D6 DRAINAGE LOGAN CO 2021
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Kinney Contractors, Inc. Low bidder | $122,464 | ||
| 2 | Stark Excavating, Inc. | $161,316 | +31.7% | |
| 3 | Sangamo Construction Company | $161,683 | +32.0% | |
| 4 | Phoenix Corporation of the Quad Cities | $168,124 | +37.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Kinney Contract… | #2 Stark Excavatin… | #3 Sangamo Constru… | #4 Phoenix Corpora… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 28100105 | STONE RIPRAP CL A3 | 100 | SQ YD | $73.00 | $205.00 | $81.75 | $95.00 | |
| 2 | 50105220 | PIPE CULVERT REMOV | 590 | FOOT | $24.90 | $10.00 | $24.60 | $46.00 | |
| 3 | 50800105 | REINFORCEMENT BARS | 301 | POUND | $10.50 | $20.00 | $19.49 | $4.00 | |
| 4 | 54002020 | EXPAN BOLTS 3/4 | 36 | EACH | $57.50 | $190.00 | $47.88 | $37.00 | |
| 5 | 54210189 | PIPE ELBOW 24 | 18 | EACH | $685.00 | $460.00 | $665.98 | $1,350.00 | |
| 6 | 54248510 | CONCRETE COLLAR | 3.5 | CU YD | $1,405.00 | $7,600.00 | $3,667.09 | $3,000.00 | |
| 7 | 60100985 | PIPE DRAINS 24 | 590 | FOOT | $93.50 | $68.00 | $87.70 | $79.75 | |
| 8 | 61000050 | CONC THRUST BLOCKS | 9 | EACH | $620.00 | $900.00 | $1,249.22 | $770.00 | |
| 9 | 67100100 | MOBILIZATION | 1 | L SUM | $7,500.00 | $13,956.00 | $9,539.27 | $13,665.00 | |
| 10 | 70100700 | TRAF CONT-PROT 701406 | 1 | L SUM | $9,750.00 | $25,000.00 | $34,055.67 | $26,500.00 |