Bid tab 93730

Let Jun 14, 2019 · District 6 · Pike Sign up free

‹ Jun 2019 results

15-00098-00-BR

Let date
Friday, June 14, 2019
Contract
93730 · job page
District
District 6
County
Pike
Highway
Limits
Replace the bridge carrying CH 4 over Kiser Creek, 2.8 miles southwest of Barry.

Bidders 3

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 County Contractors, Inc. Low bidder $1,622,768
2 Sangamo Construction Company $1,967,926 +21.3%
3 Halverson Construction Co., Inc. $2,174,130 +34.0%

Bid tab: unit prices 46 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 County Contract…#2 Sangamo Constru…#3 Halverson Const…
1XX006199 STEEL BR RAIL SM SPL560FOOT $160.00 $175.96 $172.00
2X2501000 SEEDING CL 2 SPL0.6ACRE $7,200.00 $7,258.67 $6,860.00
3X2810210 STONE RIPRAP CL A5 SP1,705TON $38.00 $43.55 $45.00
4X7010216 TRAF CONT & PROT SPL1L SUM $3,000.00 $4,233.41 $6,500.00
5Z0046304 P UNDR FOR STRUCT 4121FOOT $22.00 $19.84 $33.00
6Z0076600 TRAINEES1,000HOUR $0.8000 $0.8000 $0.8000
7Z0076604 TRAINEES TPG1,000HOUR $15.00 $15.00 $15.00
820200100 EARTH EXCAVATION240CU YD $23.00 $41.99 $20.00
920300100 CHANNEL EXCAVATION2,925CU YD $10.00 $19.74 $12.00
1020400800 FURNISHED EXCAVATION855CU YD $7.50 $20.00 $30.00
1128000250 TEMP EROS CONTR SEED750POUND $1.00 $4.05 $2.00
1228000400 PERIMETER EROS BAR1,110FOOT $1.50 $5.08 $6.00
1335100100 AGG BASE CSE A935TON $20.00 $20.77 $21.00
1440600275 BIT MATLS PR CT3,206POUND $1.00 $2.16 $1.02
1540603080 HMA BC IL-19.0 N50164TON $166.00 $161.42 $163.20
1640603310 HMA SC "C" N50107TON $169.00 $170.53 $229.50
1748101200 AGGREGATE SHLDS B117TON $45.00 $53.45 $43.00
1850100100 REM EXIST STRUCT1EACH $31,000.00 $49,880.34 $100,000.00
1950200100 STRUCTURE EXCAVATION225CU YD $10.00 $24.80 $23.00
2050200300 COFFERDAM EXCAVATION420CU YD $20.00 $62.65 $45.00
2150201121 COFFERDAM TYP 2 LOC 11EACH $10,000.00 $52,513.46 $100,000.00
2250201122 COFFERDAM TYP 2 LOC 21EACH $10,000.00 $52,513.46 $100,000.00
2350300225 CONC STRUCT206.1CU YD $575.00 $790.68 $800.00
2450300255 CONC SUP-STR278.5CU YD $975.00 $1,078.54 $950.00
2550300260 BR DECK GROOVING934SQ YD $6.75 $6.61 $6.50
2650300265 SEAL COAT CONC165CU YD $150.00 $197.87 $400.00
2750300300 PROTECTIVE COAT1,089SQ YD $3.50 $2.46 $1.75
2850500105 F & E STRUCT STEEL1L SUM $427,000.00 $426,667.64 $520,000.00
2950500505 STUD SHEAR CONNECTORS4,035EACH $3.65 $5.29 $3.75
3050800205 REINF BARS, EPOXY CTD101,700POUND $1.30 $1.55 $1.60
3151200959 FUR M S PILE 14X0.3121,489FOOT $85.00 $70.53 $52.00
3251202305 DRIVING PILES1,489FOOT $0.1000 $0.0200 $0.1000
3351203200 TEST PILE MET SHELLS4EACH $5,095.00 $4,959.47 $7,000.00
3451204650 PILE SHOES34EACH $495.00 $80.00 $500.00
3551500100 NAME PLATES1EACH $620.00 $420.18 $750.00
3652100010 ELAST BEARING ASSY T15EACH $1,800.00 $3,898.60 $640.00
3752100520 ANCHOR BOLTS 130EACH $110.00 $84.27 $120.00
3852100530 ANCHOR BOLTS 1 1/410EACH $125.00 $141.18 $165.00
3958600101 GRANULAR BACKFILL STR165CU YD $44.00 $53.15 $55.00
4059100100 GEOCOMPOSITE WALL DR70SQ YD $26.00 $21.22 $38.00
4163100087 TRAF BAR TERM T6A2EACH $3,505.00 $3,518.23 $3,660.00
4263100167 TR BAR TRM T1 SPL TAN2EACH $3,085.00 $3,094.99 $3,220.00
4363200310 GUARDRAIL REMOV312FOOT $5.00 $12.38 $11.92
4467100100 MOBILIZATION1L SUM $60,740.00 $116,107.63 $130,000.00
4572501000 TERMINAL MARKER - DA4EACH $42.00 $42.33 $40.00
4678001110 PAINT PVT MK LINE 41,600FOOT $2.00 $3.17 $0.7500