |
| 4 | X4403300 | CONC MEDIAN REMOV | 1,870 | SQ FT | $6.80 | $3.30 | $28.90 | |
| 5 | X5030250 | BR DECK GROOVING LONG | 5,198 | SQ YD | $7.40 | $8.40 | $10.31 | |
| 6 | X5080530 | BAR TERMINATORS | 1,212 | EACH | $30.50 | $20.00 | $30.60 | |
| 7 | X5230174 | DRAINAGE SCUPPR DS-11 | 4 | EACH | $2,730.00 | $2,200.00 | $2,780.00 | |
| 8 | X5537800 | SS CLEANED 12 | 179 | FOOT | $12.50 | $25.00 | $59.80 | |
| 9 | X5538200 | SS CLEANED 24 | 61 | FOOT | $22.80 | $25.00 | $63.65 | |
| 10 | X6010003 | PIPE DRAIN REMOVAL | 682 | FOOT | $12.60 | $2.80 | $13.90 | |
| 11 | X6020086 | MANHOLE SPL FRAME/LID | 1 | EACH | $9,000.00 | $12,300.00 | $1,780.00 | |
| 12 | X6370700 | CONC BAR TRANS SPL | 28 | FOOT | $222.00 | $520.00 | $1,170.30 | |
| 13 | X6640300 | CH LK FENCE REMOV | 728 | FOOT | $9.63 | $10.00 | $13.85 | |
| 14 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $70,150.00 | $48,000.00 | $88,935.00 | |
| 15 | X7200201 | WIDTH RESTRICT SIGN | 1 | L SUM | $5,500.00 | $1,500.00 | $1,530.00 | |
| 16 | Z0001002 | GDRL AGG EROS CONT | 2,233 | TON | $58.00 | $42.00 | $33.10 | |
| 17 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $75,000.00 | $89,000.00 | $75,000.00 | |
| 18 | Z0018500 | DRAINAGE STR CLEANED | 5 | EACH | $2,700.00 | $830.00 | $1,980.00 | |
| 19 | Z0029090 | DIAMOND GRIND BR SEC | 6,299 | SQ YD | $11.00 | $9.60 | $11.98 | |
| 20 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $8,000.00 | $53,000.00 | $150,000.00 | |
| 21 | Z0062456 | TEMP PAVEMENT | 618 | SQ YD | $130.00 | $85.00 | $96.13 | |
| 22 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 23 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 24 | 20200100 | EARTH EXCAVATION | 1,415 | CU YD | $16.00 | $27.25 | $33.65 | |
| 25 | 20201200 | REM & DISP UNS MATL | 185 | CU YD | $52.00 | $31.00 | $52.00 | |
| 26 | 20400800 | FURNISHED EXCAVATION | 685 | CU YD | $32.00 | $55.00 | $37.80 | |
| 27 | 20800150 | TRENCH BACKFILL | 15 | CU YD | $100.00 | $43.00 | $139.40 | |
| 28 | 21400100 | GRADING & SHAP DITCH | 319 | FOOT | $16.00 | $22.75 | $17.85 | |
| 29 | 25000210 | SEEDING CL 2A | 1 | ACRE | $7,515.00 | $4,500.00 | $2,040.00 | |
| 30 | 25000400 | NITROGEN FERT NUTR | 57 | POUND | $1.50 | $5.00 | $4.08 | |
| 31 | 25000500 | PHOSPHORUS FERT NUTR | 57 | POUND | $1.50 | $5.00 | $4.08 | |
| 32 | 25000600 | POTASSIUM FERT NUTR | 57 | POUND | $1.50 | $5.00 | $4.08 | |
| 33 | 25100630 | EROSION CONTR BLANKET | 3,011 | SQ YD | $3.50 | $2.30 | $3.06 | |
| 34 | 28000250 | TEMP EROS CONTR SEED | 195.3 | POUND | $24.00 | $10.00 | $3.57 | |
| 35 | 28000305 | TEMP DITCH CHECKS | 90 | FOOT | $25.00 | $15.00 | $4.08 | |
| 36 | 28000400 | PERIMETER EROS BAR | 3,085 | FOOT | $4.00 | $5.50 | $2.04 | |
| 37 | 28000510 | INLET FILTERS | 40 | EACH | $600.00 | $150.00 | $487.10 | |
| 38 | 28001100 | TEMP EROS CONTR BLANK | 9,418 | SQ YD | $2.50 | $1.50 | $2.04 | |
| 39 | 28100107 | STONE RIPRAP CL A4 | 415 | SQ YD | $75.00 | $94.00 | $87.90 | |
| 40 | 28200200 | FILTER FABRIC | 1,655 | SQ YD | $3.10 | $4.60 | $5.35 | |
| 41 | 30300112 | AGG SUBGRADE IMPR 12 | 3,041 | SQ YD | $40.00 | $26.75 | $33.80 | |
| 42 | 31100300 | SUB GRAN MAT A 4 | 3,041 | SQ YD | $11.25 | $15.75 | $11.15 | |
| 43 | 35101100 | AGG BASE CSE A 12 | 25 | SQ YD | $75.00 | $82.00 | $121.85 | |
| 44 | 42000080 | PVT CON PCC BR APP SL | 511 | SQ YD | $105.00 | $180.00 | $187.35 | |
| 45 | 42000405 | PCC PVT 9 1/4 | 2,399 | SQ YD | $110.00 | $160.00 | $117.70 | |
| 46 | 42001300 | PROTECTIVE COAT | 3,868 | SQ YD | $3.00 | $2.50 | $3.70 | |
| 47 | 44000100 | PAVEMENT REM | 2,870 | SQ YD | $15.00 | $21.25 | $23.40 | |
| 48 | 44000300 | CURB REM | 1,858 | FOOT | $6.00 | $4.80 | $15.90 | |
| 49 | 44000500 | COMB CURB GUTTER REM | 2,271 | FOOT | $6.00 | $26.25 | $19.80 | |
| 50 | 44001980 | CONC BARRIER REMOV | 2,920 | FOOT | $24.00 | $29.75 | $46.80 | |
| 51 | 44004250 | PAVED SHLD REMOVAL | 1,352 | SQ YD | $14.50 | $24.25 | $16.75 | |
| 52 | 44201337 | CL C PATCH T1 9 | 18 | SQ YD | $350.00 | $290.00 | $267.90 | |
| 53 | 44201345 | CL C PATCH T3 9 | 20 | SQ YD | $350.00 | $210.00 | $267.90 | |
| 54 | 48203029 | HMA SHOULDERS 8 | 671 | SQ YD | $126.35 | $130.00 | $128.88 | |
| 55 | 48300405 | PCC SHOULDERS 9 1/4 | 753 | SQ YD | $110.00 | $150.00 | $111.85 | |
| 56 | 50101500 | REM EXIST SUP-STR | 1 | EACH | $1,012,400.00 | $1,300,000.00 | $1,400,000.00 | |
| 57 | 50102400 | CONC REM | 340.1 | CU YD | $495.00 | $640.00 | $1,390.00 | |
| 58 | 50104650 | SLOPE WALL REMOV | 928 | SQ YD | $20.00 | $11.25 | $49.90 | |
| 59 | 50157300 | PROTECTIVE SHIELD | 6,845 | SQ YD | $100.00 | $96.00 | $3.35 | |
| 60 | 50200100 | STRUCTURE EXCAVATION | 722 | CU YD | $32.00 | $31.00 | $43.65 | |
| 61 | 50300225 | CONC STRUCT | 1,009.9 | CU YD | $1,000.00 | $1,800.00 | $1,987.30 | |
| 62 | 50300255 | CONC SUP-STR | 2,257.8 | CU YD | $1,400.00 | $1,300.00 | $1,892.85 | |
| 63 | 50300300 | PROTECTIVE COAT | 8,643 | SQ YD | $3.00 | $2.50 | $4.55 | |
| 64 | 50301350 | CONC SUPSTR APP SLAB | 283.2 | CU YD | $425.00 | $600.00 | $597.70 | |
| 65 | 50401305 | F&E PP CON BEAM IL27N | 8,097 | FOOT | $565.00 | $520.00 | $592.85 | |
| 66 | 50800205 | REINF BARS, EPOXY CTD | 884,140 | POUND | $1.60 | $1.40 | $2.15 | |
| 67 | 50800515 | BAR SPLICERS | 36 | EACH | $85.00 | $71.00 | $94.91 | |
| 68 | 51100100 | SLOPE WALL 4 | 1,356 | SQ YD | $160.00 | $175.00 | $147.60 | |
| 69 | 51500100 | NAME PLATES | 1 | EACH | $1,967.57 | $1,300.00 | $1,687.90 | |
| 70 | 52000030 | PREF JOINT SEAL 2 1/2 | 1,302 | FOOT | $64.00 | $66.00 | $93.45 | |
| 71 | 52000110 | PREF JT STRIP SEAL | 210 | FOOT | $160.00 | $450.00 | $467.35 | |
| 72 | 52100010 | ELAST BEARING ASSY T1 | 238 | EACH | $1,360.00 | $1,300.00 | $1,390.00 | |
| 73 | 52100510 | ANCHOR BOLTS 3/4 | 28 | EACH | $147.00 | $130.00 | $123.90 | |
| 74 | 52100520 | ANCHOR BOLTS 1 | 476 | EACH | $188.00 | $160.00 | $89.85 | |
| 75 | 52200010 | TEMP SHT PILING | 794 | SQ FT | $75.00 | $40.00 | $89.70 | |
| 76 | 53212754 | STR REP CON DP = < 5 | 78 | SQ FT | $106.00 | $190.00 | $237.80 | |
| 77 | 54248510 | CONCRETE COLLAR | 1 | CU YD | $400.00 | $760.00 | $4,980.00 | |
| 78 | 550A0340 | STORM SEW CL A 2 12 | 6 | FOOT | $420.00 | $220.00 | $211.00 | |
| 79 | 550A0360 | STORM SEW CL A 2 15 | 22 | FOOT | $270.00 | $190.00 | $97.80 | |
| 80 | 550A0410 | STORM SEW CL A 2 24 | 6 | FOOT | $460.00 | $260.00 | $269.80 | |
| 81 | 55100500 | STORM SEWER REM 12 | 6 | FOOT | $130.00 | $53.00 | $221.00 | |
| 82 | 55100700 | STORM SEWER REM 15 | 22 | FOOT | $66.00 | $35.00 | $47.00 | |
| 83 | 55101200 | STORM SEWER REM 24 | 6 | FOOT | $130.00 | $53.00 | $217.00 | |
| 84 | 58600101 | GRANULAR BACKFILL STR | 384 | CU YD | $75.00 | $96.00 | $78.15 | |
| 85 | 58700300 | CONCRETE SEALER | 3,236 | SQ FT | $1.25 | $2.10 | $3.95 | |
| 86 | 59000200 | EPOXY CRACK INJECTION | 4 | FOOT | $175.00 | $75.00 | $598.85 | |
| 87 | 59100100 | GEOCOMPOSITE WALL DR | 202 | SQ YD | $30.00 | $41.00 | $69.80 | |
| 88 | 60100060 | CONC HDWL FOR P DRAIN | 4 | EACH | $1,900.00 | $360.00 | $397.40 | |
| 89 | 60146304 | P UNDR FOR STRUCT 4 | 282 | FOOT | $15.00 | $39.00 | $17.90 | |
| 90 | 60500060 | REMOV INLETS | 12 | EACH | $500.00 | $790.00 | $697.00 | |
| 91 | 60600605 | CONC CURB TB | 1,086.5 | FOOT | $78.00 | $66.00 | $29.90 | |
| 92 | 60618320 | CONC MEDIAN SURF 6 | 1,747 | SQ FT | $10.00 | $22.75 | $23.90 | |
| 93 | 60622400 | CONC MED TSM6.06 | 2,289.5 | SQ FT | $12.00 | $26.25 | $18.90 | |
| 94 | 63000001 | SPBGR TY A 6FT POSTS | 2,237.5 | FOOT | $29.00 | $29.00 | $27.54 | |
| 95 | 63100045 | TRAF BAR TERM T2 | 2 | EACH | $2,000.00 | $2,000.00 | $1,963.50 | |
| 96 | 63100070 | TRAF BAR TERM T5 | 2 | EACH | $1,900.00 | $1,900.00 | $1,402.50 | |
| 97 | 63100085 | TRAF BAR TERM T6 | 2 | EACH | $5,000.00 | $5,000.00 | $3,748.50 | |
| 98 | 63100167 | TR BAR TRM T1 SPL TAN | 2 | EACH | $4,200.00 | $4,200.00 | $3,391.50 | |
| 99 | 63200310 | GUARDRAIL REMOV | 2,181 | FOOT | $6.00 | $7.30 | $7.00 | |
| 100 | 63700280 | CONC BAR 2F 44HT | 1,029 | FOOT | $225.00 | $160.00 | $149.60 | |
| 101 | 63700900 | CONC BARRIER BASE | 1,116 | FOOT | $54.00 | $61.00 | $59.80 | |
| 102 | 63800920 | MOD GLAR SCR SYS TEMP | 2,749 | FOOT | $6.00 | $6.00 | $6.12 | |
| 103 | 64300770 | IMP ATTEN SU NAR TL3 | 1 | EACH | $35,500.00 | $36,000.00 | $35,241.00 | |
| 104 | 66400305 | CH LK FENCE 6 | 728 | FOOT | $46.00 | $46.00 | $36.72 | |
| 105 | 66402900 | CH LK GATE 6X6 SINGL | 4 | EACH | $1,475.00 | $1,500.00 | $484.50 | |
| 106 | 66900200 | NON SPL WASTE DISPOSL | 650 | CU YD | $55.00 | $35.00 | $103.88 | |
| 107 | 66900530 | SOIL DISPOSAL ANALY | 2 | EACH | $1,350.00 | $1,400.00 | $1,377.00 | |
| 108 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,200.00 | $2,300.00 | $2,244.00 | |
| 109 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,200.00 | $2,500.00 | $2,244.00 | |
| 110 | 66901006 | REG SUB MON | 10 | CAL DA | $1,115.00 | $950.00 | $117.30 | |
| 111 | 67000400 | ENGR FIELD OFFICE A | 8 | CAL MO | $650.00 | $6,000.00 | $5,790.00 | |
| 112 | 67100100 | MOBILIZATION | 1 | L SUM | $1,220,000.00 | $1,050,000.00 | $1,250,000.00 | |
| 113 | 70103815 | TR CONT SURVEILLANCE | 540 | CAL DA | $500.00 | $250.00 | $0.0100 | |
| 114 | 70107025 | CHANGEABLE MESSAGE SN | 56 | CAL DA | $250.00 | $80.00 | $81.60 | |
| 115 | 70300241 | TEMP PVT MK LINE 6 - PAINT | 4,240 | FOOT | $0.8700 | $1.50 | $1.53 | |
| 116 | 70307100 | TEMP PVT MK LTR & SYM T4 TAPE | 256 | SQ FT | $15.40 | $16.00 | $16.32 | |
| 117 | 70307130 | TEMP PVT MK L6 T4 TAPE | 60,495 | FOOT | $2.70 | $2.40 | $2.40 | |
| 118 | 70307160 | TEMP PVT MK L12 T4 TAPE | 229 | FOOT | $5.00 | $4.70 | $4.80 | |
| 119 | 70307210 | TEMP PVT MK L24 T4 TAPE | 12 | FOOT | $14.00 | $9.40 | $9.59 | |
| 120 | 70400100 | TEMP CONC BARRIER | 3,400 | FOOT | $56.00 | $53.00 | $62.00 | |
| 121 | 70400125 | PIN TEMP CONC BARRIER | 474 | EACH | $56.00 | $75.00 | $69.90 | |
| 122 | 70400200 | REL TEMP CONC BARRIER | 2,988 | FOOT | $3.00 | $12.25 | $8.90 | |
| 123 | 70600250 | IMP ATTN TEMP NRD TL3 | 2 | EACH | $6,500.00 | $6,500.00 | $8,970.00 | |
| 124 | 70600350 | IMP ATTN REL NRD TL3 | 1 | EACH | $400.00 | $400.00 | $2,290.00 | |
| 125 | 72400205 | REM & REL SIGN PANEL ASMBLY TA | 9 | EACH | $2,200.00 | $1,300.00 | $1,480.20 | |
| 126 | 72400210 | REM & REL SIGN PANEL ASMBLY TB | 2 | EACH | $2,200.00 | $1,300.00 | $1,390.00 | |
| 127 | 78006100 | PREF THPL PM LTR-SYM | 128 | SQ FT | $18.00 | $26.50 | $18.36 | |
| 128 | 78006130 | PREF THPL PM LINE 6 | 22,504 | FOOT | $4.92 | $9.50 | $5.02 | |
| 129 | 78006150 | PREF THPL PM LINE 12 | 43 | FOOT | $10.00 | $5.00 | $10.20 | |
| 130 | 78006180 | PREF THPL PM LINE 24 | 96 | FOOT | $18.00 | $10.00 | $18.36 | |
| 131 | 78009006 | MOD URETH PM LINE 6 | 4,950 | FOOT | $5.00 | $1.00 | $5.10 | |
| 132 | 78100100 | RAISED REFL PAVT MKR | 428 | EACH | $44.72 | $61.00 | $46.16 | |
| 133 | 78200005 | GRDRAIL REF TYPE A | 46 | EACH | $10.00 | $10.00 | $12.24 | |
| 134 | 78200010 | BARR WALL REF TYPE B | 60 | EACH | $30.00 | $10.00 | $25.00 | |
| 135 | 78300200 | RAISED REF PVT MK REM | 478 | EACH | $17.00 | $33.00 | $5.10 | |
| 136 | 78300202 | PVT MKG REM WTR BLAST | 7,465 | SQ FT | $2.60 | $2.00 | $2.66 | |
| 137 | 81028200 | UNDRGRD C GALVS 2 | 75 | FOOT | $57.00 | $50.00 | $58.09 | |
| 138 | 85000200 | MAIN EX TR SIG INSTAL | 1 | EACH | $20,000.00 | $1,500.00 | $25,000.00 | |
| 139 | 88600100 | DET LOOP T1 | 265 | FOOT | $24.35 | $14.00 | $24.84 |