D9 RESURFACE 2022-1
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $72,246 | ||
| 2 | Southern Illinois Asphalt Co., Inc. | $84,695 | +17.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Southern Illino… |
|---|---|---|---|---|---|---|---|
| 1 | X7030005 | TEMP PAVT MKING REMOV | 575 | SQ FT | $0.00 | $0.00 | |
| 2 | 40600982 | HMA SURF REM BUTT JT | 150 | SQ YD | $16.22 | $18.94 | |
| 3 | 40600990 | TEMPORARY RAMP | 30 | SQ YD | $24.33 | $21.04 | |
| 4 | 40602970 | HMA BC IL-9.5FG N70 | 112 | TON | $100.36 | $135.78 | |
| 5 | 40603085 | HMA BC IL-19.0 N70 | 47 | TON | $159.98 | $312.12 | |
| 6 | 40604052 | HMA SC IL-9.5 C N70 | 126 | TON | $134.74 | $120.58 | |
| 7 | 40700100 | BIT MATLS TACK CT | 1,067 | POUND | $0.00 | $0.00 | |
| 8 | 40800050 | INCIDENTAL HMA SURF | 4 | TON | $303.35 | $746.68 | |
| 9 | 44000155 | HMA SURF REM 1 1/2 | 1,500 | SQ YD | $6.02 | $9.08 | |
| 10 | 48102100 | AGG WEDGE SHLD TYPE B | 17 | TON | $100.00 | $202.68 | |
| 11 | 67100100 | MOBILIZATION | 1 | L SUM | $9,728.78 | $8,036.14 | |
| 12 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $5,825.52 | $3,341.16 | |
| 13 | 70107025 | CHANGEABLE MESSAGE SN | 14 | CAL DA | $113.34 | $83.58 | |
| 14 | 70300100 | SHORT TERM PAVT MKING | 73 | FOOT | $0.3200 | $0.00 | |
| 15 | 70300150 | SHRT TRM PAVT MK REM | 24 | SQ FT | $23.24 | $0.00 | |
| 16 | 70300220 | TEMP PVT MK LINE 4 | 1,725 | FOOT | $0.00 | $0.00 | |
| 17 | 78001110 | PAINT PVT MK LINE 4 | 1,725 | FOOT | $2.04 | $2.06 | |
| 18 | 78300200 | RAISED REF PVT MK REM | 5 | EACH | $32.28 | $0.00 |