112RS-5
- Let date
- Friday, September 17, 2021
- Contract
- 78898 · job page
- District
- District 9
- County
- Franklin
- Highway
- Limits
- 5.4 miles of patching, HMA surface removal and resurfacing, safety shoulders and guardrail removal and replacement on IL 154 from near the rail crossing in Sesser to near Fitzgerrell Park Drive.
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $4,066,957 | ||
| 2 | Samron Midwest Contracting, Inc. | $4,217,974 | +3.7% | |
| 3 | Southern Illinois Asphalt Co., Inc. | $4,336,786 | +6.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Samron Midwest … | #3 Southern Illino… |
|---|---|---|---|---|---|---|---|---|
| 1 | X7030005 | TEMP PAVT MKING REMOV | 23,736 | SQ FT | $0.00 | $0.00 | $0.00 | |
| 2 | Z0033700 | LONG JOINT SEALANT | 28,017 | FOOT | $2.29 | $2.25 | $2.28 | |
| 3 | Z0034105 | MATL TRANSFER DEVICE | 16,475 | TON | $1.97 | $2.00 | $1.76 | |
| 4 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $6,615.00 | $7,500.00 | $2,577.50 | |
| 5 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 6 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 7 | 20200600 | EXC & GR EX SHOULDER | 481 | UNIT | $192.94 | $250.00 | $251.73 | |
| 8 | 40600290 | BIT MATLS TACK CT | 69,286 | POUND | $0.00 | $0.00 | $0.00 | |
| 9 | 40600982 | HMA SURF REM BUTT JT | 2,410 | SQ YD | $10.62 | $8.00 | $6.02 | |
| 10 | 40600990 | TEMPORARY RAMP | 570 | SQ YD | $48.48 | $25.00 | $13.12 | |
| 11 | 40603085 | HMA BC IL-19.0 N70 | 9,864 | TON | $66.51 | $70.00 | $77.56 | |
| 12 | 40604052 | HMA SC IL-9.5 C N70 | 6,611 | TON | $75.50 | $74.00 | $80.99 | |
| 13 | 40800050 | INCIDENTAL HMA SURF | 150 | TON | $144.86 | $230.00 | $281.63 | |
| 14 | 44000153 | HMA SURF REM 1 | 10,470 | SQ YD | $1.05 | $2.00 | $1.33 | |
| 15 | 44000160 | HMA SURF REM 2 3/4 | 77,592 | SQ YD | $1.08 | $2.00 | $1.17 | |
| 16 | 44000164 | HMA SURF REM 3 3/4 | 173 | SQ YD | $6.50 | $6.00 | $11.12 | |
| 17 | 44201361 | CL C PATCH T1 11 | 40 | SQ YD | $170.00 | $150.00 | $170.12 | |
| 18 | 44201365 | CL C PATCH T2 11 | 960 | SQ YD | $137.00 | $140.00 | $154.65 | |
| 19 | 44201369 | CL C PATCH T3 11 | 171 | SQ YD | $134.00 | $140.00 | $149.49 | |
| 20 | 44201371 | CL C PATCH T4 11 | 220 | SQ YD | $130.00 | $135.00 | $139.19 | |
| 21 | 44201385 | CL C PATCH T1 13 | 3 | SQ YD | $190.00 | $175.00 | $231.97 | |
| 22 | 44201389 | CL C PATCH T2 13 | 941 | SQ YD | $140.00 | $160.00 | $164.96 | |
| 23 | 44201394 | CL C PATCH T3 13 | 179 | SQ YD | $137.00 | $155.00 | $158.77 | |
| 24 | 44201396 | CL C PATCH T4 13 | 418 | SQ YD | $135.00 | $150.00 | $152.59 | |
| 25 | 44300200 | STRIP REF CR CON TR | 32,074 | FOOT | $0.6700 | $1.35 | $0.8900 | |
| 26 | 48102100 | AGG WEDGE SHLD TYPE B | 668 | TON | $40.56 | $35.00 | $36.47 | |
| 27 | 48203029 | HMA SHOULDERS 8 | 23,946 | SQ YD | $31.17 | $28.50 | $38.18 | |
| 28 | 48203100 | HMA SHOULDERS | 1,193 | TON | $77.64 | $95.00 | $92.73 | |
| 29 | 50104000 | BRIDGE RAIL REMOVAL | 197 | FOOT | $6.75 | $11.00 | $16.26 | |
| 30 | 50300255 | CONC SUP-STR | 6 | CU YD | $1,534.64 | $1,850.00 | $3,870.61 | |
| 31 | 50800205 | REINF BARS, EPOXY CTD | 1,440 | POUND | $3.37 | $3.50 | $11.49 | |
| 32 | 63000003 | SPBGR TY A 9FT POSTS | 17,166 | FOOT | $41.20 | $42.25 | $41.24 | |
| 33 | 63100089 | TRAF BAR TERM T6B | 8 | EACH | $5,150.00 | $5,350.00 | $5,155.00 | |
| 34 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,296.00 | $3,500.00 | $3,299.20 | |
| 35 | 63200310 | GUARDRAIL REMOV | 17,766 | FOOT | $5.41 | $5.50 | $5.41 | |
| 36 | 64200108 | SHOULDER RUM STRIP 8 | 55,974 | FOOT | $0.2700 | $0.2000 | $0.2300 | |
| 37 | 67000400 | ENGR FIELD OFFICE A | 7 | CAL MO | $1,925.59 | $1,200.00 | $2,062.00 | |
| 38 | 67100100 | MOBILIZATION | 1 | L SUM | $182,303.42 | $240,000.00 | $57,128.79 | |
| 39 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $30,372.69 | $10,000.00 | $15,924.00 | |
| 40 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $39,855.87 | $7,500.00 | $0.00 | |
| 41 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $34,255.67 | $12,500.00 | $35,029.53 | |
| 42 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $0.00 | $2,500.00 | $2,370.12 | |
| 43 | 70103815 | TR CONT SURVEILLANCE | 18 | CAL DA | $0.00 | $200.00 | $0.00 | |
| 44 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $42.48 | $75.00 | $77.33 | |
| 45 | 70300100 | SHORT TERM PAVT MKING | 11,629 | FOOT | $0.00 | $0.5000 | $0.5000 | |
| 46 | 70300150 | SHRT TRM PAVT MK REM | 3,876 | SQ FT | $0.00 | $1.25 | $0.00 | |
| 47 | 70300210 | TEMP PVT MK LTR & SYM | 61.2 | SQ FT | $0.00 | $0.00 | $0.00 | |
| 48 | 70300220 | TEMP PVT MK LINE 4 | 70,711 | FOOT | $0.00 | $0.00 | $0.00 | |
| 49 | 70300280 | TEMP PVT MK LINE 24 | 52 | FOOT | $0.00 | $0.00 | $0.00 | |
| 50 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $10.30 | $50.00 | $51.55 | |
| 51 | 78000100 | THPL PVT MK LTR & SYM | 61.2 | SQ FT | $24.72 | $25.00 | $24.74 | |
| 52 | 78000200 | THPL PVT MK LINE 4 | 70,711 | FOOT | $0.5200 | $0.5200 | $0.5200 | |
| 53 | 78000650 | THPL PVT MK LINE 24 | 52 | FOOT | $28.84 | $29.50 | $28.87 | |
| 54 | 78100100 | RAISED REFL PAVT MKR | 359 | EACH | $33.99 | $35.00 | $34.02 | |
| 55 | 78200005 | GRDRAIL REF TYPE A | 54 | EACH | $51.50 | $10.10 | $10.31 | |
| 56 | 78200011 | BARR WALL REF TYPE C | 4 | EACH | $10.50 | $33.00 | $5.16 | |
| 57 | 78300200 | RAISED REF PVT MK REM | 359 | EACH | $4.78 | $10.00 | $10.22 |