$128.75Avg low bid / EACH
$144.47Avg of all bids
—Avg engineer's estimate
29Jobs · 1,820 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 18 | 1,100 | $119.44 | $139.56 |
| 2025 | 10 | 600 | $147.55 | $163.04 |
| 2024 | 1 | 120 | $120.00 | $81.67 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Sep 18, 2026 | 97892 | St. ClairDistrict 8 | 40 EACH | $88.00 | Plocher Construction Company, Inc. |
| Sep 18, 2026 | 66926 | LasalleDistrict 3 | 48 EACH | $100.00 | D. Construction, Inc. |
| Jun 12, 2026 | 78791 | AlexanderDistrict 9 | 48 EACH | $114.00 | Samron Midwest Contracting, Inc. |
| Jun 12, 2026 | 62R61 | CookDistrict 1 | 162 EACH | $86.00 | OHLA Central, Inc. |
| Jun 12, 2026 | 66N45 | BureauDistrict 3 | 10 EACH | $100.00 | D. Construction, Inc. |
| Jun 12, 2026 | 76R32 | MadisonDistrict 8 | 96 EACH | $110.00 | Stutz Excavating, Inc. |
| Apr 24, 2026 | 78B36 | FranklinDistrict 9 | 26 EACH | $105.10 | E. T. Simonds Construction Company |
| Feb 27, 2026 | 78B34 | JeffersonDistrict 9 | 192 EACH | $103.84 | E. T. Simonds Construction Company |
| Feb 27, 2026 | 76B42 | Marion, WashingtonDistrict 8 | 24 EACH | $124.00 | C-Hill Civil Contractors, Inc. |
| Feb 27, 2026 | 70F37 | McleanDistrict 5 | 120 EACH | $165.00 | Stark Excavating, Inc. |
| Feb 27, 2026 | 74653 | ColesDistrict 7 | 20 EACH | $110.12 | Sangamo Construction Company |
| Feb 27, 2026 | 74C49 | ClarkDistrict 7 | 36 EACH | $102.89 | Sangamo Construction Company |
| Feb 27, 2026 | 76A37 | MarionDistrict 8 | 24 EACH | $88.00 | Samron Midwest Contracting, Inc. |
| Jan 16, 2026 | 62K65 | CookDistrict 1 | 40 EACH | $178.31 | F. H. Paschen, S.N. Nielsen & Associates LLC |
| Jan 16, 2026 | 76N65 | St.clairDistrict 8 | 28 EACH | $147.00 | Plocher Construction Company, Inc. |
| Jan 16, 2026 | 76A46 | MadisonDistrict 8 | 32 EACH | $113.00 | Keller Construction, Inc. |
| Jan 16, 2026 | 78937 | JacksonDistrict 9 | 24 EACH | $84.02 | E. T. Simonds Construction Company |
| Jan 16, 2026 | 62K64 | CookDistrict 1 | 130 EACH | $167.37 | F. H. Paschen, S.N. Nielsen & Associates LLC |
| Sep 19, 2025 | 62R22 | WillDistrict 1 | 104 EACH | $100.00 | D. Construction, Inc. |
| Jun 13, 2025 | 60R76 | WillDistrict 1 | 20 EACH | $1,000.00 | D. Construction, Inc. |
| Jun 13, 2025 | 62Y04 | CookDistrict 1 | 160 EACH | $134.20 | Areatha Construction Co., Inc. |
| Jun 13, 2025 | 91631 | EdgarDistrict 5 | 40 EACH | $150.00 | Big O Services, LLC |
| Jun 13, 2025 | 68E44 | Peoria, TazewellDistrict 4 | 80 EACH | $160.00 | William Charles Construction Company, LLC |
| Jun 13, 2025 | 66K63 | DekalbDistrict 3 | 96 EACH | $90.00 | Civil Constructors, Inc. d/b/a/ Helm Civil |
| Apr 25, 2025 | 61K26 | KaneDistrict 1 | 24 EACH | $26.90 | Rausch Infrastructure, LLC |
| Apr 25, 2025 | 62X93 | WillDistrict 1 | 24 EACH | $38.00 | D. Construction, Inc. |
| Mar 7, 2025 | 87876 | LasalleDistrict 3 | 32 EACH | $100.00 | D. Construction, Inc. |
| Jan 17, 2025 | 74C56 | MoultrieDistrict 7 | 20 EACH | $223.00 | Samron Midwest Contracting, Inc. |
| Dec 13, 2024 | 64N05 | HenryDistrict 2 | 120 EACH | $120.00 | Civil Constructors d/b/a Helm Civil and Phoenix Corporation of the Quad Cities |