SR PATCHING
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Advanced Asphalt Company Low bidder | $513,534 | ||
| 2 | Gillan Construction LLC | $534,444 | +4.1% | |
| 3 | G. M. Sipes Construction, Inc. | $612,830 | +19.3% | |
| 4 | D. Construction, Inc. | $627,474 | +22.2% | |
| 5 | Gensini Excavating, Inc. | $765,466 | +49.1% | |
| 6 | Davis Concrete Construction Co. | $811,053 | +57.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Advanced Asphal… | #2 Gillan Construc… | #3 G. M. Sipes Con… | #4 D. Construction… | #5 Gensini Excavat… | #6 Davis Concrete … |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $8,325.00 | $8,250.00 | $1,000.00 | $5,000.00 | $7,500.00 | $10,000.00 | |
| 2 | 28100107 | STONE RIPRAP CL A4 | 11 | SQ YD | $114.00 | $90.00 | $250.00 | $200.00 | $90.00 | $100.00 | |
| 3 | 44000500 | COMB CURB GUTTER REM | 50 | FOOT | $80.00 | $52.00 | $40.00 | $20.00 | $25.00 | $20.00 | |
| 4 | 44200050 | WELDED WIRE REINF | 3,484 | SQ YD | $9.00 | $8.50 | $0.0100 | $15.00 | $10.00 | $10.00 | |
| 5 | 44200905 | CL B PATCH T2 6 | 256 | SQ YD | $110.00 | $86.00 | $180.00 | $110.00 | $151.28 | $155.00 | |
| 6 | 44200909 | CL B PATCH T3 6 | 382 | SQ YD | $100.00 | $86.00 | $180.00 | $110.00 | $151.28 | $145.00 | |
| 7 | 44200911 | CL B PATCH T4 6 | 2,847 | SQ YD | $85.00 | $86.00 | $130.00 | $110.00 | $151.28 | $135.00 | |
| 8 | 44201297 | DOWEL BARS 1 | 3,474 | EACH | $12.00 | $20.00 | $0.0100 | $18.00 | $20.00 | $12.00 | |
| 9 | 44213200 | SAW CUTS | 7,000 | FOOT | $1.75 | $3.00 | $8.50 | $5.00 | $3.30 | $3.00 | |
| 10 | 44213204 | TIE BARS 3/4 | 2,046 | EACH | $11.00 | $15.00 | $0.0100 | $12.00 | $15.00 | $10.00 | |
| 11 | 54390230 | INSERT CUL LIN 36 | 60 | FOOT | $490.00 | $330.00 | $345.00 | $450.00 | $450.00 | $2,225.00 | |
| 12 | 67100100 | MOBILIZATION | 1 | L SUM | $28,750.00 | $24,000.00 | $16,000.00 | $0.0100 | $15,000.00 | $40,500.00 | |
| 13 | 78009004 | MOD URETH PM LINE 4 | 9,500 | FOOT | $1.35 | $1.49 | $1.42 | $1.82 | $1.56 | $1.50 | |
| 14 | 78011025 | GRV RCSD PVT MRKG 5 | 9,500 | FOOT | $1.35 | $1.49 | $1.30 | $1.82 | $1.43 | $1.40 |