ILLINI 2023
- Let date
- Friday, June 13, 2025
- Contract
- 46937 · job page
- District
- District 3
- County
- Lasalle
- Highway
- Limits
- Roadway improvements (HMA resurfacing, A3 oil and chip, drainage improvements and other work) within Illini State Park (IDNR) in LaSalle County, IL. 1.6 miles gross length.
- Classification
- ·
- Project number
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $1,632,707 | ||
| 2 | Advanced Asphalt Company | $1,737,725 | +6.4% | |
| 3 | Tobey's Construction & Cartage, Inc. | $2,048,310 | +25.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 Advanced Asphal… | #3 Tobey's Constru… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0327176 | WOOD GRDRAIL REM | 701 | FOOT | $9.71 | $10.00 | $11.00 | |
| 2 | X1500004 | BIT SURF TREATMNT A1 | 12,655 | SQ YD | $4.00 | $4.00 | $3.64 | |
| 3 | X1500006 | BIT SURF TREATMNT A3 | 6,570 | SQ YD | $10.42 | $12.15 | $9.47 | |
| 4 | X2020114 | GRAD & SHAP DITCH SPL | 5,635 | FOOT | $40.00 | $3.50 | $18.50 | |
| 5 | X2130010 | EXPLOR TRENCH SPL | 200 | FOOT | $50.00 | $12.00 | $33.50 | |
| 6 | X4060107 | BIT MATLS FS | 10,382 | POUND | $1.08 | $1.00 | $0.9800 | |
| 7 | X4420201 | PAVEMENT PATCHING SPL | 329 | SQ YD | $70.00 | $115.00 | $165.00 | |
| 8 | X5015225 | PIPE CULVERT REM SPL | 6 | FOOT | $100.00 | $110.00 | $175.00 | |
| 9 | X7011801 | TRAF CONT-PROT BLR 22 | 1 | L SUM | $47,364.00 | $8,500.00 | $4,975.00 | |
| 10 | Z0004542 | HMA REMOVAL SPL | 10,690 | SQ YD | $17.00 | $31.50 | $33.50 | |
| 11 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $15,000.00 | $8,875.00 | $11,200.00 | |
| 12 | 25000115 | SEEDING CL 1B | 1.5 | ACRE | $3,135.00 | $2,850.00 | $6,000.00 | |
| 13 | 25000400 | NITROGEN FERT NUTR | 135 | POUND | $3.30 | $3.00 | $4.00 | |
| 14 | 25000500 | PHOSPHORUS FERT NUTR | 135 | POUND | $3.30 | $3.00 | $4.00 | |
| 15 | 25000600 | POTASSIUM FERT NUTR | 135 | POUND | $3.30 | $3.00 | $4.00 | |
| 16 | 25100115 | MULCH METHOD 2 | 1.5 | ACRE | $3,850.00 | $3,500.00 | $6,000.00 | |
| 17 | 28000200 | EARTH EXC - EROS CONT | 21 | CU YD | $50.00 | $150.00 | $72.00 | |
| 18 | 28000250 | TEMP EROS CONTR SEED | 150 | POUND | $4.40 | $4.00 | $5.00 | |
| 19 | 28000400 | PERIMETER EROS BAR | 5,116 | FOOT | $2.48 | $2.25 | $3.50 | |
| 20 | 28000500 | INLET & PIPE PROTECT | 17 | EACH | $220.00 | $200.00 | $120.00 | |
| 21 | 28001000 | AGGREGATE - EROS CONT | 9 | TON | $65.00 | $170.00 | $200.00 | |
| 22 | 30300112 | AGG SUBGRADE IMPR 12 | 13,919 | SQ YD | $20.65 | $27.50 | $25.75 | |
| 23 | 35800100 | PREPARATION OF BASE | 6,570 | SQ YD | $2.00 | $1.35 | $1.25 | |
| 24 | 40600275 | BIT MATLS PR CT | 31,318 | POUND | $0.0100 | $1.10 | $0.0100 | |
| 25 | 40600290 | BIT MATLS TACK CT | 2,953 | POUND | $0.0100 | $2.45 | $0.0100 | |
| 26 | 40600370 | LONG JOINT SEALANT | 5,271 | FOOT | $4.35 | $2.50 | $5.50 | |
| 27 | 40603080 | HMA BC IL-19.0 N50 | 1,668 | TON | $82.00 | $110.00 | $170.00 | |
| 28 | 40604050 | HMA SC IL-9.5 C N50 | 1,097 | TON | $89.00 | $130.00 | $180.00 | |
| 29 | 50105220 | PIPE CULVERT REMOV | 558 | FOOT | $20.00 | $50.00 | $31.50 | |
| 30 | 542A0220 | P CUL CL A 1 15 | 30 | FOOT | $100.00 | $88.50 | $134.00 | |
| 31 | 542A0253 | P CUL CL A 1 48 | 94 | FOOT | $255.00 | $185.00 | $264.00 | |
| 32 | 542A0259 | P CUL CL A 1 54 | 129 | FOOT | $299.00 | $240.00 | $385.00 | |
| 33 | 542A5470 | P CUL CL A 1 EQRS 15 | 314 | FOOT | $115.00 | $82.25 | $197.00 | |
| 34 | 54213660 | PRC FLAR END SEC 15 | 2 | EACH | $1,500.00 | $1,275.00 | $1,625.00 | |
| 35 | 54213693 | PRC FLAR END SEC 48 | 4 | EACH | $3,500.00 | $3,750.00 | $4,300.00 | |
| 36 | 54213699 | PRC FLAR END SEC 54 | 6 | EACH | $6,200.00 | $6,000.00 | $5,200.00 | |
| 37 | 54214500 | PRC FL END S EQ RS 15 | 22 | EACH | $2,000.00 | $1,250.00 | $1,700.00 | |
| 38 | 59300100 | CONTR LOW-STRENG MATL | 139 | CU YD | $300.00 | $200.00 | $295.00 | |
| 39 | 63000001 | SPBGR TY A 6FT POSTS | 600 | FOOT | $32.08 | $44.00 | $42.00 | |
| 40 | 63100167 | TR BAR TRM T1 SPL TAN | 2 | EACH | $3,676.20 | $5,500.00 | $3,900.00 | |
| 41 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $4,000.00 | $3,000.00 | $3,750.00 | |
| 42 | 67100100 | MOBILIZATION | 1 | L SUM | $97,800.00 | $97,350.00 | $115,000.00 | |
| 43 | 72000100 | SIGN PANEL T1 | 30 | SQ FT | $27.50 | $37.50 | $25.00 | |
| 44 | 72501000 | TERMINAL MARKER - DA | 2 | EACH | $38.50 | $50.00 | $40.00 | |
| 45 | 73000100 | WOOD SIN SUPPORT | 57 | FOOT | $27.50 | $65.00 | $25.00 | |
| 46 | 78200006 | GRDRAIL REF TYPE B | 9 | EACH | $13.20 | $41.50 | $24.00 |