20-00018-02-RS
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Stutz Excavating, Inc. Low bidder | $829,420 | ||
| 2 | Baxmeyer Construction, Inc. | $913,218 | +10.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Stutz Excavatin… | #2 Baxmeyer Constr… |
|---|---|---|---|---|---|---|---|
| 1 | X4401198 | HMA SURF REM VAR DP | 4,556 | SQ YD | $5.50 | $8.75 | |
| 2 | X6062400 | CONC GUTTER SPL | 116 | FOOT | $61.80 | $119.00 | |
| 3 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $6,500.00 | $9,700.00 | |
| 4 | 20200100 | EARTH EXCAVATION | 220 | CU YD | $135.00 | $250.00 | |
| 5 | 25000200 | SEEDING CL 2 | 0.25 | ACRE | $8,000.00 | $35,750.00 | |
| 6 | 25000400 | NITROGEN FERT NUTR | 23 | POUND | $5.00 | $1.00 | |
| 7 | 25000500 | PHOSPHORUS FERT NUTR | 23 | POUND | $5.00 | $1.00 | |
| 8 | 25000600 | POTASSIUM FERT NUTR | 23 | POUND | $5.00 | $1.00 | |
| 9 | 25100105 | MULCH METHOD 1 | 0.5 | ACRE | $9,000.00 | $7,900.00 | |
| 10 | 28000250 | TEMP EROS CONTR SEED | 25 | POUND | $5.00 | $0.0100 | |
| 11 | 31100300 | SUB GRAN MAT A 4 | 260 | SQ YD | $10.85 | $18.25 | |
| 12 | 40201000 | AGGREGATE-TEMP ACCESS | 100 | TON | $51.15 | $80.50 | |
| 13 | 40600275 | BIT MATLS PR CT | 585 | POUND | $2.25 | $7.35 | |
| 14 | 40600290 | BIT MATLS TACK CT | 3,192 | POUND | $1.95 | $2.25 | |
| 15 | 40600370 | LONG JOINT SEALANT | 1,669 | FOOT | $10.70 | $10.00 | |
| 16 | 40600990 | TEMPORARY RAMP | 196 | SQ YD | $6.00 | $22.75 | |
| 17 | 40602970 | HMA BC IL-9.5FG N70 | 383 | TON | $167.60 | $171.00 | |
| 18 | 40604062 | HMA SC IL-9.5 D N70 | 470 | TON | $181.70 | $195.00 | |
| 19 | 42001300 | PROTECTIVE COAT | 2,753 | SQ YD | $1.00 | $2.65 | |
| 20 | 42300200 | PCC DRIVEWAY PAVT 6 | 831 | SQ YD | $126.85 | $169.00 | |
| 21 | 42400100 | PC CONC SIDEWALK 4 | 14,724 | SQ FT | $11.25 | $9.50 | |
| 22 | 42400800 | DETECTABLE WARNINGS | 123 | SQ FT | $35.00 | $28.00 | |
| 23 | 44000100 | PAVEMENT REM | 260 | SQ YD | $18.50 | $22.00 | |
| 24 | 44000200 | DRIVE PAVEMENT REM | 766 | SQ YD | $23.55 | $46.75 | |
| 25 | 44000400 | GUTTER REM | 117 | FOOT | $5.90 | $12.00 | |
| 26 | 44000500 | COMB CURB GUTTER REM | 772 | FOOT | $52.40 | $38.00 | |
| 27 | 44000600 | SIDEWALK REM | 13,812 | SQ FT | $3.40 | $3.00 | |
| 28 | 44201359 | CL C PATCH T4 10 | 96 | SQ YD | $137.00 | $245.00 | |
| 29 | 60261510 | INLETS ADJ NEW T20F&G | 1 | EACH | $910.00 | $1,475.00 | |
| 30 | 60605000 | COMB CC&G TY B-6.24 | 774 | FOOT | $128.70 | $143.00 | |
| 31 | 67100100 | MOBILIZATION | 1 | L SUM | $48,500.00 | $20,501.22 | |
| 32 | 70300100 | SHORT TERM PAVT MKING | 431 | FOOT | $2.50 | $5.25 | |
| 33 | 70300150 | SHRT TRM PAVT MK REM | 144 | SQ FT | $12.00 | $6.50 | |
| 34 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 3,160 | FOOT | $1.25 | $1.25 | |
| 35 | 70300241 | TEMP PVT MK LINE 6 - PAINT | 195 | FOOT | $8.50 | $8.25 | |
| 36 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 26 | FOOT | $23.00 | $22.00 | |
| 37 | 78000200 | THPL PVT MK LINE 4 | 3,160 | FOOT | $1.65 | $1.50 | |
| 38 | 78000400 | THPL PVT MK LINE 6 | 195 | FOOT | $9.25 | $9.00 | |
| 39 | 78000600 | THPL PVT MK LINE 12 | 26 | FOOT | $27.25 | $26.00 | |
| 40 | 78300201 | PVT MKG REM GRINDING | 1,176 | SQ FT | $1.65 | $1.60 |