D2 GRDRL DELIN MAINT INT 26-03
- Let date
- Friday, June 13, 2025
- Contract
- 46661 · job page
- District
- District 2
- County
- Various
- Highway
- Limits
- Removing existing guardrail delineators and barrier wall delineators and installing new guardrail delineators and barrier wall delineators within the limits of each individual work order.
- Classification
- ·
- Project number
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | O'Brien Civil Works, Inc. Low bidder | $167,625 | ||
| 2 | Northern Contracting, Inc. | $176,865 | +5.5% | |
| 3 | Done Rite Construction Co., Inc. | $199,993 | +19.3% | |
| 4 | ROADSAFE TRAFFIC SYSTEMS, INC. | $379,500 | +126.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 O'Brien Civil W… | #2 Northern Contra… | #3 Done Rite Const… | #4 ROADSAFE TRAFFI… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X7820007 | GRDRAIL REFL TY C SPL | 5,385 | EACH | $18.05 | $18.33 | $22.00 | $40.00 | |
| 2 | X7820008 | BARRIER WALL REFL SPL | 1,010 | EACH | $16.70 | $22.83 | $24.00 | $40.00 | |
| 3 | 72501000 | TERMINAL MARKER - DA | 1,100 | EACH | $40.90 | $41.80 | $44.00 | $90.00 | |
| 4 | 72501100 | TERMINAL MARKER - PM | 95 | EACH | $90.20 | $96.00 | $93.50 | $260.00 |