17-00134-00-BR
- Let date
- Friday, June 13, 2025
- Contract
- 91631 · job page
- District
- District 5
- County
- Edgar
- Highway
- Limits
- Construction of a three-span steel beam structure with concrete deck to carry CH 16 over Flemington Tributary in Edgar County. Includes HMA approach pavement and traffic barrier terminals.
- Classification
- ·
- Project number
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Big O Services, LLC Low bidder | $1,648,370 | ||
| 2 | C-Hill Civil Contractors, Inc. | $1,650,000 | +0.1% | |
| 3 | Sangamo Construction Company | $1,713,745 | +4.0% | |
| 4 | William Charles Construction Company, LLC | $2,139,000 | +29.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Big O Services,… | #2 C-Hill Civil Co… | #3 Sangamo Constru… | #4 William Charles… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X2501000 | SEEDING CL 2 SPL | 0.25 | ACRE | $18,000.00 | $17,500.00 | $21,087.64 | $19,950.00 | |
| 2 | X2810208 | STONE RIPRAP CL A4 SP | 544 | TON | $125.00 | $97.00 | $75.05 | $135.00 | |
| 3 | X7011800 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $6,000.00 | $6,200.00 | $8,102.36 | $11,400.00 | |
| 4 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $28,000.00 | $40,000.00 | $25,104.18 | $15,000.00 | |
| 5 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 6 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 7 | 20200100 | EARTH EXCAVATION | 198 | CU YD | $55.00 | $40.00 | $29.49 | $100.00 | |
| 8 | 20300100 | CHANNEL EXCAVATION | 657 | CU YD | $65.00 | $36.00 | $30.13 | $80.00 | |
| 9 | 28000250 | TEMP EROS CONTR SEED | 19 | POUND | $9.00 | $3.00 | $3.97 | $50.00 | |
| 10 | 35101400 | AGG BASE CSE B | 441 | TON | $70.00 | $41.00 | $41.22 | $65.00 | |
| 11 | 40600275 | BIT MATLS PR CT | 2,090 | POUND | $2.25 | $2.00 | $2.06 | $1.95 | |
| 12 | 40600290 | BIT MATLS TACK CT | 209 | POUND | $9.50 | $9.00 | $9.01 | $8.52 | |
| 13 | 40603080 | HMA BC IL-19.0 N50 | 117 | TON | $280.00 | $268.00 | $270.06 | $255.49 | |
| 14 | 40604050 | HMA SC IL-9.5 C N50 | 78 | TON | $375.00 | $360.00 | $361.86 | $342.34 | |
| 15 | 50100100 | REM EXIST STRUCT | 1 | EACH | $35,000.00 | $31,500.00 | $19,924.91 | $50,000.00 | |
| 16 | 50200100 | STRUCTURE EXCAVATION | 243 | CU YD | $60.00 | $38.00 | $40.64 | $80.00 | |
| 17 | 50200300 | COFFERDAM EXCAVATION | 167 | CU YD | $70.00 | $83.00 | $55.93 | $100.00 | |
| 18 | 50201101 | COFFERDAM TYP 1 LOC 1 | 1 | EACH | $35,000.00 | $38,315.00 | $53,648.10 | $175,000.00 | |
| 19 | 50201102 | COFFERDAM TYP 1 LOC 2 | 1 | EACH | $35,000.00 | $38,315.00 | $53,648.10 | $175,000.00 | |
| 20 | 50300225 | CONC STRUCT | 190 | CU YD | $1,200.00 | $1,065.00 | $1,144.18 | $1,500.00 | |
| 21 | 50300255 | CONC SUP-STR | 120.8 | CU YD | $1,900.00 | $2,895.00 | $3,048.73 | $2,000.00 | |
| 22 | 50300300 | PROTECTIVE COAT | 454 | SQ YD | $3.00 | $4.50 | $3.39 | $7.50 | |
| 23 | 50500105 | F & E STRUCT STEEL | 1 | L SUM | $221,000.00 | $213,750.00 | $252,068.32 | $270,774.65 | |
| 24 | 50500505 | STUD SHEAR CONNECTORS | 3,000 | EACH | $9.23 | $5.20 | $5.25 | $5.75 | |
| 25 | 50800205 | REINF BARS, EPOXY CTD | 47,320 | POUND | $2.25 | $1.91 | $1.79 | $2.25 | |
| 26 | 50901050 | STEEL RAILING TY SM | 245 | FOOT | $285.00 | $272.00 | $288.97 | $259.10 | |
| 27 | 51201800 | FUR STL PILE HP14X73 | 1,732 | FOOT | $88.00 | $55.60 | $94.54 | $115.00 | |
| 28 | 51202305 | DRIVING PILES | 1,732 | FOOT | $0.0100 | $0.0100 | $0.0300 | $0.0100 | |
| 29 | 51203800 | TEST PILE ST HP14X73 | 4 | EACH | $15,000.00 | $22,300.00 | $5,453.13 | $7,000.00 | |
| 30 | 51500100 | NAME PLATES | 1 | EACH | $900.00 | $825.00 | $1,072.08 | $1,000.00 | |
| 31 | 52100010 | ELAST BEARING ASSY T1 | 15 | EACH | $2,500.00 | $1,200.00 | $1,423.59 | $1,500.00 | |
| 32 | 52100510 | ANCHOR BOLTS 3/4 | 40 | EACH | $150.00 | $82.00 | $84.87 | $100.00 | |
| 33 | 58600101 | GRANULAR BACKFILL STR | 174 | CU YD | $130.00 | $97.00 | $96.09 | $100.00 | |
| 34 | 59100100 | GEOCOMPOSITE WALL DR | 104 | SQ YD | $23.00 | $35.00 | $26.53 | $60.00 | |
| 35 | 60146304 | P UNDR FOR STRUCT 4 | 210 | FOOT | $13.00 | $35.00 | $28.14 | $40.00 | |
| 36 | 63100087 | TRAF BAR TERM T6A | 2 | EACH | $5,500.00 | $5,155.00 | $5,573.48 | $4,910.00 | |
| 37 | 63100167 | TR BAR TRM T1 SPL TAN | 2 | EACH | $4,500.00 | $4,205.00 | $4,233.38 | $4,005.00 | |
| 38 | 63200310 | GUARDRAIL REMOV | 136 | FOOT | $4.00 | $11.00 | $13.13 | $30.00 | |
| 39 | 67100100 | MOBILIZATION | 1 | L SUM | $60,000.00 | $95,803.28 | $101,110.95 | $128,760.00 | |
| 40 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $55.00 | $52.50 | $52.85 | $50.00 | |
| 41 | 78200006 | GRDRAIL REF TYPE B | 8 | EACH | $20.00 | $15.75 | $15.86 | $15.00 |