10BidsJun 13, 2025 to Jul 31, 2026
3Wins (low bidder)
30.0%Win rate
$6,131,249Total won
| Let date | Contract | Project | Rank | Their bid | Low bid | vs low |
|---|---|---|---|---|---|---|
| Jul 31, 2026 | 62W91 | 2024-966-TSCook · District 1 | 2 of 3 | $2,726,629 | $1,753,960H & H Electric Co. | +55.5% |
| Jun 12, 2026 | 62W82 | 2024-956-TSVarious · District 1 | 2 of 3 | $8,866,667 | $6,878,841H & H Electric Co. | +28.9% |
| Jun 12, 2026 | 62W83 | 2024-957-TSCook · District 1 | 2 of 4 | $2,326,258 | $2,052,267H & H Electric Co. | +13.4% |
| Jun 12, 2026 | 80C89 | 2026-2160-TSCook, Lake · District 1 | 2 of 2 | $3,939,373 | $2,718,198H & H Electric Co. | +44.9% |
| Feb 27, 2026 | 62W78 | 2024-960-LTLake · District 1 | 1 of 2 | $1,798,186 | $1,798,186 | Won |
| Feb 27, 2026 | 61M20 | 24-00199-00-LTCook · District 1 | 4 of 5 | $475,619 | $318,848H & H Electric Co. | +49.2% |
| Feb 27, 2026 | 61M21 | 24-00198-00-LTCook · District 1 | 5 of 5 | $546,573 | $326,553H & H Electric Co. | +67.4% |
| Aug 1, 2025 | 62W57 | 2023-941-N,TSCook · District 1 | 1 of 1 | $2,599,373 | $2,599,373 | Won |
| Jun 13, 2025 | 62X42 | 2024-1005-TSCook · District 1 | 1 of 1 | $1,733,690 | $1,733,690 | Won |
| Jun 13, 2025 | 62W15 | FAI 80 23 LIGHTINGWill · District 1 | 3 of 4 | $1,788,147 | $1,709,237John Burns Construction Com… | +4.6% |
Subcontracts on active jobs 0
No subcontracts on TxDOT's active contract list.