24-00024-00-SW
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Gillan Construction LLC Low bidder | $255,362 | ||
| 2 | Universal Asphalt & Excavating, Inc. | $299,648 | +17.3% | |
| 3 | Advanced Asphalt Company | $403,286 | +57.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Gillan Construc… | #2 Universal Aspha… | #3 Advanced Asphal… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0327618 | LANDSCAPING, SPECIAL | 1 | L SUM | $5,462.00 | $8,000.00 | $15,965.00 | |
| 2 | X6024503 | INLET ADJ NEW F&G SPL | 3 | EACH | $1,000.00 | $1,200.00 | $3,500.00 | |
| 3 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $5,000.00 | $7,300.00 | $12,000.00 | |
| 4 | X7200043 | RADAR SPEED SIGN | 2 | EACH | $11,000.00 | $5,900.00 | $17,500.00 | |
| 5 | 35101400 | AGG BASE CSE B | 406 | TON | $32.00 | $30.00 | $50.00 | |
| 6 | 40200800 | AGG SURF COURSE TY B | 6 | TON | $60.00 | $30.00 | $80.00 | |
| 7 | 40800025 | BIT MATLS PR CT | 612 | POUND | $0.0100 | $0.0100 | $1.50 | |
| 8 | 40800029 | BIT MATLS TACK CT | 65 | POUND | $0.0100 | $0.0100 | $3.50 | |
| 9 | 40800050 | INCIDENTAL HMA SURF | 76 | TON | $154.00 | $250.00 | $500.00 | |
| 10 | 42300200 | PCC DRIVEWAY PAVT 6 | 334 | SQ YD | $79.00 | $90.00 | $80.00 | |
| 11 | 42400100 | PC CONC SIDEWALK 4 | 7,955 | SQ FT | $10.00 | $15.00 | $15.00 | |
| 12 | 42400800 | DETECTABLE WARNINGS | 166 | SQ FT | $27.50 | $30.00 | $25.00 | |
| 13 | 44000200 | DRIVE PAVEMENT REM | 261 | SQ YD | $16.00 | $20.00 | $18.00 | |
| 14 | 44000300 | CURB REM | 816 | FOOT | $6.50 | $10.00 | $25.00 | |
| 15 | 44000600 | SIDEWALK REM | 1,024 | SQ FT | $3.25 | $3.00 | $5.00 | |
| 16 | 60255800 | MAN ADJ NEW T1F CL | 1 | EACH | $900.00 | $1,800.00 | $2,000.00 | |
| 17 | 60260100 | INLETS ADJUST | 7 | EACH | $350.00 | $600.00 | $650.00 | |
| 18 | 60266600 | VALVE BOX ADJ | 6 | EACH | $275.00 | $100.00 | $95.00 | |
| 19 | 60600605 | CONC CURB TB | 25 | FOOT | $100.00 | $60.00 | $40.00 | |
| 20 | 60604400 | COMB CC&G TB6.18 | 862 | FOOT | $43.50 | $39.00 | $45.00 | |
| 21 | 67100100 | MOBILIZATION | 1 | L SUM | $12,500.00 | $5,000.00 | $23,000.00 | |
| 22 | 72000100 | SIGN PANEL T1 | 44.4 | SQ FT | $50.00 | $50.00 | $50.00 | |
| 23 | 72400310 | REMOV SIGN PANEL T1 | 34 | SQ FT | $25.00 | $25.00 | $25.00 | |
| 24 | 72800100 | TELES STL SIN SUPPORT | 34 | FOOT | $30.00 | $35.00 | $35.00 | |
| 25 | 73000100 | WOOD SIN SUPPORT | 40 | FOOT | $40.00 | $40.00 | $90.00 | |
| 26 | 78001130 | PAINT PVT MK LINE 6 | 84 | FOOT | $8.25 | $29.00 | $15.72 | |
| 27 | 78001150 | PAINT PVT MK LINE 12 | 87 | FOOT | $24.75 | $56.50 | $31.45 | |
| 28 | 78001180 | PAINT PVT MK LINE 24 | 16 | FOOT | $49.50 | $160.00 | $62.87 | |
| 29 | 78300202 | PVT MKG REM WTR BLAST | 95 | SQ FT | $49.50 | $45.00 | $70.00 |