(32Q-MFT)BR
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Sangamo Construction Company Low bidder | $3,082,674 | ||
| 2 | Samron Midwest Contracting, Inc. | $4,354,187 | +41.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Sangamo Constru… | #2 Samron Midwest … |
|---|---|---|---|---|---|---|---|
| 1 | X2501000 | SEEDING CL 2 SPL | 0.5 | ACRE | $9,375.44 | $11,000.00 | |
| 2 | X4401198 | HMA SURF REM VAR DP | 771 | SQ YD | $13.92 | $25.00 | |
| 3 | X5080530 | BAR TERMINATORS | 494 | EACH | $28.11 | $30.00 | |
| 4 | X5230174 | DRAINAGE SCUPPR DS-11 | 4 | EACH | $2,300.99 | $2,000.00 | |
| 5 | X7011800 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $8,677.26 | $5,000.00 | |
| 6 | X7011801 | TRAF CONT-PROT BLR 22 | 1 | L SUM | $4,986.35 | $5,000.00 | |
| 7 | X7200203 | DETOUR SIGNING | 1 | L SUM | $3,191.34 | $2,000.00 | |
| 8 | Z0004552 | APPROACH SLAB REM | 89 | SQ YD | $65.98 | $68.00 | |
| 9 | 20200100 | EARTH EXCAVATION | 184 | CU YD | $64.73 | $85.00 | |
| 10 | 20200600 | EXC & GR EX SHOULDER | 7 | UNIT | $1,548.29 | $950.00 | |
| 11 | 21101505 | TOPSOIL EXC & PLAC | 132 | CU YD | $27.10 | $36.00 | |
| 12 | 25100630 | EROSION CONTR BLANKET | 298 | SQ YD | $1.95 | $4.00 | |
| 13 | 28000250 | TEMP EROS CONTR SEED | 11 | POUND | $4.31 | $13.00 | |
| 14 | 28000400 | PERIMETER EROS BAR | 873 | FOOT | $7.02 | $3.00 | |
| 15 | 28100105 | STONE RIPRAP CL A3 | 48 | SQ YD | $59.47 | $32.00 | |
| 16 | 28100109 | STONE RIPRAP CL A5 | 1,411 | SQ YD | $104.33 | $142.00 | |
| 17 | 28200200 | FILTER FABRIC | 1,459 | SQ YD | $5.07 | $5.00 | |
| 18 | 40600290 | BIT MATLS TACK CT | 347 | POUND | $4.23 | $5.00 | |
| 19 | 40600370 | LONG JOINT SEALANT | 347 | FOOT | $2.11 | $40.00 | |
| 20 | 40604052 | HMA SC IL-9.5 C N70 | 86 | TON | $311.63 | $350.00 | |
| 21 | 42000080 | PVT CON PCC BR APP SL | 203 | SQ YD | $282.70 | $178.00 | |
| 22 | 44000100 | PAVEMENT REM | 378 | SQ YD | $46.90 | $17.00 | |
| 23 | 48101500 | AGGREGATE SHLDS B 6 | 206 | SQ YD | $30.89 | $40.00 | |
| 24 | 48203029 | HMA SHOULDERS 8 | 438 | SQ YD | $121.48 | $135.00 | |
| 25 | 50100100 | REM EXIST STRUCT | 1 | EACH | $178,215.22 | $372,000.00 | |
| 26 | 50200100 | STRUCTURE EXCAVATION | 226 | CU YD | $57.91 | $41.00 | |
| 27 | 50200300 | COFFERDAM EXCAVATION | 607 | CU YD | $10.57 | $137.00 | |
| 28 | 50201121 | COFFERDAM TYP 2 LOC 1 | 1 | EACH | $188,760.97 | $400,000.00 | |
| 29 | 50201122 | COFFERDAM TYP 2 LOC 2 | 1 | EACH | $188,760.97 | $400,000.00 | |
| 30 | 50300225 | CONC STRUCT | 253.1 | CU YD | $1,081.10 | $1,200.00 | |
| 31 | 50300255 | CONC SUP-STR | 257.4 | CU YD | $1,618.38 | $1,700.00 | |
| 32 | 50300260 | BR DECK GROOVING | 807 | SQ YD | $11.14 | $12.00 | |
| 33 | 50300265 | SEAL COAT CONC | 205.4 | CU YD | $24.50 | $300.00 | |
| 34 | 50300300 | PROTECTIVE COAT | 1,059 | SQ YD | $3.40 | $2.00 | |
| 35 | 50301350 | CONC SUPSTR APP SLAB | 95.6 | CU YD | $607.81 | $840.00 | |
| 36 | 50500105 | F & E STRUCT STEEL | 1 | L SUM | $794,793.30 | $930,000.00 | |
| 37 | 50500505 | STUD SHEAR CONNECTORS | 4,785 | EACH | $4.34 | $4.50 | |
| 38 | 50800205 | REINF BARS, EPOXY CTD | 121,500 | POUND | $1.58 | $2.00 | |
| 39 | 51201710 | FUR STL PILE HP12X84 | 1,266 | FOOT | $1.00 | $124.00 | |
| 40 | 51202305 | DRIVING PILES | 1,266 | FOOT | $0.0200 | $0.0100 | |
| 41 | 51203710 | TEST PILE ST HP12X84 | 4 | EACH | $8,876.82 | $5,100.00 | |
| 42 | 51500100 | NAME PLATES | 1 | EACH | $1,185.68 | $1,000.00 | |
| 43 | 52100510 | ANCHOR BOLTS 3/4 | 20 | EACH | $110.12 | $95.00 | |
| 44 | 52100520 | ANCHOR BOLTS 1 | 20 | EACH | $115.35 | $106.00 | |
| 45 | 58600101 | GRANULAR BACKFILL STR | 133 | CU YD | $91.85 | $65.00 | |
| 46 | 59100100 | GEOCOMPOSITE WALL DR | 74 | SQ YD | $34.05 | $38.00 | |
| 47 | 60146304 | P UNDR FOR STRUCT 4 | 163 | FOOT | $28.54 | $29.00 | |
| 48 | 63000001 | SPBGR TY A 6FT POSTS | 363 | FOOT | $29.95 | $33.00 | |
| 49 | 63100085 | TRAF BAR TERM T6 | 4 | EACH | $4,730.55 | $4,700.00 | |
| 50 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,597.00 | $4,000.00 | |
| 51 | 63200310 | GUARDRAIL REMOV | 835 | FOOT | $8.02 | $11.00 | |
| 52 | 67000400 | ENGR FIELD OFFICE A | 4 | CAL MO | $3,181.40 | $2,300.00 | |
| 53 | 67100100 | MOBILIZATION | 1 | L SUM | $181,877.76 | $261,000.00 | |
| 54 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $118.49 | $170.00 | |
| 55 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $52.82 | $58.00 | |
| 56 | 78001110 | PAINT PVT MK LINE 4 | 1,454 | FOOT | $2.57 | $3.00 | |
| 57 | 78100100 | RAISED REFL PAVT MKR | 8 | EACH | $476.43 | $521.00 | |
| 58 | 78200005 | GRDRAIL REF TYPE A | 16 | EACH | $1.06 | $12.00 | |
| 59 | 78300200 | RAISED REF PVT MK REM | 4 | EACH | $12.23 | $61.00 |