17-00157-00-BR
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Samron Midwest Contracting, Inc. Low bidder | $497,333 | ||
| 2 | Dees, Inc. | $512,496 | +3.0% | |
| 3 | E. T. Simonds Construction Company | $582,803 | +17.2% | |
| 4 | Kieffer Bros. Construction Co., Inc. | $631,121 | +26.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Samron Midwest … | #2 Dees, Inc. | #3 E. T. Simonds C… | #4 Kieffer Bros. C… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X2501000 | SEEDING CL 2 SPL | 0.2 | ACRE | $15,000.00 | $21,000.00 | $18,700.00 | $19,820.00 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $3,500.00 | $6,000.00 | $6,793.53 | $6,034.00 | |
| 3 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 4 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 5 | 20100110 | TREE REMOV 6-15 | 24 | UNIT | $0.00 | $0.00 | $65.43 | $38.00 | |
| 6 | 20100210 | TREE REMOV OVER 15 | 37 | UNIT | $0.00 | $0.00 | $63.66 | $50.00 | |
| 7 | 20200100 | EARTH EXCAVATION | 25 | CU YD | $19.00 | $20.00 | $41.20 | $29.00 | |
| 8 | 20300100 | CHANNEL EXCAVATION | 500 | CU YD | $19.00 | $15.00 | $20.69 | $15.00 | |
| 9 | 28100807 | STONE DUMP RIP CL A4 | 547 | TON | $30.00 | $28.00 | $39.95 | $54.00 | |
| 10 | 35100100 | AGG BASE CSE A | 51 | TON | $30.00 | $80.00 | $28.24 | $49.00 | |
| 11 | 40600275 | BIT MATLS PR CT | 202 | POUND | $0.00 | $0.00 | $0.00 | $51.00 | |
| 12 | 40600290 | BIT MATLS TACK CT | 622 | POUND | $0.00 | $0.00 | $0.00 | $16.00 | |
| 13 | 40600982 | HMA SURF REM BUTT JT | 98 | SQ YD | $8.00 | $21.00 | $15.84 | $7.00 | |
| 14 | 40603085 | HMA BC IL-19.0 N70 | 25 | TON | $125.00 | $280.00 | $155.19 | $320.00 | |
| 15 | 40604052 | HMA SC IL-9.5 C N70 | 150 | TON | $125.00 | $109.00 | $112.33 | $126.58 | |
| 16 | 44000157 | HMA SURF REM 2 | 923 | SQ YD | $8.00 | $9.60 | $7.63 | $7.00 | |
| 17 | 48101200 | AGGREGATE SHLDS B | 130 | TON | $42.00 | $67.00 | $27.98 | $39.00 | |
| 18 | 50100100 | REM EXIST STRUCT | 1 | EACH | $22,600.00 | $24,000.00 | $46,363.25 | $16,112.00 | |
| 19 | 50200100 | STRUCTURE EXCAVATION | 101 | CU YD | $19.00 | $15.00 | $24.08 | $29.00 | |
| 20 | 50300225 | CONC STRUCT | 51 | CU YD | $500.00 | $600.00 | $695.04 | $1,196.00 | |
| 21 | 50300280 | CONCRETE ENCASEMENT | 4 | CU YD | $500.00 | $600.00 | $691.89 | $3,025.00 | |
| 22 | 50400605 | P P CONC DK BM 33 DP | 2,465 | SQ FT | $93.00 | $92.00 | $97.20 | $101.00 | |
| 23 | 50800105 | REINFORCEMENT BARS | 5,300 | POUND | $1.50 | $2.00 | $2.41 | $3.58 | |
| 24 | 50900205 | STEEL RAILING TY S1 | 166 | FOOT | $162.00 | $145.00 | $160.82 | $170.00 | |
| 25 | 51201500 | FUR STL PILE HP10X57 | 516 | FOOT | $73.00 | $74.00 | $85.66 | $97.00 | |
| 26 | 51202305 | DRIVING PILES | 516 | FOOT | $0.00 | $1.00 | $1.00 | $5.00 | |
| 27 | 51500100 | NAME PLATES | 1 | EACH | $350.00 | $400.00 | $447.54 | $789.00 | |
| 28 | 58100200 | WATERPRF MEMBRANE SYS | 282 | SQ YD | $31.00 | $43.00 | $54.55 | $20.00 | |
| 29 | 59300100 | CONTR LOW-STRENG MATL | 16 | CU YD | $200.00 | $120.00 | $198.38 | $288.00 | |
| 30 | 63000001 | SPBGR TY A 6FT POSTS | 175 | FOOT | $36.00 | $34.00 | $36.69 | $38.00 | |
| 31 | 63100075 | TRAF BAR TERM T5A | 2 | EACH | $1,750.00 | $1,600.00 | $1,754.50 | $1,859.00 | |
| 32 | 63100167 | TR BAR TRM T1 SPL TAN | 2 | EACH | $4,000.00 | $3,700.00 | $3,982.00 | $4,220.00 | |
| 33 | 63200310 | GUARDRAIL REMOV | 160 | FOOT | $8.00 | $15.00 | $7.92 | $19.00 | |
| 34 | 67100100 | MOBILIZATION | 1 | L SUM | $28,277.00 | $25,000.00 | $39,885.14 | $27,560.00 | |
| 35 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $65.00 | $150.00 | $69.50 | $173.00 | |
| 36 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $45.00 | $70.00 | $44.00 | $46.00 | |
| 37 | 78001110 | PAINT PVT MK LINE 4 | 1,240 | FOOT | $3.30 | $2.00 | $1.49 | $3.50 |