21-00036-00-BT
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Stutz Excavating, Inc. Low bidder | $683,304 | ||
| 2 | Keller Construction, Inc. | $770,728 | +12.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Stutz Excavatin… | #2 Keller Construc… |
|---|---|---|---|---|---|---|---|
| 1 | A2007120 | T-QUERCUS RUBRA 2-1/2 | 2 | EACH | $750.00 | $2,450.00 | |
| 2 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $13,000.00 | $6,140.00 | |
| 3 | X1700066 | POTHOLING | 20 | EACH | $530.00 | $550.00 | |
| 4 | X5036003 | CONCRETE HEADWALL SPL | 1 | EACH | $10,425.00 | $22,000.00 | |
| 5 | X5400005 | BOX CULVERT REMOVAL | 15 | FOOT | $125.00 | $200.00 | |
| 6 | X6023508 | INLETS TA W/SPL F&G | 1 | EACH | $1,910.00 | $3,500.00 | |
| 7 | X6024242 | INLETS SPL N1 | 1 | EACH | $5,625.00 | $10,000.00 | |
| 8 | X6024244 | INLETS SPL N2 | 1 | EACH | $3,265.00 | $5,000.00 | |
| 9 | X6062400 | CONC GUTTER SPL | 228 | FOOT | $52.80 | $81.11 | |
| 10 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $5,900.00 | $6,350.00 | |
| 11 | Z0004002 | BOLLARDS | 12 | EACH | $3,795.00 | $3,622.50 | |
| 12 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | |
| 13 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | |
| 14 | 20100110 | TREE REMOV 6-15 | 12 | UNIT | $60.00 | $167.00 | |
| 15 | 20200100 | EARTH EXCAVATION | 780 | CU YD | $56.25 | $66.15 | |
| 16 | 20400800 | FURNISHED EXCAVATION | 700 | CU YD | $75.35 | $35.20 | |
| 17 | 20800150 | TRENCH BACKFILL | 27 | CU YD | $117.00 | $55.00 | |
| 18 | 25000110 | SEEDING CL 1A | 1.5 | ACRE | $3,000.00 | $4,825.50 | |
| 19 | 25000400 | NITROGEN FERT NUTR | 135 | POUND | $2.00 | $9.24 | |
| 20 | 25000500 | PHOSPHORUS FERT NUTR | 135 | POUND | $2.00 | $9.24 | |
| 21 | 25000600 | POTASSIUM FERT NUTR | 135 | POUND | $2.00 | $9.24 | |
| 22 | 25100105 | MULCH METHOD 1 | 1.5 | ACRE | $3,940.00 | $5,455.00 | |
| 23 | 25100630 | EROSION CONTR BLANKET | 1,430 | SQ YD | $2.90 | $5.50 | |
| 24 | 28000305 | TEMP DITCH CHECKS | 36 | FOOT | $22.00 | $27.75 | |
| 25 | 28000400 | PERIMETER EROS BAR | 4,736 | FOOT | $3.35 | $4.55 | |
| 26 | 28000500 | INLET & PIPE PROTECT | 15 | EACH | $265.00 | $429.00 | |
| 27 | 28100107 | STONE RIPRAP CL A4 | 10 | SQ YD | $156.00 | $160.00 | |
| 28 | 31000600 | PR LIM STAB SOIL M 12 | 3,854 | SQ YD | $5.25 | $2.75 | |
| 29 | 31001500 | LIME | 101 | TON | $240.00 | $186.00 | |
| 30 | 35100300 | AGG BASE CSE A 4 | 457 | SQ YD | $24.00 | $0.0100 | |
| 31 | 35100500 | AGG BASE CSE A 6 | 3,910 | SQ YD | $7.25 | $11.65 | |
| 32 | 40600275 | BIT MATLS PR CT | 8,411 | POUND | $1.85 | $1.28 | |
| 33 | 40604050 | HMA SC IL-9.5 C N50 | 611 | TON | $168.00 | $163.72 | |
| 34 | 42400300 | PC CONC SIDEWALK 6 | 2,185 | SQ FT | $9.35 | $13.23 | |
| 35 | 42400800 | DETECTABLE WARNINGS | 269 | SQ FT | $52.80 | $87.94 | |
| 36 | 44000300 | CURB REM | 41 | FOOT | $19.50 | $27.15 | |
| 37 | 44000500 | COMB CURB GUTTER REM | 60 | FOOT | $24.50 | $18.55 | |
| 38 | 44000600 | SIDEWALK REM | 732 | SQ FT | $3.35 | $1.95 | |
| 39 | 44200050 | WELDED WIRE REINF | 169 | SQ YD | $19.80 | $14.00 | |
| 40 | 44200944 | CL B PATCH T4 8 | 169 | SQ YD | $128.00 | $243.00 | |
| 41 | 44201298 | DOWEL BARS 1 1/4 | 120 | EACH | $26.50 | $20.10 | |
| 42 | 44201723 | CL D PATCH T4 6 | 111 | SQ YD | $165.00 | $158.70 | |
| 43 | 44213198 | TIE BARS 1/2 | 60 | EACH | $17.50 | $20.85 | |
| 44 | 44213200 | SAW CUTS | 140 | FOOT | $13.20 | $10.80 | |
| 45 | 54010302 | PCBC 3X2 | 28 | FOOT | $762.00 | $850.00 | |
| 46 | 542A0220 | P CUL CL A 1 15 | 121.5 | FOOT | $102.00 | $120.00 | |
| 47 | 54213660 | PRC FLAR END SEC 15 | 8 | EACH | $1,725.00 | $2,250.00 | |
| 48 | 54248510 | CONCRETE COLLAR | 3.1 | CU YD | $830.00 | $525.00 | |
| 49 | 56109210 | WATER VALVES ADJUST | 2 | EACH | $210.00 | $645.00 | |
| 50 | 56500300 | DOM MET VLTS ADJ | 1 | EACH | $435.00 | $1,230.00 | |
| 51 | 60600605 | CONC CURB TB | 32 | FOOT | $52.80 | $168.50 | |
| 52 | 60604400 | COMB CC&G TB6.18 | 60 | FOOT | $52.80 | $100.59 | |
| 53 | 66900200 | NON SPL WASTE DISPOSL | 10 | CU YD | $260.00 | $123.00 | |
| 54 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,650.00 | $1,575.00 | |
| 55 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,200.00 | $2,100.00 | |
| 56 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,200.00 | $2,100.00 | |
| 57 | 66901006 | REG SUB MON | 5 | CAL DA | $1,095.00 | $1,044.75 | |
| 58 | 67100100 | MOBILIZATION | 1 | L SUM | $33,000.00 | $75,000.00 | |
| 59 | 72000100 | SIGN PANEL T1 | 164.5 | SQ FT | $38.50 | $36.75 | |
| 60 | 72800100 | TELES STL SIN SUPPORT | 90 | FOOT | $21.00 | $19.95 | |
| 61 | 73000100 | WOOD SIN SUPPORT | 297 | FOOT | $44.00 | $42.00 | |
| 62 | 78001110 | PAINT PVT MK LINE 4 | 1,746 | FOOT | $1.45 | $0.9000 | |
| 63 | 78001180 | PAINT PVT MK LINE 24 | 606 | FOOT | $13.50 | $3.94 |