22-00061-00-SW
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Feutz Contractors, Inc. Low bidder | $394,399 | ||
| 2 | Kieffer Bros. Construction Co., Inc. | $470,129 | +19.2% | |
| 3 | McCarthy Improvement Company | $524,555 | +33.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Feutz Contracto… | #2 Kieffer Bros. C… | #3 McCarthy Improv… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0326806 | WASHOUT BASIN | 1 | L SUM | $3,700.00 | $1,696.00 | $2,266.00 | |
| 2 | X0326899 | SOLAR-POWER FB AS CMP | 1 | EACH | $34,000.00 | $41,597.05 | $37,745.00 | |
| 3 | X2500920 | SEEDING CL 1A SPL | 0.2 | ACRE | $15,000.00 | $17,198.50 | $15,563.00 | |
| 4 | X4021000 | TEMP ACCESS- PRIV ENT | 9 | EACH | $750.00 | $1,208.40 | $684.00 | |
| 5 | X4022000 | TEMP ACCESS- COM ENT | 2 | EACH | $1,000.00 | $1,325.00 | $952.00 | |
| 6 | X4401198 | HMA SURF REM VAR DP | 286 | SQ YD | $9.00 | $92.39 | $84.00 | |
| 7 | X7200044 | PERM RADAR SPEED SIGN | 2 | EACH | $13,500.00 | $16,067.48 | $14,500.00 | |
| 8 | X7240205 | REMOV SIGN COMPLETE | 8 | EACH | $200.00 | $159.00 | $0.0100 | |
| 9 | 25100125 | MULCH METHOD 3 | 0.2 | ACRE | $10,000.00 | $11,368.50 | $10,288.00 | |
| 10 | 40200800 | AGG SURF COURSE TY B | 2 | TON | $450.00 | $73.14 | $430.00 | |
| 11 | 40600290 | BIT MATLS TACK CT | 130 | POUND | $15.00 | $21.28 | $19.00 | |
| 12 | 40600990 | TEMPORARY RAMP | 177 | SQ YD | $35.00 | $17.63 | $16.00 | |
| 13 | 40604052 | HMA SC IL-9.5 C N70 | 34 | TON | $345.00 | $973.90 | $1,100.00 | |
| 14 | 42300200 | PCC DRIVEWAY PAVT 6 | 41 | SQ YD | $110.00 | $87.98 | $112.00 | |
| 15 | 42300400 | PCC DRIVEWAY PAVT 8 | 40 | SQ YD | $125.00 | $101.97 | $120.00 | |
| 16 | 42400100 | PC CONC SIDEWALK 4 | 9,612 | SQ FT | $12.00 | $11.10 | $18.50 | |
| 17 | 42400300 | PC CONC SIDEWALK 6 | 375 | SQ FT | $13.00 | $12.56 | $15.00 | |
| 18 | 42400410 | PC CONC SIDEWALK 8 | 445 | SQ FT | $15.00 | $15.85 | $19.00 | |
| 19 | 42400800 | DETECTABLE WARNINGS | 173 | SQ FT | $27.00 | $37.10 | $39.00 | |
| 20 | 44000200 | DRIVE PAVEMENT REM | 158 | SQ YD | $44.00 | $23.53 | $30.00 | |
| 21 | 44000300 | CURB REM | 229 | FOOT | $28.00 | $20.88 | $10.00 | |
| 22 | 44000600 | SIDEWALK REM | 7,485 | SQ FT | $5.50 | $3.23 | $1.70 | |
| 23 | 56500300 | DOM MET VLTS ADJ | 4 | EACH | $445.00 | $217.30 | $500.00 | |
| 24 | 60260100 | INLETS ADJUST | 1 | EACH | $600.00 | $212.00 | $2,000.00 | |
| 25 | 60600605 | CONC CURB TB | 229 | FOOT | $58.00 | $56.92 | $83.00 | |
| 26 | 67100100 | MOBILIZATION | 1 | L SUM | $21,000.00 | $24,542.03 | $31,000.00 | |
| 27 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $6,300.00 | $17,172.00 | $27,200.00 | |
| 28 | 70102622 | TR CONT & PROT 701502 | 1 | L SUM | $1,400.00 | $13,992.00 | $8,500.00 | |
| 29 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1,000.00 | $1,378.00 | $8,700.00 | |
| 30 | 72000100 | SIGN PANEL T1 | 103 | SQ FT | $41.00 | $92.11 | $22.00 | |
| 31 | 72800100 | TELES STL SIN SUPPORT | 107 | FOOT | $24.00 | $116.60 | $10.00 | |
| 32 | 78000400 | THPL PVT MK LINE 6 | 596 | FOOT | $15.00 | $16.32 | $14.00 | |
| 33 | 78000600 | THPL PVT MK LINE 12 | 120 | FOOT | $30.00 | $32.65 | $31.00 | |
| 34 | 87502680 | TS POST A 14 | 4 | EACH | $3,000.00 | $3,959.74 | $3,583.00 | |
| 35 | 87800100 | CONC FDN TY A | 12 | FOOT | $825.00 | $903.65 | $820.00 | |
| 36 | 88800100 | PED PUSH-BUTTON | 2 | EACH | $1,400.00 | $1,579.93 | $1,430.00 | |
| 37 | 89502400 | REM EX FB INSTAL COMP | 1 | EACH | $6,000.00 | $6,733.65 | $6,093.00 |