4,3,2,1(RS-6)
- Let date
- Friday, July 30, 2021
- Contract
- 78838 · job page
- District
- District 9
- County
- Jackson, Perry
- Highway
- Limits
- 17.8 miles of pavement patching, HMA surface removal, HMA surfacing, HMA shoulders and ADA sidewalk improvements on US 51 from near Industrial Park Road in Carbondale to Grant Way in Du Quoin.
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $8,586,162 | ||
| 2 | Samron Midwest Contracting, Inc. | $8,638,795 | +0.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Samron Midwest … |
|---|---|---|---|---|---|---|---|
| 1 | X0326697 | CENTERLN RUM STRIP 8 | 19,557 | FOOT | $0.2800 | $0.4500 | |
| 2 | X4240430 | PC CONC SIDEWALK 5 SP | 531 | SQ FT | $14.34 | $15.00 | |
| 3 | X6330900 | VERT ADJ OF GUARDRAIL | 2,683 | FOOT | $10.30 | $10.25 | |
| 4 | X7030005 | TEMP PAVT MKING REMOV | 149,631 | SQ FT | $0.00 | $0.00 | |
| 5 | Z0033700 | LONG JOINT SEALANT | 134,768 | FOOT | $2.25 | $2.40 | |
| 6 | Z0034105 | MATL TRANSFER DEVICE | 49,588 | TON | $2.26 | $2.00 | |
| 7 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | |
| 8 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | |
| 9 | 20200600 | EXC & GR EX SHOULDER | 1,539 | UNIT | $144.44 | $115.00 | |
| 10 | 40600290 | BIT MATLS TACK CT | 241,768 | POUND | $0.00 | $0.00 | |
| 11 | 40600990 | TEMPORARY RAMP | 871 | SQ YD | $45.75 | $5.00 | |
| 12 | 40602970 | HMA BC IL-9.5FG N70 | 18,077 | TON | $69.91 | $63.50 | |
| 13 | 40603085 | HMA BC IL-19.0 N70 | 2,576 | TON | $65.73 | $63.50 | |
| 14 | 40604062 | HMA SC IL-9.5 D N70 | 29,730 | TON | $73.73 | $63.50 | |
| 15 | 42400800 | DETECTABLE WARNINGS | 50 | SQ FT | $30.53 | $25.00 | |
| 16 | 44000155 | HMA SURF REM 1 1/2 | 74,817 | SQ YD | $1.29 | $1.25 | |
| 17 | 44000160 | HMA SURF REM 2 3/4 | 271,295 | SQ YD | $1.51 | $1.40 | |
| 18 | 44000164 | HMA SURF REM 3 3/4 | 20,270 | SQ YD | $2.06 | $1.75 | |
| 19 | 44000500 | COMB CURB GUTTER REM | 40 | FOOT | $48.03 | $15.00 | |
| 20 | 44000600 | SIDEWALK REM | 499 | SQ FT | $5.53 | $5.00 | |
| 21 | 44201423 | CL C PATCH T1 16 | 20 | SQ YD | $250.00 | $195.00 | |
| 22 | 44201427 | CL C PATCH T2 16 | 4,174 | SQ YD | $139.00 | $180.00 | |
| 23 | 44201431 | CL C PATCH T3 16 | 959 | SQ YD | $136.00 | $178.00 | |
| 24 | 44201433 | CL C PATCH T4 16 | 1,849 | SQ YD | $130.00 | $174.00 | |
| 25 | 44213204 | TIE BARS 3/4 | 18 | EACH | $31.08 | $15.00 | |
| 26 | 48102100 | AGG WEDGE SHLD TYPE B | 1,673 | TON | $35.40 | $25.00 | |
| 27 | 48203029 | HMA SHOULDERS 8 | 45,272 | SQ YD | $30.35 | $36.00 | |
| 28 | 48203100 | HMA SHOULDERS | 1,693 | TON | $69.35 | $63.50 | |
| 29 | 60605000 | COMB CC&G TB6.24 | 58 | FOOT | $71.19 | $35.00 | |
| 30 | 63000001 | SPBGR TY A 6FT POSTS | 850 | FOOT | $36.05 | $37.00 | |
| 31 | 63000370 | LSG OVER CUL 25' SPAN | 50 | FOOT | $118.45 | $125.00 | |
| 32 | 63100085 | TRAF BAR TERM T6 | 2 | EACH | $4,892.50 | $5,100.00 | |
| 33 | 63100167 | TR BAR TRM T1 SPL TAN | 11 | EACH | $4,094.25 | $4,200.00 | |
| 34 | 63100169 | TR BAR TRM T1 SPL FLR | 1 | EACH | $4,145.75 | $4,300.00 | |
| 35 | 63200310 | GUARDRAIL REMOV | 671 | FOOT | $6.18 | $6.25 | |
| 36 | 64200108 | SHOULDER RUM STRIP 8 | 108,532 | FOOT | $0.2400 | $0.2000 | |
| 37 | 64300260 | IMP ATTEN FRD NAR TL3 | 1 | EACH | $30,591.82 | $28,000.00 | |
| 38 | 67000400 | ENGR FIELD OFFICE A | 15 | CAL MO | $1,854.97 | $1,200.00 | |
| 39 | 67100100 | MOBILIZATION | 1 | L SUM | $402,711.97 | $515,000.00 | |
| 40 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $101,642.18 | $94,000.00 | |
| 41 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $61,214.00 | $20,000.00 | |
| 42 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $61,977.73 | $20,000.00 | |
| 43 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $0.00 | $0.00 | |
| 44 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $0.00 | $7,500.00 | |
| 45 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $0.00 | $2,500.00 | |
| 46 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $420.00 | $2,500.00 | |
| 47 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $45.00 | $75.00 | |
| 48 | 70300100 | SHORT TERM PAVT MKING | 28,275 | FOOT | $0.6600 | $1.00 | |
| 49 | 70300150 | SHRT TRM PAVT MK REM | 14,138 | SQ FT | $0.00 | $0.7500 | |
| 50 | 70300210 | TEMP PVT MK LTR & SYM | 1,264 | SQ FT | $0.00 | $0.00 | |
| 51 | 70300240 | TEMP PVT MK LINE 6 | 289,733 | FOOT | $0.00 | $0.00 | |
| 52 | 70300260 | TEMP PVT MK LINE 12 | 3,030 | FOOT | $0.00 | $0.00 | |
| 53 | 70300280 | TEMP PVT MK LINE 24 | 235 | FOOT | $0.00 | $0.00 | |
| 54 | 72501000 | TERMINAL MARKER - DA | 12 | EACH | $41.20 | $43.00 | |
| 55 | 78000100 | THPL PVT MK LTR & SYM | 1,264 | SQ FT | $10.30 | $10.65 | |
| 56 | 78000400 | THPL PVT MK LINE 6 | 289,733 | FOOT | $0.7100 | $0.7500 | |
| 57 | 78000600 | THPL PVT MK LINE 12 | 3,030 | FOOT | $10.30 | $10.65 | |
| 58 | 78000650 | THPL PVT MK LINE 24 | 235 | FOOT | $12.88 | $13.00 | |
| 59 | 78100100 | RAISED REFL PAVT MKR | 2,884 | EACH | $23.89 | $25.00 | |
| 60 | 78200005 | GRDRAIL REF TYPE A | 75 | EACH | $10.30 | $10.75 | |
| 61 | 78300200 | RAISED REF PVT MK REM | 2,884 | EACH | $5.00 | $10.00 |