29-2BR
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Samron Midwest Contracting, Inc. Low bidder | $4,343,470 | ||
| 2 | Keeley & Sons, Inc. | $4,823,383 | +11.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Samron Midwest … | #2 Keeley & Sons, … |
|---|---|---|---|---|---|---|---|
| 1 | X5080530 | BAR TERMINATORS | 422 | EACH | $28.00 | $47.85 | |
| 2 | X5230174 | DRAINAGE SCUPPR DS-11 | 6 | EACH | $1,900.00 | $2,780.00 | |
| 3 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $3,700.00 | $11,890.00 | |
| 4 | X7200075 | REM & REIN SIGN PANEL | 57 | SQ FT | $29.00 | $167.85 | |
| 5 | X7200203 | DETOUR SIGNING | 1 | L SUM | $34,000.00 | $11,315.00 | |
| 6 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $75,000.00 | $63,750.00 | |
| 7 | Z0076600 | TRAINEES | 2,500 | HOUR | $0.8000 | $0.8000 | |
| 8 | Z0076604 | TRAINEES TPG | 2,500 | HOUR | $15.00 | $15.00 | |
| 9 | 20100500 | TREE REMOV ACRES | 0.25 | ACRE | $100,000.00 | $27,890.00 | |
| 10 | 20200100 | EARTH EXCAVATION | 409 | CU YD | $60.00 | $38.85 | |
| 11 | 20300100 | CHANNEL EXCAVATION | 1,635 | CU YD | $65.00 | $39.15 | |
| 12 | 25000210 | SEEDING CL 2A | 0.25 | ACRE | $9,500.00 | $22,440.00 | |
| 13 | 25000400 | NITROGEN FERT NUTR | 9 | POUND | $1.50 | $8.16 | |
| 14 | 25000500 | PHOSPHORUS FERT NUTR | 9 | POUND | $1.50 | $89.76 | |
| 15 | 25000600 | POTASSIUM FERT NUTR | 9 | POUND | $1.50 | $8.16 | |
| 16 | 25100115 | MULCH METHOD 2 | 0.25 | ACRE | $4,000.00 | $12,240.00 | |
| 17 | 28000250 | TEMP EROS CONTR SEED | 9 | POUND | $25.00 | $18.36 | |
| 18 | 28000305 | TEMP DITCH CHECKS | 10 | FOOT | $11.00 | $48.96 | |
| 19 | 28000400 | PERIMETER EROS BAR | 1,183 | FOOT | $3.00 | $4.08 | |
| 20 | 28100109 | STONE RIPRAP CL A5 | 2,546 | SQ YD | $125.00 | $67.35 | |
| 21 | 28200200 | FILTER FABRIC | 2,546 | SQ YD | $4.00 | $6.85 | |
| 22 | 30300112 | AGG SUBGRADE IMPR 12 | 338 | SQ YD | $36.00 | $38.90 | |
| 23 | 31102000 | SUB GRAN MAT C | 7 | CU YD | $128.00 | $217.90 | |
| 24 | 40600275 | BIT MATLS PR CT | 1,396 | POUND | $2.00 | $4.65 | |
| 25 | 40600290 | BIT MATLS TACK CT | 335 | POUND | $0.0100 | $22.00 | |
| 26 | 40701901 | HMA PAVT FD 11 | 255 | SQ YD | $325.00 | $446.74 | |
| 27 | 42000080 | PVT CON PCC BR APP SL | 107 | SQ YD | $250.00 | $206.15 | |
| 28 | 44000100 | PAVEMENT REM | 782 | SQ YD | $25.00 | $18.65 | |
| 29 | 48100500 | AGGREGATE SHLDS A 6 | 449 | SQ YD | $29.00 | $21.80 | |
| 30 | 48203029 | HMA SHOULDERS 8 | 406 | SQ YD | $197.00 | $247.37 | |
| 31 | 50100100 | REM EXIST STRUCT | 1 | EACH | $415,000.00 | $197,310.00 | |
| 32 | 50200100 | STRUCTURE EXCAVATION | 369 | CU YD | $26.00 | $33.50 | |
| 33 | 50200300 | COFFERDAM EXCAVATION | 97 | CU YD | $112.00 | $79.80 | |
| 34 | 50200400 | ROCK EXC STRUCT | 50 | CU YD | $270.00 | $497.80 | |
| 35 | 50201121 | COFFERDAM TYP 2 LOC 1 | 1 | EACH | $0.0100 | $187,550.00 | |
| 36 | 50201122 | COFFERDAM TYP 2 LOC 2 | 1 | EACH | $0.0100 | $187,550.00 | |
| 37 | 50300100 | FLOOR DRAINS | 12 | EACH | $523.00 | $1,315.00 | |
| 38 | 50300225 | CONC STRUCT | 221.5 | CU YD | $1,350.00 | $1,795.50 | |
| 39 | 50300255 | CONC SUP-STR | 326.6 | CU YD | $1,850.00 | $1,897.10 | |
| 40 | 50300260 | BR DECK GROOVING | 1,010 | SQ YD | $10.00 | $28.21 | |
| 41 | 50300300 | PROTECTIVE COAT | 1,427 | SQ YD | $1.50 | $5.95 | |
| 42 | 50301350 | CONC SUPSTR APP SLAB | 94.8 | CU YD | $712.00 | $497.85 | |
| 43 | 50500105 | F & E STRUCT STEEL | 1 | L SUM | $1,100,000.00 | $1,297,650.00 | |
| 44 | 50500505 | STUD SHEAR CONNECTORS | 6,732 | EACH | $4.00 | $4.25 | |
| 45 | 50800205 | REINF BARS, EPOXY CTD | 137,340 | POUND | $2.00 | $1.90 | |
| 46 | 51201900 | FUR STL PILE HP14X89 | 280 | FOOT | $174.00 | $127.80 | |
| 47 | 51202100 | FUR STL PILE HP14X117 | 408 | FOOT | $110.00 | $167.90 | |
| 48 | 51202305 | DRIVING PILES | 280 | FOOT | $0.0100 | $0.0100 | |
| 49 | 51203900 | TEST PILE ST HP14X89 | 2 | EACH | $3,258.00 | $27,890.00 | |
| 50 | 51265001 | DRILL & SET PILES (IS) | 78 | CU FT | $77.00 | $151.15 | |
| 51 | 51265002 | DRILL & SET PILES (IR) | 552 | CU FT | $112.00 | $178.15 | |
| 52 | 51500100 | NAME PLATES | 1 | EACH | $956.00 | $1,655.00 | |
| 53 | 52100510 | ANCHOR BOLTS 3/4 | 24 | EACH | $88.00 | $119.80 | |
| 54 | 52100520 | ANCHOR BOLTS 1 | 24 | EACH | $94.00 | $127.10 | |
| 55 | 58600101 | GRANULAR BACKFILL STR | 234 | CU YD | $77.00 | $73.45 | |
| 56 | 60146304 | P UNDR FOR STRUCT 4 | 136 | FOOT | $38.00 | $47.80 | |
| 57 | 63000001 | SPBGR TY A 6FT POSTS | 575 | FOOT | $34.00 | $29.58 | |
| 58 | 63100085 | TRAF BAR TERM T6 | 4 | EACH | $4,964.00 | $4,386.00 | |
| 59 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,900.00 | $3,366.00 | |
| 60 | 63200310 | GUARDRAIL REMOV | 929 | FOOT | $10.00 | $8.85 | |
| 61 | 66900200 | NON SPL WASTE DISPOSL | 104 | CU YD | $90.00 | $136.28 | |
| 62 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,700.00 | $2,250.00 | |
| 63 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $3,500.00 | $7,370.00 | |
| 64 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $1,200.00 | $7,370.00 | |
| 65 | 66901006 | REG SUB MON | 10 | CAL DA | $1,300.00 | $300.00 | |
| 66 | 67000400 | ENGR FIELD OFFICE A | 8 | CAL MO | $1,900.00 | $4,780.00 | |
| 67 | 67100100 | MOBILIZATION | 1 | L SUM | $261,000.00 | $288,450.00 | |
| 68 | 70107025 | CHANGEABLE MESSAGE SN | 260 | CAL DA | $63.00 | $43.35 | |
| 69 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $60.00 | $51.00 | |
| 70 | 78009006 | MOD URETH PM LINE 6 | 957 | FOOT | $13.00 | $10.97 | |
| 71 | 78100100 | RAISED REFL PAVT MKR | 2 | EACH | $780.00 | $3,570.00 | |
| 72 | 78200005 | GRDRAIL REF TYPE A | 18 | EACH | $12.00 | $10.20 | |
| 73 | 78200011 | BARR WALL REF TYPE C | 16 | EACH | $28.00 | $35.00 |