| Let date | Contract / PPS | County / Division | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| Jul 30, 2021 | 78656 | FranklinDistrict 9 | 9 miles of lane addition, median barrier installation and resurfacing existing lanes of I-57 from mile post 66 to Marcum Branch. | — | Executed | E. T. Simonds Construction Company $67,611,531 · | ||
| Jul 30, 2021 | 78838 | JacksonPerryDistrict 9 | 17.8 miles of pavement patching, HMA surface removal, HMA surfacing, HMA shoulders and ADA sidewalk improvements on US 51 from near Industrial Park Road in Carbondale to Grant Way in Du Quoin. | — | Executed | E. T. Simonds Construction Company $8,586,162 · | ||
| Jul 30, 2021 | 78863 | JohnsonDistrict 9 | 3.4 miles of patching, milling, surfacing, median repairs and curb and gutter repairs at 2 locations: 1) US 45 from 0.7 miles northeast of I-24 to 1.07 miles southwest of I-24; 2) Just north of IL 146 to 1.85 miles south of IL 146. | — | Executed | Southern Illinois Asphalt Co., Inc. $1,536,649 · | ||
| Jul 30, 2021 | 78865 | JacksonDistrict 9 | 6.2 miles of HMA surface removal, resurfacing of the mainline and shoulders and ADA upgrades on IL 149 from IL 13/127 in Murphysboro to US 51 in Desoto. | — | Executed | Samron Midwest Contracting, Inc. $1,641,027 · | ||
| Jul 30, 2021 | 78872 | PulaskiUnionDistrict 9 | 5 miles of micro-surfacing on Northbound I-57 / US 51 from 1 mile south of Big Creek to Perks Road. | — | Executed | A. C. Pavement Striping Co. $338,806 · | ||
| Jul 30, 2021 | 78886 | PulaskiDistrict 9 | 1000- of milling, resurfacing, guardrail removal and replacement and concrete rail removal and replacement on West Cedar Street from east of SN 077-0030 to Front Street in Olmstead. | — | Executed | Samron Midwest Contracting, Inc. $221,401 · | ||
| Jul 30, 2021 | 85713 | BooneDistrict 2 | Replace the bridge carrying TR 120 over Piscasaw Creek, 3.5 miles southeast of Poplar Grove. | — | Executed | Sjostrom & Sons, Inc. $409,085 · | ||
| Jul 30, 2021 | 87754 | DeKalbDistrict 3 | Resurfacing, sidewalk replacement, curb and gutter, pavement markings and pedestrian signal improvements at three locations on Northern University Campus in the City of DeKalb. | — | Rejected | Stenstrom Excavation & Blacktop, Inc. $369,273 · | ||
| Jul 30, 2021 | 87767 | DeKalbDistrict 3 | Replace the bridge carrying TR 244 over Coon Creek 0.30 mile south of IL 72. | — | Rejected | Sjostrom & Sons, Inc. $456,936 · | ||
| Jul 30, 2021 | 87780 | FordDistrict 3 | Resurfacing and aggregate shoulders on Elliot Road from IL 54 to IL 9. | — | Executed | Iroquois Paving Corporation $1,626,354 · | ||
| Jul 30, 2021 | 87781 | BureauDistrict 3 | Repair the undermining at the abutments and install improved drainage at the bridge carrying Peru Road over Negro Creek, just south of US 6. | — | Executed | D. Construction, Inc. $198,183 · | ||
| Jul 30, 2021 | 89784 | TazewellDistrict 4 | Resurfacing on Parkway Drive from Lick Creek to Willow Street in Pekin. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $1,195,692 · | ||
| Jul 30, 2021 | 89786 | PeoriaDistrict 4 | Construction of sidewalks and ADA ramps on the south side of West Knolls Road from North University Drive to 0.15 mile east of Allen Road in Peoria. | — | Executed | Illinois Civil Contractors, Inc. $234,082 · | ||
| Jul 30, 2021 | 89791 | KnoxDistrict 4 | Resurfacing, patching and ADA ramps on Henderson Road from the County Fairground entrance to Poplar Street in Knoxville. | — | Executed | Gunther Construction, a div of UCM, Inc. $275,374 · | ||
| Jul 30, 2021 | 89807 | PutnamDistrict 4 | Resurfacing, aggregate shoulders, and guardrail on CH 11 from IL 89 to the LaSalle County line. | — | Executed | Advanced Asphalt Company $753,023 · | ||
| Jul 30, 2021 | 91606 | VermilionDistrict 5 | Replace the bridge carrying TR 183 over Unnamed Stream, 1 mile south of Hope. | — | Executed | Big O Services, LLC $391,390 · | ||
| Jul 30, 2021 | 93764 | HancockDistrict 6 | Replace the bridge carrying CH 19 over Panther Creek, 4 miles west of Plymouth. | — | Executed | County Contractors, Inc. $744,143 · | ||
| Jul 30, 2021 | 93771 | SangamonDistrict 6 | Install lighting at the intersection of Mechanicsburg-Illiopolis Road and Mt. Auburn Roiad in Sangamon County. | — | Executed | Capitol Construction Group, LLC d/b/a Egizii Electric $28,864 · | ||
| Jul 30, 2021 | 95904 | LawrenceDistrict 7 | Resurfacing, HMA shoulders, rumble strips and culvert replacement on FAS 1804 from 1150 North Road to Sun and Sand Road. | — | Executed | Ambraw Asphalt Materials, Inc. $1,263,794 · | ||
| Jul 30, 2021 | 99601 | SalineDistrict 9 | Replace the bridge carrying Forest Road over Little Eagle Creek, 8 miles west of IL 1. | — | Executed | Samron Midwest Contracting, Inc. $497,333 · | ||
| Jul 30, 2021 | 99612 | GallatinDistrict 9 | Replace the bridge carrying Eldorado Blacktop Road over North Fork of Saline River, 1.8 miles west of IL 1. | — | Executed | Samron Midwest Contracting, Inc. $2,973,552 · | ||
| Jul 30, 2021 | 99668 | JeffersonDistrict 9 | Resurfacing and aggregate shoulders on East Divide Road from Harmony Lane to Papertown Lane. | — | Executed | Southern Illinois Asphalt Co., Inc. $1,035,795 · | ||
| Sep 17, 2021 | 46577 | VariousDistrict 7 | Pavement marking rehabilitation throughout District 7. | — | Executed | Varsity Striping & Construction Co. $776,874 · | ||
| Sep 17, 2021 | 61H17 | KaneDistrict 1 | Reconstruct the existing Illinois Prairie Path from Indian Trial Road to the DuPage County line in Aurora. | — | Executed | Martam Construction Incorporated $894,048 · | ||
| Sep 17, 2021 | 61H21 | McHenryDistrict 1 | Resurfacing Reed Road from the west village limits to Lakewood Road in the Village of Lake in the Hills. | — | Executed | Plote Construction, Inc. $125,400 · | ||
| Sep 17, 2021 | 62D79 | CookLakeDistrict 1 | The project extends from Montrose Ave to Park Blvd. Improvements cover 13.5 miles along 1-94 and 2 miles along US 41. The scope includes fiber optic cable, CCTV and dynamic message signs in order to provide surveillance coverage of the highway. | — | Executed | Meade Inc. $11,996,355 · | ||
| Sep 17, 2021 | 62G35 | McHenryDistrict 1 | (7.74-Mile) Pavement widening and resurfacing to provide left turn lanes at 8 intersections, replacement of 3 culverts, 5 culverts repair, widening 5 culverts to accommodate proposed intersections, guardrails, regrading, shoulder improvements and rumblestrips along IL 176 from Deerpass Rd -Dean St in the City of Marengo. | — | Executed | William Charles Construction Company, LLC $8,277,010 · | ||
| Sep 17, 2021 | 62H87 | CookDistrict 1 | Intersection improvements at US 14 and Propect Road to include traffic signal modernization, left turn lanes, railroad interconnect, pedestrian signals, drainage system, and ADA/shared-use path improvements in Des Plaines and Mt. Prospect. | — | Executed | Berger Excavating Contractors, Inc. $2,974,033 · | ||
| Sep 17, 2021 | 62J90 | LakeDistrict 1 | (2.17-Mile) Designed Overlay, ADA Improvements; Location: FAU 3506: Sheridan Rd from St. Johns Ave to Lambert Tree Ave in the City of Highland Park in Lake County. | — | Executed | Builders Paving, LLC $1,448,000 · | ||
| Sep 17, 2021 | 62K02 | CookDistrict 1 | (2,897-Ft) Intersection improvement and traffic signal modernization project located at the intersection of IL 19 (FAU 1321) and Barrington Road in the Village of Hanover Park in Cook County. | — | Executed | Alliance Contractors, Inc. $2,935,409 · | ||
| Sep 17, 2021 | 62K30 | WillDistrict 1 | (13.6-Mile) Pavement Rehabilitation (designed overlay). Includes milling and resurfacing, Class D patching, pavement markings, drainage, ITS and landscaping improvements. Location: I-55 Southbound, from South of I-80 to just South of Weber Rd in Will County. | — | Executed | K-Five Construction Corporation and D Construction, Inc. and Gallagher Asphalt Corp JV $23,952,848 · | ||
| Sep 17, 2021 | 62K51 | WillDistrict 1 | (13.6-miles) Pavement rehabilitation (designed overlay) project for Northbound direction. Includes milling and resurfacing, Class D patching, pavement markings, drainage, ITS and landscaping improvements. Location: I-55 Northbound, from South of I-80 to just South of Weber Rd in Will County. | — | Executed | K-Five Construction Corporation and D Construction, Inc. and Gallagher Asphalt Corp JV $23,734,628 · | ||
| Sep 17, 2021 | 62L67 | CookDistrict 1 | (5,255-Ft) Standard Overlay with ADA improvements. Location: 47th Street, from Central Ave to IL-50 (Cicero Ave) in the Village of Stickney and the City of Chicago, in Cook County. | — | Executed | MAT Construction Leasing, Inc. $904,416 · | ||
| Sep 17, 2021 | 62M76 | CookDistrict 1 | The improvement is located at the structure carrying Metra commuter rail over 1-90 and CTA at Jefferson Park (SN 016-0515) in the city of Chicago. | — | Executed | Copenhaver Construction, Inc. $367,420 · | ||
| Sep 17, 2021 | 62M86 | VariousDistrict 1 | This contract is for annual maintenance of electrical systems including the Signal Systems, Lighting Systems, Pump Station Systems, Surveilliance System and other Electrical Systems, many subsystems and components, mechanical system and including buildings, structures and grounds located withing District 1. | — | Rejected | Meade Inc. $39,292,732 · | ||
| Sep 17, 2021 | 62N95 | VariousDistrict 1 | 89 Traffic Signal Intersections. Installation of traffic signal safety devices to increase visibility of signal indications during inclement weather. Location - 23 intersections in Cook, 4 locations in Lake, 35 locations in Kane, 4 locations in McHenry, 23 locations in Will. | — | Executed | H & H Electric Co. $929,834 · | ||
| Sep 17, 2021 | 62P25 | CookDistrict 1 | (597-Ft.) Cleaning and painting designated steel surfaces of bridge structure carrying Western Ave over Calumet Sag Channel in the City of Blue Island, Worth and Calumet Townships, Cook County. | — | Executed | Capital Industrial Services $1,533,930 · | ||
| Sep 17, 2021 | 62P26 | McHenryDistrict 1 | (16.3-Mile) Pavement surface patching (2-in mill and fill / intermittent resurfacing) improvement. Includes affected PMKs restoration. Location: IL 173 (Maple Ave) from Alden Rd to Lake Co Line in the Villages Alden Hebron and Richmond in McHenry County. | — | Executed | Payne & Dolan, Inc. $597,319 · | ||
| Sep 17, 2021 | 62P27 | VariousDistrict 1 | (15.3-Mile) Replacement of existing signs with new guide signs, removal of walkway, and removal of existing sign lighting Location - Along 1-55 Northbound and Southbound as well as exit ramps between Weber Rd and l-294 (Tri-State Tollway) | — | Executed | Aldridge Electric, Inc. $1,244,418 · | ||
| Sep 17, 2021 | 64L75 | OgleDistrict 2 | Deck replacement and substructure repairs, IL 251 over Soo Line Railroad 0.1 mile South of Il 72. | — | Executed | Civil Constructors, Inc. d/b/a/ Helm Civil $2,189,925 · | ||
| Sep 17, 2021 | 64N63 | Jo DaviessDistrict 2 | 1.0 mile of safety improvements - Road Diet, patching and resurfacing along US 20 from 6th St. to 0.1 mile W of Camillus Drive in East Dubuque. | — | Executed | Civil Constructors, Inc. d/b/a/ Helm Civil $1,226,553 · | ||
| Sep 17, 2021 | 64R22 | WhitesideDistrict 2 | Safety improvement at Science Ridge Road North of Sterling. | — | Executed | Civil Constructors, Inc. d/b/a/ Helm Civil $139,824 · | ||
| Sep 17, 2021 | 64R29 | VariousDistrict 2 | Installation of oversized chevrons along interchange ramp curves at various locations. | — | Executed | T.M.F. Construction Company $569,683 · | ||
| Sep 17, 2021 | 66997 | KankakeeDistrict 3 | The structure replacement carrying Maple St/Waldron Rd over I-57 in Kankakee along with construction of adjace The project consists of the structure replacement carrying Maple St/Waldron Rd over I-57 in Kankakee along with construction of adjacent retaining walls. The project includes the reconstruction of portions of Maple St, Waldron Rd, construction of shared-use path and realigning/reconstructing County RD S89E. | — | Executed | Kankakee Valley Construction Company, Inc. $11,309,823 · | ||
| Sep 17, 2021 | 66D53 | IroquoisDistrict 3 | US 52 - 3P milling and resurfacing, shoulder widening and ADA in Iroquois from East of IL 1 to South of Donovan in Iroquois county. | — | Executed | Iroquois Paving Corporation $5,186,160 · | ||
| Sep 17, 2021 | 66F11 | KankakeeDistrict 3 | Removal and replacement of SN 046-0063 carrying Armour Road over Illinois Central Railroad located 0.3 miles west of IL 50. | — | Executed | D. Construction, Inc. $5,976,820 · | ||
| Sep 17, 2021 | 66K18 | KankakeeDistrict 3 | This project consists of 5.9 miles of shoulder widening and rumble strip installation on IL 17 from 0.10 miles South of IL 1/17 (E Taylor St) to State Line Rd in Kankakee County. | — | Executed | Kankakee Valley Construction Company, Inc. $1,262,477 · | ||
| Sep 17, 2021 | 66L97 | IroquoisDistrict 3 | Removal and replacement of existing 48" and 12" storm sewer, catch basin, manhole, pavement patching and other This project is located at failed 48- diameter pipe culvert at Sta. 391+00 carrying IL 49 over Shavetail Creek approximately 8 miles South of US 24 (Cresent City). This project consists of removal and replacement of existing 48" and 12" storm sewer, catch basin, manhole, pavement patching and other related construction items. | — | Executed | Dirtworks Trucking & Excavating $69,245 · | ||
| Sep 17, 2021 | 66M06 | VariousDistrict 3 | The removal and replacement of all symbol and stop bar pavement markings at various interchanges throughout Di This project consists of the removal and replacement of all symbol and stop bar pavement markings at various interchanges throughout District 3. | — | Executed | A. C. Pavement Striping Co. $978,534 · | ||
| Sep 17, 2021 | 66M07 | VariousDistrict 3 | The installation, maintenance, and pickup/removal of smart traffic monitoring systems or real-time traffic con This project consists of the installation, maintenance, and pickup/removal of smart traffic monitoring systems or real-time traffic control systems. The work will be completed on a work order basis for repairs and maintenance activities. | — | Executed | ROADSAFE TRAFFIC SYSTEMS, INC. $574,990 · | ||
| Sep 17, 2021 | 66M08 | BureauLaSalleDistrict 3 | The installation of four changeable speed warning signs on the outer interchange ramps at I-80 and I-39 and th This project consists of the installation of four changeable speed warning signs on the outer interchange ramps at I-80 and I-39 and three changeable speed warning signs at the I-80 and I-180 interchange. | — | Executed | T.M.F. Construction Company $71,655 · | ||
| Sep 17, 2021 | 68D17 | WoodfordDistrict 4 | Box culvert replacements on US 150 (S.N. 102-1005; S.N. 102-2503 (new)), 0.9 mile East of Mackinaw River and (S.N. 102-1004; S.N. 102-2030 (new)), 0.16 mile East of CR 1825E. | — | Executed | Phoenix Corporation of the Quad Cities $2,337,434 · | ||
| Sep 17, 2021 | 68G62 | FultonDistrict 4 | Intersection improvement with flashing lights and lighting upgrades in Fulton County. | — | Executed | Illinois Civil Contractors, Inc. $723,553 · | ||
| Sep 17, 2021 | 68G63 | WoodfordDistrict 4 | New shoulders along US 150 from County Road 1250E, West of Goodfield to the McLean County Line. | — | Executed | Rowe Construction, a div of UCM, Inc. $3,018,142 · | ||
| Sep 17, 2021 | 70F64 | ChampaignDouglasMcLeanDistrict 5 | 43.69 miles of pavement marking on I-55 from Sugar Creek to 1.0 miles E of the Veterans Parkway interchange, and on I-57 from the Coles County line S of Arcola to the Ford County line. | — | Executed | Varsity Striping & Construction Co. $1,676,308 · | ||
| Sep 17, 2021 | 72D40 | ScottDistrict 6 | Removing existing box culvert and replacing with 8' x 4' box culvert on Old US 36, 1.7 miles northeast of I-72, west of Riggston. | — | Executed | Kinney Contractors, Inc. $339,921 · | ||
| Sep 17, 2021 | 72K08 | SchuylerDistrict 6 | Bridge replacement (SN 085-0002) carrying US 67 over Bluff Ditch, 1.8 miles northwest of IL 100. | — | Executed | County Contractors, Inc. $1,553,674 · | ||
| Sep 17, 2021 | 72N00 | MorganDistrict 6 | Lot improvements at the Jacksonville Maintenance Yard. | — | Executed | K. E. Vas Company $129,762 · | ||
| Sep 17, 2021 | 72N01 | SchuylerDistrict 6 | Lot improvements at the Rushville Maintenance Yard. | — | Executed | Lee Hood d/b/a Hood Demolition & Excavation $129,336 · | ||
| Sep 17, 2021 | 72N15 | LoganDistrict 6 | Pipe culvert removal and replacement on I-55 around Lincoln. | — | Executed | Kinney Contractors, Inc. $122,464 · | ||
| Sep 17, 2021 | 72N16 | PikeDistrict 6 | Cured-in-place pipe liners on IL 96 in Atlas. | — | Executed | Phoenix Corporation of the Quad Cities $163,615 · | ||
| Sep 17, 2021 | 74752 | EffinghamDistrict 7 | Shoulder work, base course widening, curb and gutter, ADA sidewalk improvements and box culvert replacement on US 40 from the Fayette County line to Division Street in Altamont and on IL 128 from US 40 in Altamont to 0.1 miles north of I-70. | — | Executed | Howell Paving, Inc. $4,548,184 · | ||
| Sep 17, 2021 | 74899 | LawrenceDistrict 7 | Tree removal along IL 33 from County Road 1300 to Westport. | — | Executed | Endrizzi Contracting, Inc $241,553 · | ||
| Sep 17, 2021 | 74A72 | VariousDistrict 7 | Chain link fence replacement at 4 locations: D7 headquarters in Effingham, Shelbyville Yard, Charleston Yard and Lawrenceville Yard. | — | Rejected | COLLINS & HERMANN, INC. $307,866 · | ||
| Sep 17, 2021 | 76P29 | VariousDistrict 8 | Repair and maintenance of electrical equipment at various pump stations in District 8. | — | Executed | Electrico, Inc. $58,258 · | ||
| Sep 17, 2021 | 76P30 | CalhounDistrict 8 | Repair and maintenance of electrical equipment at the Joe Page Bridge in Hardin (SN 031-0001). | — | Executed | Wissehr Electric, Inc. $52,601 · | ||
| Sep 17, 2021 | 76P31 | St. ClairDistrict 8 | Well treatment at various locations in East St. Louis and Venice. | — | Executed | Davinroy Mechanical Contractor, Inc. $714,100 · | ||
| Sep 17, 2021 | 76P38 | ClintonDistrict 8 | 2.6 miles of resurfacing on Old US 50 from 0.2 miles west of Carter Street to 0.6 miles east of Pipeline Road. | — | Executed | The Kilian Corporation $518,909 · | ||
| Sep 17, 2021 | 76P68 | MadisonDistrict 8 | Bridge painting on I-255 over I-55/70 (SN 060-0206 and 060-0207). | — | Executed | Venus Painting Co. $779,600 · | ||
| Sep 17, 2021 | 76P69 | St. ClairDistrict 8 | Bridge painting on IL 13 (SN 082-0115 and 082-0116). | — | Executed | Civil Coatings and Construction Inc. $492,648 · | ||
| Sep 17, 2021 | 76P74 | VariousDistrict 8 | Pavement marking at various locations in Bond, Clinton, Marion and Washington Counties. | — | Executed | ROADSAFE TRAFFIC SYSTEMS, INC. $1,148,148 · | ||
| Sep 17, 2021 | 76P75 | GreeneJerseyDistrict 8 | 39.4 miles of pavement marking removal and replacement on IL 108 from the Calhoun County line to IL 267 and on IL 100/16 from 0.3 miles east of Eldred Eldred Road to 0.1 miles west of Grafton Hills Drive. | — | Executed | STF, LLC d/b/a Traffic Control Company $898,383 · | ||
| Sep 17, 2021 | 76P76 | MadisonDistrict 8 | Pavement marking in various locations of Madison County. | — | Executed | ROADSAFE TRAFFIC SYSTEMS, INC. $666,667 · | ||
| Sep 17, 2021 | 76P77 | RandolphSt. ClairDistrict 8 | Water blasting removal of existing pavement marking and replacement with thermoplastic or modified urethane pavement marking at various locations in St. Clair and Randolph Counties. | — | Executed | ROADSAFE TRAFFIC SYSTEMS, INC. $1,234,568 · | ||
| Sep 17, 2021 | 76P81 | RandolphDistrict 8 | 5.6 miles of patching on IL 3 from IL 150 to 1 mile south of Pleasant Hill Road and IL 150 from IL 3 to Murphysboro Road. | — | Executed | E. T. Simonds Construction Company $682,813 · | ||
| Sep 17, 2021 | 76P82 | RandolphDistrict 8 | 6.2 miles of patching on IL 150 from IL 4, west of Steeleville, to the Perry County line. | — | Executed | G. M. Sipes Construction, Inc. $475,119 · | ||
| Sep 17, 2021 | 78503 | FranklinDistrict 9 | Conversion of the wye intersection of IL 149 and IL 184 to a roundabout intersection. | — | Executed | E. T. Simonds Construction Company $1,777,808 · | ||
| Sep 17, 2021 | 78602 | SalineDistrict 9 | 5.9 miles of patching, HMA surface removal, HMA surface, HMA shoulders and aggregate shoulders on IL 34 / 145 from the signalized intersection of US 45 and IL 34 / 145 to the intersection of IL 34 and IL 145. | — | Executed | E. T. Simonds Construction Company $2,188,313 · | ||
| Sep 17, 2021 | 78848 | FranklinUnionWilliamsonDistrict 9 | Bridge deck repairs on SN 100-0069 carrying IL 148 over Crab Orchard Lake, 2.8 miles south of IL 13; SN 091-0064 carrying IL 127 over Lingle Creek, 0.3 miles north of Mill Creek; SN 091-0067 carrying IL 127 over Mill Creek, 0.5 miles 0.5 miles north of Mill Creek; SN 028-0037 carrying IL 149 over Big Muddy River, 1.6 miles east of Ziegler. | — | Executed | E. T. Simonds Construction Company $1,177,173 · | ||
| Sep 17, 2021 | 78862 | VariousDistrict 9 | Surface preparation and application of bridge deck sealer on bridges in Alexander, Johnson, Massac, Pulaski and Union Counties. | — | Executed | All States Painting, Inc. $238,300 · | ||
| Sep 17, 2021 | 78864 | JacksonDistrict 9 | 19.3 miles of patching, HMA surface removal, HMA resurfacing and HMA safety shoulders on IL 3 and IL 149. | — | Executed | Samron Midwest Contracting, Inc. $4,252,377 · | ||
| Sep 17, 2021 | 78873 | UnionDistrict 9 | 7.4 miles of HMA surface removal and resurfacing on US 51 from IL 146 to I-57. | — | Executed | E. T. Simonds Construction Company $2,275,872 · | ||
| Sep 17, 2021 | 78875 | AlexanderDistrict 9 | 1.8 miles of pavement patching, HMA surface removal and HMA surfacing on IL 3 in Olive Branch from 0.1 miles west of Pigeon Roost Road to Brownsville Road. | — | Rejected | Southern Illinois Asphalt Co., Inc. $811,280 · | ||
| Sep 17, 2021 | 78881 | VariousDistrict 9 | Bridge painting in various counties; 2 in Jefferson, 1 in Hamilton, 1 in White, 1 in Johnson and 4 in Pulaski Counties. | — | Executed | ERA-Valdivia Contractors, Inc. $1,887,170 · | ||
| Sep 17, 2021 | 78889 | JohnsonDistrict 9 | 500 feet of grade adjustment by milling and filling with HMA binder and HMA surface coarse on US 45 approximately 2.5 miles north of the I-24 Intersection, near Roosevelt Loop. | — | Executed | E. T. Simonds Construction Company $72,246 · | ||
| Sep 17, 2021 | 78898 | FranklinDistrict 9 | 5.4 miles of patching, HMA surface removal and resurfacing, safety shoulders and guardrail removal and replacement on IL 154 from near the rail crossing in Sesser to near Fitzgerrell Park Drive. | — | Executed | E. T. Simonds Construction Company $4,066,957 · | ||
| Sep 17, 2021 | 89795 | FultonDistrict 4 | Replace the bridge carrying CH 2 over Coal Creek, 4.25 miles south of London Mills. | — | Executed | Stark Excavating, Inc. $1,359,595 · | ||
| Sep 17, 2021 | 93772 | CassDistrict 6 | Resurfacing CH 8 from IL 125 to south of Pine Street. | — | Executed | Illinois Valley Paving, a div of UCM, Inc. $580,391 · | ||
| Sep 17, 2021 | 97758 | MadisonDistrict 8 | Replace the bridge carrying Albers Lane over Rocky Branch Creek in Bethalto. | — | Executed | Stutz Excavating, Inc. $1,316,433 · | ||
| Sep 17, 2021 | 97760 | MadisonDistrict 8 | Pavement reconstruction, new sidewalks and drainage improvements on North Prairie Street from Corbin Street to Dorothy Street in Bethalto. | — | Executed | Baxmeyer Construction, Inc. $1,375,777 · | ||
| Sep 17, 2021 | 97762 | MadisonDistrict 8 | Construction of a shared-use path along IL 157 from Lewis Road to the Goshen Trail Pedestrian Tunnel under IL 157 in Edwardsville. | — | Executed | Baxmeyer Construction, Inc. $837,008 · | ||
| Sep 17, 2021 | 97764 | MadisonDistrict 8 | Resurfcing Johnson Road from Terrace Lane to Wabsh Avenue in Granite City. | — | Executed | RCS Construction, Inc. $769,306 · | ||
| Nov 5, 2021 | 46583 | VariousDistrict 3 | Repairing various widths of pavement markings including lines, letters, numbers and symbols This project is located on various highways throughout District 3. This project consists of repairing various widths of pavement markings including lines, letters, numbers and symbols. | — | Executed | ROADSAFE TRAFFIC SYSTEMS, INC. $1,854,677 · | ||
| Nov 5, 2021 | 46924 | LaSalleDistrict 3 | Reconstructing a new retaining wall with associated appurtenances, HMA pavement, aggregate base course, type B The project consists of reconstructing a new retaining wall with associated appurtenances, HMA pavement, aggregate base course, type B gutter, guardrail, pavement markings and other improvements along the Entrance Road to the Buffalo Rock State Park, gross and net length 0.05 mi. | — | Executed | D. Construction, Inc. $637,507 · | ||
| Nov 5, 2021 | 46930 | WinnebagoDistrict 2 | Road reconstruction, bridge repairs, culvert replacements to park roads and parking areas, and all other neces These proposed improvements consist of road reconstruction, bridge repairs, culvert replacements to park roads and parking areas, and all other necessary work to complete the project within the Rock Cut State Park in Winnebago County, gross/net length 3.00 mi. | — | Executed | William Charles Construction Company, LLC $1,855,251 · | ||
| Nov 5, 2021 | 61G85 | LakeDistrict 1 | Pavement reconstruction, resurfacing, curb and gutter replacement, sidewalk replacement, storm sewer, traffic signal improvements and pavement markings on Clavey Road, from 0.4 miles east of US 41 to Green Bay Road in Highland. | — | Rejected | Lake County Grading Company, LLC $9,399,399 · | ||
| Nov 5, 2021 | 61H15 | CookDistrict 1 | Reconstruction and widening of roadway, sidewalk replacement, construct multi-use path, roadway lighting and traffic signal upgrade on IL 19 from Winchester DRive to east of Bartlett Road and on Bartlett Road from East Oltendorf Road to south of IL 19 in Streamwood | — | Executed | Plote Construction, Inc. $5,898,529 · | ||
| Nov 5, 2021 | 61H22 | DuPageDistrict 1 | Traffic signal improvements at various locations in DuPage County | — | Executed | Home Towne Electric, Inc. $5,849,810 · | ||
| Nov 5, 2021 | 61H27 | McHenryDistrict 1 | Pavement widening and construction, curb and gutter, sidewalks, lighting, traffic signals, storm sewer and water main improvements on Main Street from IL 176 to the UP Railroad tracks, and on IL 176 from 2nd Street to Illinois Street in Crystal Lake. | — | Executed | Pir Tano Construction Company, Inc. $4,564,372 · | ||
| Nov 5, 2021 | 61H28 | LakeDistrict 1 | Replace the bridge carrying Central Avenue over an unamed ravine, 0.1 mile west of Lake Michigan in Highland Park. | — | Executed | Dunnet Bay Construction Company $3,315,548 · |
Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.