11-CR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Phoenix Corporation of the Quad Cities Low bidder | $2,337,434 | ||
| 2 | Otto Baum Company, Inc. | $2,368,964 | +1.3% | |
| 3 | Stark Excavating, Inc. | $2,596,372 | +11.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Phoenix Corpora… | #2 Otto Baum Compa… | #3 Stark Excavatin… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0328001 | REG AIR SWEEPER | 3,822 | SQ YD | $2.80 | $2.90 | $2.80 | |
| 2 | X0900064 | MEMBR WTRPR SYS B STR | 157 | SQ YD | $40.00 | $58.96 | $33.00 | |
| 3 | X3550015 | HMA BASE CSE VAR DP | 831 | TON | $145.00 | $152.13 | $147.00 | |
| 4 | X4400196 | HMA SURF REM SPL | 125 | SQ YD | $94.00 | $94.93 | $92.00 | |
| 5 | X4401198 | HMA SURF REM VAR DP | 946 | SQ YD | $15.00 | $14.77 | $14.00 | |
| 6 | X6062700 | CONC GUTTER TA SPL | 750 | FOOT | $80.00 | $65.54 | $70.00 | |
| 7 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $19,500.00 | $15,324.30 | $15,000.00 | |
| 8 | X7011801 | TRAF CONT-PROT BLR 22 | 1 | L SUM | $10,500.00 | $2,083.94 | $2,000.00 | |
| 9 | X7040125 | PIN TEMP CONC BARRIER | 369 | EACH | $40.00 | $29.64 | $44.00 | |
| 10 | Z0001002 | GDRL AGG EROS CONT | 300 | TON | $65.00 | $73.60 | $82.00 | |
| 11 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $10,500.00 | $13,806.08 | $8,640.00 | |
| 12 | Z0022800 | FENCE REMOVAL | 873 | FOOT | $3.25 | $4.47 | $5.00 | |
| 13 | Z0023600 | FILL EXIST CULVERTS | 1 | EACH | $4,000.00 | $2,384.36 | $2,000.00 | |
| 14 | Z0034105 | MATL TRANSFER DEVICE | 795.7 | TON | $20.00 | $20.53 | $20.00 | |
| 15 | Z0062456 | TEMP PAVEMENT | 1,456 | SQ YD | $65.00 | $87.56 | $94.00 | |
| 16 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 17 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | $15.00 | |
| 18 | 20100110 | TREE REMOV 6-15 | 326 | UNIT | $45.00 | $70.52 | $23.00 | |
| 19 | 20100210 | TREE REMOV OVER 15 | 179 | UNIT | $50.00 | $82.09 | $39.00 | |
| 20 | 20200100 | EARTH EXCAVATION | 2,884 | CU YD | $24.00 | $35.93 | $20.00 | |
| 21 | 20300100 | CHANNEL EXCAVATION | 68 | CU YD | $25.00 | $55.37 | $23.00 | |
| 22 | 20400800 | FURNISHED EXCAVATION | 778 | CU YD | $33.00 | $31.15 | $36.00 | |
| 23 | 20700220 | POROUS GRAN EMBANK | 652 | CU YD | $70.00 | $77.09 | $95.00 | |
| 24 | 21001000 | GEOTECH FAB F/GR STAB | 156 | SQ YD | $4.00 | $4.63 | $6.00 | |
| 25 | 21101615 | TOPSOIL F & P 4 | 10,912 | SQ YD | $6.00 | $7.09 | $6.50 | |
| 26 | 25000210 | SEEDING CL 2A | 2.25 | ACRE | $1,900.00 | $1,578.74 | $1,500.00 | |
| 27 | 25000400 | NITROGEN FERT NUTR | 203 | POUND | $1.00 | $1.05 | $1.00 | |
| 28 | 25000500 | PHOSPHORUS FERT NUTR | 203 | POUND | $1.00 | $1.05 | $1.00 | |
| 29 | 25000600 | POTASSIUM FERT NUTR | 203 | POUND | $1.00 | $1.05 | $1.00 | |
| 30 | 25000750 | MOWING | 4.4 | ACRE | $315.00 | $278.91 | $300.00 | |
| 31 | 25100115 | MULCH METHOD 2 | 2.25 | ACRE | $850.00 | $736.74 | $700.00 | |
| 32 | 25100630 | EROSION CONTR BLANKET | 4,835 | SQ YD | $1.50 | $1.47 | $1.40 | |
| 33 | 25200200 | SUPPLE WATERING | 32.8 | UNIT | $200.00 | $210.50 | $200.00 | |
| 34 | 28000250 | TEMP EROS CONTR SEED | 451 | POUND | $4.00 | $2.91 | $4.00 | |
| 35 | 28000305 | TEMP DITCH CHECKS | 322 | FOOT | $11.00 | $13.77 | $14.00 | |
| 36 | 28000315 | AGG DITCH CHECKS | 60 | TON | $125.00 | $97.43 | $95.00 | |
| 37 | 28000400 | PERIMETER EROS BAR | 3,325 | FOOT | $3.00 | $4.35 | $3.00 | |
| 38 | 28000500 | INLET & PIPE PROTECT | 3 | EACH | $150.00 | $171.29 | $160.00 | |
| 39 | 28100109 | STONE RIPRAP CL A5 | 467 | SQ YD | $85.00 | $108.80 | $104.00 | |
| 40 | 28200200 | FILTER FABRIC | 467 | SQ YD | $3.00 | $5.04 | $6.50 | |
| 41 | 30300106 | AGG SUBGRADE IMPR 6 | 2,446 | SQ YD | $14.50 | $14.85 | $27.00 | |
| 42 | 30300112 | AGG SUBGRADE IMPR 12 | 512 | SQ YD | $30.00 | $31.11 | $45.00 | |
| 43 | 35501320 | HMA BASE CSE 9 | 189.3 | SQ YD | $80.00 | $82.25 | $80.00 | |
| 44 | 40600295 | P BIT MATLS TACK CT | 15,855 | POUND | $1.80 | $1.85 | $1.80 | |
| 45 | 40600982 | HMA SURF REM BUTT JT | 332 | SQ YD | $42.00 | $43.22 | $42.00 | |
| 46 | 40600990 | TEMPORARY RAMP | 38 | SQ YD | $45.00 | $43.36 | $42.00 | |
| 47 | 40603200 | P HMA BC IL-4.75 N50 | 374.8 | TON | $185.00 | $190.87 | $184.00 | |
| 48 | 40604160 | P HMA SC IL-9.5 D N50 | 585.7 | TON | $190.00 | $194.71 | $188.00 | |
| 49 | 44000100 | PAVEMENT REM | 1,341 | SQ YD | $20.00 | $19.74 | $32.00 | |
| 50 | 44000153 | HMA SURF REM 1 | 2,544 | SQ YD | $4.50 | $4.53 | $4.50 | |
| 51 | 44201796 | CL D PATCH T4 12 | 183 | SQ YD | $225.00 | $194.57 | $190.00 | |
| 52 | 48101200 | AGGREGATE SHLDS B | 119.4 | TON | $55.00 | $62.87 | $120.00 | |
| 53 | 48203029 | HMA SHOULDERS 8 | 2,618 | SQ YD | $56.00 | $57.89 | $56.00 | |
| 54 | 50100300 | REM EXIST STRUCT N1 | 1 | EACH | $12,500.00 | $22,565.00 | $20,000.00 | |
| 55 | 50100400 | REM EXIST STRUCT N2 | 1 | EACH | $24,500.00 | $25,728.26 | $20,000.00 | |
| 56 | 50200100 | STRUCTURE EXCAVATION | 2,956 | CU YD | $15.00 | $11.88 | $30.00 | |
| 57 | 50200450 | REM/DISP UNS MATL-STR | 29 | CU YD | $45.00 | $72.64 | $100.00 | |
| 58 | 50800205 | REINF BARS, EPOXY CTD | 35,380 | POUND | $1.80 | $1.57 | $1.90 | |
| 59 | 50800515 | BAR SPLICERS | 125 | EACH | $52.00 | $56.19 | $58.00 | |
| 60 | 50901760 | PIPE HANDRAIL | 26 | FOOT | $200.00 | $253.65 | $245.00 | |
| 61 | 51500100 | NAME PLATES | 2 | EACH | $650.00 | $619.52 | $635.00 | |
| 62 | 52200010 | TEMP SHT PILING | 633 | SQ FT | $45.00 | $53.75 | $48.00 | |
| 63 | 54001001 | BOX CUL END SEC C1 | 1 | EACH | $24,525.00 | $14,853.28 | $17,000.00 | |
| 64 | 54003000 | CONC BOX CUL | 154.6 | CU YD | $1,450.00 | $1,362.35 | $1,400.00 | |
| 65 | 54010604 | PCBC 6X4 | 178 | FOOT | $830.00 | $624.43 | $1,900.00 | |
| 66 | 542D0223 | P CUL CL D 1 18 | 45 | FOOT | $76.00 | $73.31 | $68.00 | |
| 67 | 54262718 | METAL FL END SEC 18" | 2 | EACH | $600.00 | $484.47 | $590.00 | |
| 68 | 59100100 | GEOCOMPOSITE WALL DR | 157 | SQ YD | $20.00 | $17.96 | $22.00 | |
| 69 | 60600095 | CLASS SI CONC OUTLET | 13.4 | CU YD | $1,200.00 | $952.69 | $700.00 | |
| 70 | 63000001 | SPBGR TY A 6FT POSTS | 1,350 | FOOT | $38.00 | $38.94 | $38.00 | |
| 71 | 63000030 | SPGR ATT TO CULVERT | 50 | FOOT | $310.00 | $57.89 | $56.00 | |
| 72 | 63100167 | TR BAR TRM T1 SPL TAN | 8 | EACH | $3,200.00 | $4,499.41 | $4,300.00 | |
| 73 | 63200310 | GUARDRAIL REMOV | 1,000 | FOOT | $4.50 | $4.47 | $7.00 | |
| 74 | 66600105 | FUR ERECT ROW MARKERS | 10 | EACH | $350.00 | $345.65 | $255.00 | |
| 75 | 66700205 | PERM SURV MKRS T1 | 5 | EACH | $300.00 | $369.05 | $525.00 | |
| 76 | 66700305 | PERM SURV MKRS T2 | 2 | EACH | $300.00 | $769.37 | $770.00 | |
| 77 | 67000400 | ENGR FIELD OFFICE A | 10 | CAL MO | $1,500.00 | $2,130.11 | $2,200.00 | |
| 78 | 67100100 | MOBILIZATION | 1 | L SUM | $160,000.00 | $138,418.08 | $75,000.00 | |
| 79 | 70100405 | TRAF CONT-PROT 701321 | 1 | EACH | $7,200.00 | $18,260.76 | $17,350.00 | |
| 80 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $950.00 | $736.74 | $700.00 | |
| 81 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $950.00 | $710.43 | $675.00 | |
| 82 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $950.00 | $1,631.36 | $1,550.00 | |
| 83 | 70103815 | TR CONT SURVEILLANCE | 50 | CAL DA | $600.00 | $409.53 | $800.00 | |
| 84 | 70106500 | TEMP BR TRAF SIGNALS | 1 | EACH | $22,500.00 | $19,352.19 | $18,500.00 | |
| 85 | 70106700 | TEMP RUMBLE STRIPS | 6 | EACH | $600.00 | $1,683.99 | $1,600.00 | |
| 86 | 70107025 | CHANGEABLE MESSAGE SN | 120 | CAL DA | $60.00 | $78.94 | $75.00 | |
| 87 | 70300100 | SHORT TERM PAVT MKING | 1,038 | FOOT | $1.40 | $1.47 | $2.75 | |
| 88 | 70300150 | SHRT TRM PAVT MK REM | 346 | SQ FT | $1.40 | $2.00 | $2.00 | |
| 89 | 70300220 | TEMP PVT MK LINE 4 | 7,313 | FOOT | $1.30 | $1.37 | $0.8000 | |
| 90 | 70300280 | TEMP PVT MK LINE 24 | 33 | FOOT | $12.60 | $13.26 | $31.00 | |
| 91 | 70400100 | TEMP CONC BARRIER | 1,088 | FOOT | $30.00 | $27.57 | $30.00 | |
| 92 | 70400200 | REL TEMP CONC BARRIER | 763 | FOOT | $9.00 | $7.40 | $12.00 | |
| 93 | 70600250 | IMP ATTN TEMP NRD TL3 | 4 | EACH | $5,000.00 | $4,157.35 | $4,750.00 | |
| 94 | 70600350 | IMP ATTN REL NRD TL3 | 2 | EACH | $1,500.00 | $473.62 | $370.00 | |
| 95 | 72501000 | TERMINAL MARKER - DA | 8 | EACH | $30.00 | $42.10 | $41.00 | |
| 96 | 78009004 | MOD URETH PM LINE 4 | 8,773 | FOOT | $1.75 | $1.82 | $1.75 | |
| 97 | 78100100 | RAISED REFL PAVT MKR | 31 | EACH | $250.00 | $188.29 | $180.00 | |
| 98 | 78200005 | GRDRAIL REF TYPE A | 18 | EACH | $8.00 | $10.53 | $10.00 | |
| 99 | 78300200 | RAISED REF PVT MK REM | 31 | EACH | $10.00 | $13.35 | $30.00 | |
| 100 | 78300202 | PAVMT MRKG REM WTR BL | 967 | SQ FT | $7.50 | $9.21 | $9.00 |