133RS-7
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Charles E. Mahoney Co. Low bidder | $619,161 | ||
| 2 | Christ Bros. Asphalt, Inc. | $639,451 | +3.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Charles E. Maho… | #2 Christ Bros. As… |
|---|---|---|---|---|---|---|---|
| 1 | 20200100 | EARTH EXCAVATION | 15 | CU YD | $72.00 | $92.00 | |
| 2 | 20800150 | TRENCH BACKFILL | 24 | CU YD | $104.00 | $124.00 | |
| 3 | 28100225 | STONE RIPRAP CL B3 | 6 | TON | $315.00 | $335.00 | |
| 4 | 28200200 | FILTER FABRIC | 17 | SQ YD | $20.00 | $20.00 | |
| 5 | 35101800 | AGG BASE CSE B 6 | 36 | SQ YD | $53.00 | $73.00 | |
| 6 | 40600290 | BIT MATLS TACK CT | 7,656 | POUND | $2.50 | $2.94 | |
| 7 | 40600370 | LONG JOINT SEALANT | 8,208 | FOOT | $3.75 | $3.67 | |
| 8 | 40600990 | TEMPORARY RAMP | 64 | SQ YD | $28.27 | $0.0100 | |
| 9 | 40603085 | HMA BC IL-19.0 N70 | 2 | TON | $1,026.37 | $138.04 | |
| 10 | 40604090 | HMA SC IL-9.5L C N30 | 300 | TON | $127.90 | $138.04 | |
| 11 | 40604162 | P HMA SC IL-9.5 D N70 | 1,432 | TON | $169.54 | $138.04 | |
| 12 | 42400100 | PC CONC SIDEWALK 4 | 80 | SQ FT | $42.00 | $62.00 | |
| 13 | 44000155 | HMA SURF REM 1 1/2 | 20,576 | SQ YD | $4.44 | $3.82 | |
| 14 | 44000200 | DRIVE PAVEMENT REM | 24 | SQ YD | $27.00 | $47.00 | |
| 15 | 44200994 | CL B PATCH T2 12 | 37 | SQ YD | $394.00 | $394.00 | |
| 16 | 44201299 | DOWEL BARS 1 1/2 | 42 | EACH | $34.00 | $34.00 | |
| 17 | 44201785 | CL D PATCH T1 12 | 5 | SQ YD | $1,102.20 | $492.00 | |
| 18 | 44213200 | SAW CUTS | 84 | FOOT | $50.00 | $25.00 | |
| 19 | 48102100 | AGG WEDGE SHLD TYPE B | 30 | TON | $236.14 | $98.33 | |
| 20 | 50105220 | PIPE CULVERT REMOV | 76 | FOOT | $41.00 | $61.00 | |
| 21 | 542D0223 | P CUL CL D 1 18 | 92 | FOOT | $74.00 | $94.00 | |
| 22 | 54261718 | STEEL FL END SEC 18" | 4 | EACH | $2,300.00 | $3,300.00 | |
| 23 | 67100100 | MOBILIZATION | 1 | L SUM | $54,332.95 | $59,844.00 | |
| 24 | 70102622 | TR CONT & PROT 701502 | 1 | L SUM | $21,914.32 | $58,950.00 | |
| 25 | 70107025 | CHANGEABLE MESSAGE SN | 56 | CAL DA | $89.00 | $99.00 | |
| 26 | 70300100 | SHORT TERM PAVT MKING | 1,500 | FOOT | $3.14 | $3.93 | |
| 27 | 70300150 | SHRT TRM PAVT MK REM | 251 | SQ FT | $11.15 | $0.0100 | |
| 28 | 70300211 | TEMP PVT MK LTR & SYM PAINT | 655 | SQ FT | $0.0100 | $0.0100 | |
| 29 | 72400310 | REMOV SIGN PANEL T1 | 3 | SQ FT | $30.00 | $30.00 | |
| 30 | 72400710 | RELOC SIGN PANEL T1 | 3 | SQ FT | $30.00 | $30.00 | |
| 31 | 78000100 | THPL PVT MK LTR & SYM | 655.2 | SQ FT | $15.00 | $10.65 | |
| 32 | 78000400 | THPL PVT MK LINE 6 | 18,496 | FOOT | $0.7900 | $2.85 | |
| 33 | 78100100 | RAISED REFL PAVT MKR | 214 | EACH | $68.21 | $61.95 | |
| 34 | 78300200 | RAISED REF PVT MK REM | 214 | EACH | $5.60 | $0.0100 | |
| 35 | 78300202 | PVT MKG REM WTR BLAST | 6,167 | SQ FT | $0.0100 | $0.0100 |