(1,2)RS-4
- Let date
- Friday, September 17, 2021
- Contract
- 78602 · job page
- District
- District 9
- County
- Saline
- Highway
- Limits
- 5.9 miles of patching, HMA surface removal, HMA surface, HMA shoulders and aggregate shoulders on IL 34 / 145 from the signalized intersection of US 45 and IL 34 / 145 to the intersection of IL 34 and IL 145.
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $2,188,313 | ||
| 2 | Southern Illinois Asphalt Co., Inc. | $2,324,660 | +6.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Southern Illino… |
|---|---|---|---|---|---|---|---|
| 1 | X0326697 | CENTERLN RUM STRIP 8 | 7,151 | FOOT | $1.89 | $1.44 | |
| 2 | X7030005 | TEMP PAVT MKING REMOV | 30,407 | SQ FT | $0.00 | $0.00 | |
| 3 | Z0033700 | LONG JOINT SEALANT | 31,394 | FOOT | $2.36 | $2.32 | |
| 4 | Z0034105 | MATL TRANSFER DEVICE | 13,816 | TON | $2.32 | $1.91 | |
| 5 | 40600290 | BIT MATLS TACK CT | 61,159 | POUND | $0.00 | $0.00 | |
| 6 | 40600990 | TEMPORARY RAMP | 591 | SQ YD | $40.39 | $11.65 | |
| 7 | 40602970 | HMA BC IL-9.5FG N70 | 6,271 | TON | $75.80 | $84.42 | |
| 8 | 40604062 | HMA SC IL-9.5 D N70 | 7,545 | TON | $75.37 | $85.71 | |
| 9 | 44000160 | HMA SURF REM 2 3/4 | 95,840 | SQ YD | $1.47 | $1.09 | |
| 10 | 44201403 | CL C PATCH T2 14 | 1,050 | SQ YD | $166.00 | $240.05 | |
| 11 | 44201407 | CL C PATCH T3 14 | 550 | SQ YD | $162.00 | $240.05 | |
| 12 | 44201409 | CL C PATCH T4 14 | 1,100 | SQ YD | $158.00 | $213.96 | |
| 13 | 48102100 | AGG WEDGE SHLD TYPE B | 2,039 | TON | $31.06 | $30.87 | |
| 14 | 48203100 | HMA SHOULDERS | 314 | TON | $90.76 | $108.18 | |
| 15 | 63000003 | SPBGR TY A 9FT POSTS | 1,588 | FOOT | $42.00 | $41.75 | |
| 16 | 63100087 | TRAF BAR TERM T6A | 1 | EACH | $4,725.00 | $4,696.61 | |
| 17 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,360.00 | $3,339.81 | |
| 18 | 63200310 | GUARDRAIL REMOV | 1,965 | FOOT | $5.25 | $5.22 | |
| 19 | 67100100 | MOBILIZATION | 1 | L SUM | $128,283.90 | $51,013.62 | |
| 20 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $29,556.56 | $10,714.62 | |
| 21 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $28,076.59 | $8,349.53 | |
| 22 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $5,499.24 | $2,191.75 | |
| 23 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $43.54 | $78.28 | |
| 24 | 70300100 | SHORT TERM PAVT MKING | 9,132 | FOOT | $1.07 | $0.5900 | |
| 25 | 70300150 | SHRT TRM PAVT MK REM | 3,044 | SQ FT | $0.00 | $0.00 | |
| 26 | 70300210 | TEMP PVT MK LTR & SYM | 498 | SQ FT | $0.00 | $0.00 | |
| 27 | 70300220 | TEMP PVT MK LINE 4 | 154 | FOOT | $0.00 | $0.00 | |
| 28 | 70300240 | TEMP PVT MK LINE 6 | 87,390 | FOOT | $0.00 | $0.00 | |
| 29 | 70300260 | TEMP PVT MK LINE 12 | 626 | FOOT | $0.00 | $0.00 | |
| 30 | 70300280 | TEMP PVT MK LINE 24 | 710 | FOOT | $0.00 | $0.00 | |
| 31 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $52.50 | $52.19 | |
| 32 | 78001100 | PT PVT MK LTRS & SYMB | 154 | SQ FT | $3.15 | $3.13 | |
| 33 | 78001110 | PAINT PVT MK LINE 4 | 87,390 | FOOT | $0.1400 | $0.1400 | |
| 34 | 78001130 | PAINT PVT MK LINE 6 | 626 | FOOT | $0.2200 | $0.2200 | |
| 35 | 78001150 | PAINT PVT MK LINE 12 | 710 | FOOT | $0.4500 | $0.4500 | |
| 36 | 78001180 | PAINT PVT MK LINE 24 | 50 | FOOT | $4.20 | $4.17 | |
| 37 | 78100100 | RAISED REFL PAVT MKR | 498 | EACH | $33.74 | $38.17 | |
| 38 | 78200005 | GRDRAIL REF TYPE A | 26 | EACH | $10.50 | $10.44 | |
| 39 | 78300200 | RAISED REF PVT MK REM | 498 | EACH | $5.23 | $8.09 |