| Let date | Contract / PPS | County / Division | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| Jun 14, 2019 | 78727 | JeffersonDistrict 9 | 1.3 miles of patching and resurfacing on IL 15 from just east of 44th Street to just west of 25th Street in Mt. Vernon. | — | Executed | Southern Illinois Asphalt Co., Inc. $1,845,801 · | ||
| Jun 14, 2019 | 78728 | FranklinJeffersonDistrict 9 | Patching and resurfacing on I-57 from 1 mile north of the West Frankfort interchange (MP 66) to Bonnie (MP 87.4). | — | Executed | E. T. Simonds Construction Company $4,645,456 · | ||
| Jun 14, 2019 | 78729 | JeffersonDistrict 9 | 3.6 MILES OF HMA SURFACE REMOVAL, INLAYING WITH HMA SURFACE AND BINDER COURSE, PAVEMENT PATCHING, HMA SHOULDERS, STRIPING AND REFLECTIVE PAVEMENT MARKERS ON IL 142 FROM IL 37 TO JUST PAST I-64. | — | Executed | Southern Illinois Asphalt Co., Inc. $1,784,771 · | ||
| Jun 14, 2019 | 85680 | StephensonDistrict 2 | Replace the bridge carrying School Street over Cedar Creek, located south of Hubbard Street in the Village of Winslow. | — | Executed | Fischer Excavating, Inc. $376,862 · | ||
| Jun 14, 2019 | 87691 | IroquoisDistrict 3 | Replace the bridge carrying TR74 over Spring Creek, 1.5 miles southeast of Onarga. | — | Executed | Iroquois Paving Corporation $735,366 · | ||
| Jun 14, 2019 | 87697 | DeKalbDistrict 3 | Pavement widening to add right turn lanes on Peace Road at Freed Road and Brickville Road. | — | Executed | Curran Contracting Company $166,009 · | ||
| Jun 14, 2019 | 87715 | KankakeeDistrict 3 | Resurfacing CH 9 from IL Route 50 to IL Route 1. | — | Executed | Kankakee Valley Construction Co., Inc. & Gallagher Asphalt Corporation $2,358,766 · | ||
| Jun 14, 2019 | 89462 | MarshallDistrict 4 | Resurfacing, aggregate and HMA shoulders, culvert extensions, guardrail and pavement markings on Yankee Lane from IL 17 to Peoria County line. | — | Executed | Advanced Asphalt Company $1,499,476 · | ||
| Jun 14, 2019 | 89715 | FultonDistrict 4 | Install ornamental lighting, sidewalks, curb and gutter, storm sewers, pavement milling, resurfacing and markings on IL 116/78 from Main Street to Lightfoot Road in Farmington. | — | Executed | Otto Baum Company, Inc. $1,756,231 · | ||
| Jun 14, 2019 | 89742 | FultonDistrict 4 | Processing modified soils, HMA resurfacing, aggregate shoulders, pipe culverts and pavement markings on CH 2 from Airport Road to the BSNF Railroad crossing. | — | Executed | Gunther Construction, a div of UCM, Inc. $1,105,754 · | ||
| Jun 14, 2019 | 89750 | PeoriaDistrict 4 | Replace the bridge carrying Streitmattes Road over a Branch of Spoon River, located 1.6 miles Southeast of Duncan. | — | Executed | Stark Excavating, Inc. $823,220 · | ||
| Jun 14, 2019 | 91582 | PiattDistrict 5 | Resurfacing Bridge Street from I-72 to Market Street and resurfacing Marion Street from Market Street to Piatt Street in the City of Monticello. | — | Executed | Cross Construction, Inc. $1,712,280 · | ||
| Jun 14, 2019 | 91755 | McLeanDistrict 5 | Contruction of a bikeway along Old US 66, 1.1 miles South of E 850 North Road to E 550 North Road. | — | Rejected | Rowe Construction, a div of UCM, Inc. $2,132,081 · | ||
| Jun 14, 2019 | 93682 | MacoupinDistrict 6 | Replace the bridge carrying Quarton Road over Otter Creek, located 5.5 miles West of Nilwood. | — | Executed | Kinney Contractors, Inc. $821,741 · | ||
| Jun 14, 2019 | 93724 | AdamsDistrict 6 | Roadway reconstruction on 18th Street from Chestnut Street to Maple Street in the City of Quincy. | — | Executed | Rees Construction Company of Quincy $989,218 · | ||
| Jun 14, 2019 | 93726 | SangamonDistrict 6 | Cold-in-place recylcing along Williamsville Road from McGrath Street to Wolf Creek Road and along Spaulding Orchard Road from Curran Road to IL Route 4. | — | Executed | P. H. Broughton & Sons, Inc. $2,391,511 · | ||
| Jun 14, 2019 | 93727 | AdamsDistrict 6 | Resurfacing and aggregate shoulders on CH 12 from 450 feet South of the intersection with North 1753rd lane southerly to the intersection with Liberty St. in Columbus. | — | Executed | Diamond Construction Company $549,398 · | ||
| Jun 14, 2019 | 93728 | HancockDistrict 6 | Remove and replace steel plate beam guardrail at various locatons throughout Hancock County. | — | Executed | COLLINS & HERMANN, INC. $1,351,915 · | ||
| Jun 14, 2019 | 93730 | PikeDistrict 6 | Replace the bridge carrying CH 4 over Kiser Creek, 2.8 miles southwest of Barry. | — | Executed | County Contractors, Inc. $1,622,768 · | ||
| Jun 14, 2019 | 93733 | SangamonDistrict 6 | Replace the structures carrying the NS Railroad over 5th and 6th Streets, and the construction of new structures to carry the UP Railroad over 5th and 6th Streets in Springfield. | — | Rejected | Freesen, a div of UCM, Inc. $32,059,959 · | ||
| Jun 14, 2019 | 95840 | ShelbyDistrict 7 | Replace the bridge carryingh TR97A over Sand Creek, located 2.2 miles north of Windsor. | — | Executed | Depew and Owen Builders, Inc. $224,688 · | ||
| Jun 14, 2019 | 95844 | WayneDistrict 7 | Replace the bridge carrying FAS 2821 over a branch of the Elm River Drain, 3.5 miles southwest of Mt. Erie. | — | Executed | Allendale Gravel Co., Inc. $368,441 · | ||
| Jun 14, 2019 | 95848 | CrawfordDistrict 7 | Replace the bridge carrying TR 54 over Dogwood Creek, 0.5 miles southeast of Oblong. | — | Executed | Allendale Gravel Co., Inc. $259,455 · | ||
| Jun 14, 2019 | 95850 | ClayDistrict 7 | Replace the bridge carrying TR 179 (Quartz Lane) over Hurrican Creek, 3.0 miles south of Wendelin. | — | Executed | Depew and Owen Builders, Inc. $282,928 · | ||
| Jun 14, 2019 | 95852 | MaconDistrict 7 | Replace the bridge carrying School Road over a ditch 4.4 miles northeast of Argenta. | — | Executed | County Contractors, Inc. $288,990 · | ||
| Jun 14, 2019 | 95853 | CrawfordDistrict 7 | Resurfacing and lime modified soil and aggregate base on various routes from the Jasper County line to North 700th Street in Annapolis. | — | Executed | Ambraw Asphalt Materials, Inc. $3,003,011 · | ||
| Jun 14, 2019 | 97677 | St. ClairDistrict 8 | Streetscape project consisting of ADA compliant sidewalks, curb and gutter, decorative street lighting and resurfacing on West Main Street from 12th Street to 6th Street, and 158 feet east of 'A' Street in Belleville. | — | Executed | Hank's Excavating & Landscaping, Inc. $1,958,263 · | ||
| Jun 14, 2019 | 97679 | MonroeDistrict 8 | Streetscape improvements including resurfacing, decorative street lights and landscaping on Main Street from Whiteside Street to Legion Street and from Cherry Street to IL 3 in columbia. | — | Executed | Baxmeyer Construction, Inc. $2,443,977 · | ||
| Jun 14, 2019 | 97691 | MadisonDistrict 8 | Pavement reconstruction, patching, curb and gutter, ADA compliant sidewalks, storm sewer, and pavement markings on West clay Street from IL 162 to North Main Street in Troy. | — | Executed | Stutz Excavating, Inc. $635,115 · | ||
| Jun 14, 2019 | 97697 | BondDistrict 8 | Replace the bridge carrying TR 156 (dudleyville Road) over Beaver Creek, 2.75 miles south of Greenville. | — | Executed | Keller Construction, Inc. $1,074,740 · | ||
| Jun 14, 2019 | 97698 | MadisonDistrict 8 | Resurfacing on Eastport Plaza Drive from south of the east connection of Executive Drive to Lentes Court in the Collinsville. | — | Executed | Christ Bros. Asphalt, Inc. $628,195 · | ||
| Jun 14, 2019 | 97702 | JerseyDistrict 8 | Replace the bridge carrying Ryan Road over a tributary of Macoupin Creek, 2.8 miles south of Kemper. | — | Executed | Yamnitz, William d/b/a Yamnitz & Associates $266,979 · | ||
| Jun 14, 2019 | 97703 | MadisonDistrict 8 | Construction of a 18" reinforced concrete pavement, railroad track removal and replacement and HMA pavement, located on the East bank of the Chain of Rocks Canal, just North of Locks and Dam 27, within the property of America's Central Port District. | — | Executed | Baxmeyer Construction, Inc. $752,826 · | ||
| Jun 14, 2019 | 97705 | ClintonDistrict 8 | Resurfacing and guardrail replacement on CH 3 from US 50 to Gambill Road. | — | Executed | Howell Paving, Inc. $1,166,409 · | ||
| Jun 14, 2019 | 97706 | St. ClairDistrict 8 | Resurfacing Felling Springs Road from Monsanto Avenue to Queeny Avenue in the Village of Sauget. | — | Executed | Christ Bros. Asphalt, Inc. $317,701 · | ||
| Jun 14, 2019 | 99620 | WilliamsonDistrict 9 | Replace the bridge carrying Grassy Road over Little Wolf Creek, located 0.2 miles West of IL 148. | — | Executed | E. T. Simonds Construction Company $389,831 · | ||
| Jun 14, 2019 | 99621 | JeffersonDistrict 9 | Resurfacing Riddle Lane from IL 15 East Dubois Road. | — | Executed | Microsurfacing Contractors, LLC, a Division of Byrne and Jones Holding Company $324,064 · | ||
| Jun 14, 2019 | 99622 | FranklinDistrict 9 | Resurfacing and aggregate shoulders on Rend City Road from Rend Lake Dam Road to IL 14. | — | Executed | E. T. Simonds Construction Company $871,427 · | ||
| Jun 14, 2019 | 99624 | WilliamsonDistrict 9 | Resurfacing Grassy Road from Spillway Road to West of Caney Branch Lane and resurfacing Spillway Road from Hayton Shcool Road to Grassy Road. | — | Executed | E. T. Simonds Construction Company $512,791 · | ||
| Jun 14, 2019 | 99626 | JeffersonDistrict 9 | Replace the structure carrying Richview Road over Pierce Creek, 3 miles south-southeast of Boyd. | — | Executed | E. T. Simonds Construction Company $678,298 · | ||
| Jun 14, 2019 | 99629 | AlexanderDistrict 9 | Resurfacing Grapevine trail from 0.6 miles east of Moseby Road to Sexton Creek. | — | Executed | E. T. Simonds Construction Company $1,892,007 · | ||
| Jul 12, 2019 | 62B78 | CookDistrict 1 | Pump station 4 reconstruction. I-290 just west of the Des Plaines River in Forest Park. | — | Executed | IHC Construction Companies, L.L.C. $45,950,314 · | ||
| Jul 12, 2019 | 62F29 | CookDistrict 1 | Extensive repairs to SN 016-0575 carrying Sauk Trail over I-57 in Richton. | — | Executed | Lorig Construction Company $4,914,414 · | ||
| Jul 12, 2019 | 62G13 | WillDistrict 1 | 2.73 miles of shoulder widening and milled rumble strips with ditch regrading on IL 53 between Murphey Drive to IL 7 in Romeoville. | — | Executed | D. Construction, Inc. $1,458,014 · | ||
| Jul 12, 2019 | 62G29 | McHenryDistrict 1 | 1.8 miles of resurfacing and pedestrian ramps on IL 47 from State Line Road to IL 173 in the Village of Hebron. | — | Executed | Curran Contracting Company $1,266,714 · | ||
| Jul 12, 2019 | 62G59 | DuPageDistrict 1 | 1.6 miles of resurfacing and ADA sidewalk repair on IL 53 from St. Charles Road to Sidney Avenue in the Villages of Addison and Lombard. | — | Executed | R. W. Dunteman Company $1,651,036 · | ||
| Jul 12, 2019 | 62G69 | CookDistrict 1 | Standard overlay, ADA improvements, and pedestrian traffic signal on IL-58 from Lincoln St. to IL-43 in Morton Grove and Glenview. | — | Executed | Arrow Road Construction Co. $1,267,939 · | ||
| Jul 12, 2019 | 62G70 | CookDistrict 1 | Resurfacing and pedestrian ramps on Central Avenue from just south of 53rd Street to just north of 47th Street in Chicago | — | Executed | Bigane Paving Company $829,349 · | ||
| Jul 12, 2019 | 62G76 | CookDistrict 1 | 1.7745 miles of resurfacing (smart) and ADA improvements on Niles Center Road in Skokie. | — | Executed | Arrow Road Construction Co. $2,125,538 · | ||
| Jul 12, 2019 | 62G77 | CookDistrict 1 | 1.9 miles of resurfacing and pedestrian ramps on Elston Avenue in Chicago. | — | Executed | Bigane Paving Company $1,760,423 · | ||
| Jul 12, 2019 | 62H54 | CookDistrict 1 | Light tower removal and replacement, installing new light towers, light poles, foundations, conduits, cables, and site restoration at I-57 at US 30 in Matteson and I-290/IL-53 at I-90 in Rolling Meadows. | — | Executed | Meade Inc. $1,225,424 · | ||
| Jul 12, 2019 | 62H56 | CookDistrict 1 | 0.95 miles of standard overlay and pedestrian ramp improvements on Touhy Avenue from US 41 to Lawndale Avenue in Lincolnwood and Skokie. | — | Executed | Arrow Road Construction Co. $1,389,978 · | ||
| Jul 12, 2019 | 62H83 | McHenryDistrict 1 | 1.3 miles of standard overlay and ADA improvements on IL 31 from James R. Rakow Road to north of US 14 in Crystal Lake. | — | Executed | Arrow Road Construction Co. $1,542,056 · | ||
| Jul 12, 2019 | 62H92 | LakeDistrict 1 | 1.8 miles of resurfacing and pedestrian ramp improvements along US 45 from Lake Woodlawn Dr. to IL RTE 83 in Mundelein. | — | Executed | Builders Paving, LLC $2,634,888 · | ||
| Jul 12, 2019 | 62H93 | WillDistrict 1 | 1.3 miles of resurfacing along IL 50 from Cicero Avenue to Manhattan-Monee Road in Monee Township | — | Executed | Iroquois Paving Corporation $1,177,820 · | ||
| Jul 12, 2019 | 62H95 | LakeDistrict 1 | 3.56 miles of standard overlay and pedestrian ramp upgrades on IL-176 from Hilltop Terrace to De Webb Blvd. and on IL 60/83 from IL-176 to CN Railroad in Mundelein. | — | Executed | Arrow Road Construction Co. $2,064,157 · | ||
| Jul 12, 2019 | 62H98 | KaneDistrict 1 | 1.20 miles of designed overlay and improvements on IL-31 from Webster St. to Rathbone Ave. in Aurora. | — | Executed | D. Construction, Inc. $1,385,288 · | ||
| Jul 12, 2019 | 62J02 | CookDistrict 1 | 2.63 miles of standard overlay and pedestrian ramp improvements on IL-1 from US 6 to Ridge Rd. in Harvey and Homewood. | — | Executed | D. Construction, Inc. $3,229,163 · | ||
| Jul 12, 2019 | 62J03 | LakeDistrict 1 | 0.98 miles of designed overlay and pedestrian ramp improvements on IL 43 from McGaw Road / Pulaski Road to US 41 in Park City and Waukegan. | — | Executed | Peter Baker & Son Co. $1,997,757 · | ||
| Jul 12, 2019 | 62J21 | CookDistrict 1 | Lining of existing drainage structures on Vermont Street from Western Avenue to Ashland Avenue in the Village of Blue Island. | — | Executed | Benchmark Construction Co., Inc. $251,849 · | ||
| Jul 12, 2019 | 64C06 | HenryDistrict 2 | Resurfacing I-74 from 0.4 miles of IL-81 to 0.2 miles N of IL-17. | — | Executed | Advanced Asphalt Company $17,229,084 · | ||
| Jul 12, 2019 | 64J40 | HenryDistrict 2 | Resurfacing 10.6 miles of IL-78 between 0.2 miles N of IL-92(W) and 0.4 miles N of I-80. | — | Executed | Advanced Asphalt Company $3,358,134 · | ||
| Jul 12, 2019 | 64K15 | HenryDistrict 2 | Pavement patching and HMA resurfacing on IL-82 form IL-92 to Smith St. in Geneseo. | — | Executed | Valley Construction Co. $1,618,459 · | ||
| Jul 12, 2019 | 64M22 | HenryDistrict 2 | 17.12 miles of routing, cleaning, and sealing the centerline and shoulder joints on I-80 from 0.5 miles W of the IL-82 to the Bureau County Line. | — | Executed | Complete Asphalt Service Co. $1,364,888 · | ||
| Jul 12, 2019 | 64N32 | WhitesideDistrict 2 | Finger joint replacement, deck patching, and concrete overlay on SN 098-0100 carrying IL-78 over the rock river on the North edge of Prophetstown. | — | Executed | Civil Constructors, Inc. $857,277 · | ||
| Jul 12, 2019 | 64N55 | WhitesideDistrict 2 | Cold milling, HMA resurfacing and drainage improvements form IL-40 to 0.2 miles E and IL-40 from US 30 to 0.4 miles S. | — | Executed | Martin & Company Excavating $1,492,361 · | ||
| Jul 12, 2019 | 66A81 | FordDistrict 3 | 6 miles of milling and resurfacing of US 24 from Livingston county line to the Iroquois county line. | — | Executed | Iroquois Paving Corporation $2,795,668 · | ||
| Jul 12, 2019 | 66A84 | IroquoisDistrict 3 | 8.09 miles of 3.75 milling and resurfacing from US 24 to US 45/52. | — | Executed | Iroquois Paving Corporation $3,777,848 · | ||
| Jul 12, 2019 | 66B06 | LaSalleDistrict 3 | 10.9 miles of 3P milling and resurfacing on mainline pavement and pavement striping on IL-18 from IL-251 to WCL of Streator. | — | Executed | Advanced Asphalt Company $4,990,242 · | ||
| Jul 12, 2019 | 66D54 | LaSalleDistrict 3 | 6.3 miles of milling and resurfacing 3.75" of HMA at US-34 mainline and shoulders. Including removing and resurfacing 1" of HMA surface at bridge decks. | — | Executed | Curran Contracting Company $2,407,407 · | ||
| Jul 12, 2019 | 66D59 | KankakeeLivingstonDistrict 3 | 1.954 miles of 3P milling and resurfacing W of Reddick to 0.3 mile W of TR 48. It also includes centerline and shoulder rumble strips. | — | Executed | Kankakee Valley Construction Company, Inc. $1,002,537 · | ||
| Jul 12, 2019 | 66F25 | LivingstonDistrict 3 | 10.2 miles of 3P milling and resurfacing of 3.75" on or 66 from IL-23 to Prairie St. on Odell. Other work included is shoulder stone, pavement marking and raised reflective pavement markers. | — | Executed | Kankakee Valley Construction Company, Inc. $4,643,509 · | ||
| Jul 12, 2019 | 66F86 | IroquoisDistrict 3 | 8.948 miles of 3P milling and resurfacing on IL-1 in Watseka to the Indiana St line. | — | Executed | Iroquois Paving Corporation $5,596,979 · | ||
| Jul 12, 2019 | 66H58 | BureauDistrict 3 | 9.9 miles of 3P 3.75" milling and resurfacing on IL-26 from N of IL-92 to S of red covered bridge road according to tamp designed overlay policy. Other work includes shoulder stone, pavement marking, and raised reflective pavement markers. | — | Executed | Advanced Asphalt Company $4,128,627 · | ||
| Jul 12, 2019 | 68C97 | TazewellWoodfordDistrict 4 | Resurfacing on BUS 24 from E of Lynn St. in Washington to US 24, W of Eureka. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $3,974,381 · | ||
| Jul 12, 2019 | 68D00 | HenryStarkDistrict 4 | 2.93 miles of resurfacing, patching, and partial depth patching from N of IL-17 (W) to just N of the Stark/Henry County Line. | — | Executed | Advanced Asphalt Company $1,709,624 · | ||
| Jul 12, 2019 | 68D68 | MarshallPeoriaDistrict 4 | 7.5 miles of resurfacing on IL-29 from Senachwine Creek in Chilicothe to IL-17 E in Sparland. | — | Executed | Advanced Asphalt Company $3,791,715 · | ||
| Jul 12, 2019 | 68D88 | PeoriaDistrict 4 | Milling and resurfacing on IL-9 from 0.27 miles E of US 24 to the McNaughton bridge. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $2,138,535 · | ||
| Jul 12, 2019 | 68E93 | PeoriaDistrict 4 | Resurfacing on IL-40 from Ravinswood Rd. to N of Timber Lane. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $2,243,611 · | ||
| Jul 12, 2019 | 68F10 | HendersonDistrict 4 | Resurfacing Gulfport Interchange US 34 ramp EB to US 4, US 34 EB to Chinn Ave, US 34 WB to US 34 ramp WB. and Chinn Ave to US 34. | — | Executed | Gunther Construction, a div of UCM, Inc. $1,415,327 · | ||
| Jul 12, 2019 | 70952 | ChampaignDistrict 5 | 3.504 miles of pavement preservation designed HMA overlay of Leverett Rd. from Market St. to US 45 in Champaign county. | — | Executed | Cross Construction, Inc. $1,383,380 · | ||
| Jul 12, 2019 | 70B09 | McLeanDistrict 5 | 6.225 miles of pavement rehabilitation: standard overlay from N of Lexington to the Livingston CO. line. | — | Executed | H. J. Eppel & Co. $1,599,110 · | ||
| Jul 12, 2019 | 70E01 | DouglasPiattDistrict 5 | 9.693 miles of cape seal operations from Moultrie County line to US RTE 45 W of Tuscola. | — | Executed | A. C. Pavement Striping Co. $792,895 · | ||
| Jul 12, 2019 | 70E04 | McLeanDistrict 5 | Pavement preservation smart overlay from 0.1 miles W of Morris Ave to 0.3 miles W of US 51 BUS in Bloomington. | — | Executed | Rowe Construction, a div of UCM, Inc. $482,865 · | ||
| Jul 12, 2019 | 72K77 | MacoupinMontgomeryDistrict 6 | Painting three bridges on I-55 in Macoupin and Montgomery Counties (SN 068-0052, 059-0037, 059-0038). | — | Executed | All States Painting, Inc. $448,000 · | ||
| Jul 12, 2019 | 72L37 | MasonDistrict 6 | 11.9 miles of resurfacing on US 136 from east of Charlotte Street in Havana to 0.1 miles east of TR 2800 (Forest City Road). | — | Executed | Illinois Valley Paving, a div of UCM, Inc. $5,996,613 · | ||
| Jul 12, 2019 | 74461 | CumberlandDistrict 7 | Milling and resurfacing on I-57 from US 45 to the Coles County line. | — | Executed | Howell Paving, Inc. $9,861,290 · | ||
| Jul 12, 2019 | 74718 | ColesDistrict 7 | 4.9 miles of resurfacing on IL 130 from Fairgrange Road to the Douglas County line. | — | Executed | Ne-Co Asphalt Co., Inc. $2,351,176 · | ||
| Jul 12, 2019 | 74778 | ColesDistrict 7 | 5.9 miles of patching, resurfacing and guardrail replacement on IL 16 from west of Douglas Drive in Charleston. | — | Executed | Howell Paving, Inc. $9,115,672 · | ||
| Jul 12, 2019 | 76K38 | MonroeDistrict 8 | 3.4 miles of resurfacing on IL 3 from just north of Gilmore Lake Road to Halifax Drive. | — | Executed | Christ Bros. Asphalt, Inc. $3,841,982 · | ||
| Jul 12, 2019 | 76K42 | MadisonDistrict 8 | 3.1 miles of resurfacing and new full depth shoulders on IL 140 from just east of Moreland Road to 0.2 miles west of IL 159. | — | Executed | Christ Bros. Asphalt, Inc. $3,190,436 · | ||
| Jul 12, 2019 | 76K44 | WashingtonDistrict 8 | 4.7 miles of resurfacing and guardrail upgrades on IL 127 from Conservation Road to the Perry County line. | — | Executed | The Kilian Corporation $3,052,150 · | ||
| Jul 12, 2019 | 76L12 | JerseyDistrict 8 | 5.4 miles of resurfacing on IL 267 from the Greene County line to the Macoupin County line. | — | Executed | Charles E. Mahoney Co. $4,082,945 · | ||
| Jul 12, 2019 | 76L13 | BondDistrict 8 | Resurfacing on IL 127 from the Montgomery County line to just north of the IL 140 junction. | — | Executed | Christ Bros. Asphalt, Inc. $6,859,082 · | ||
| Jul 12, 2019 | 76L19 | RandolphDistrict 8 | 2.8 miles of resurfacing on IL 3 from 0.2 miles south of 1st Street in Ruma to 0.2 miles south of South Prairie Road. | — | Executed | E. T. Simonds Construction Company $1,171,923 · | ||
| Jul 12, 2019 | 76M64 | ClintonDistrict 8 | 2.5 miles of resurfacing on IL 160 from the Madison County line to 0.3 miles north of US 50. | — | Executed | Christ Bros. Asphalt, Inc. $657,842 · | ||
| Jul 12, 2019 | 76M65 | MadisonDistrict 8 | 9.1 miles of crack and joint seal on I-70 from 2.5 miles east of the I-55/70 interchange to 0.1 miles west of Prairie Road. | — | Executed | Kinney Contractors, Inc. $209,505 · | ||
| Jul 12, 2019 | 76M66 | St. ClairDistrict 8 | 11.7 miles of crack and joint seal on I-64 from 0.6 miles east of I-55/70 to 0.3 miles west of IL 157 and from 0.2 miles west of Greenmount to 0.4 miles west of IL 4. | — | Executed | Kinney Contractors, Inc. $380,724 · | ||
| Jul 12, 2019 | 76M72 | MadisonDistrict 8 | 6.5 miles of resurfacing on IL 255 from I-270 to IL 143. | — | Executed | The Kilian Corporation $7,935,826 · | ||
| Jul 12, 2019 | 76M73 | St. ClairDistrict 8 | 4.4 miles of resurfacing on IL 158/US 50 from US 50 to IL 161. | — | Executed | The Kilian Corporation $1,394,416 · |
Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.