17-00152-00-BR
- Let date
- Friday, June 14, 2019
- Contract
- 99620 · job page
- District
- District 9
- County
- Williamson
- Highway
- Limits
- Replace the bridge carrying Grassy Road over Little Wolf Creek, located 0.2 miles West of IL 148.
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $389,831 | ||
| 2 | Samron Midwest Contracting, Inc. | $407,315 | +4.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Samron Midwest … |
|---|---|---|---|---|---|---|---|
| 1 | X2090210 | POROUS GRAN BACK SPEC | 65 | CU YD | $50.71 | $60.00 | |
| 2 | X2501000 | SEEDING CL 2 SPL | 0.3 | ACRE | $10,941.33 | $10,000.00 | |
| 3 | Z0046304 | P UNDR FOR STRUCT 4 | 140 | FOOT | $13.36 | $23.00 | |
| 4 | 20100110 | TREE REMOV 6-15 | 50 | UNIT | $47.10 | $40.00 | |
| 5 | 20100210 | TREE REMOV OVER 15 | 150 | UNIT | $36.12 | $52.00 | |
| 6 | 20200100 | EARTH EXCAVATION | 80 | CU YD | $67.69 | $10.00 | |
| 7 | 20400800 | FURNISHED EXCAVATION | 395 | CU YD | $39.19 | $18.00 | |
| 8 | 25100630 | EROSION CONTR BLANKET | 598 | SQ YD | $2.20 | $2.00 | |
| 9 | 28000250 | TEMP EROS CONTR SEED | 30 | POUND | $4.96 | $0.00 | |
| 10 | 28000400 | PERIMETER EROS BAR | 510 | FOOT | $6.88 | $5.00 | |
| 11 | 28100809 | STONE DUMP RIP CL A5 | 550 | TON | $35.13 | $37.00 | |
| 12 | 28300400 | AGGREGATE DITCH | 85 | TON | $39.02 | $43.00 | |
| 13 | 35101400 | AGG BASE CSE B | 38 | TON | $46.14 | $34.00 | |
| 14 | 35600724 | HMA BC WID 12 | 117 | SQ YD | $112.48 | $131.00 | |
| 15 | 40600275 | BIT MATLS PR CT | 276 | POUND | $0.00 | $0.00 | |
| 16 | 40600290 | BIT MATLS TACK CT | 142 | POUND | $0.00 | $0.00 | |
| 17 | 40600625 | LEV BIND MM N50 | 30 | TON | $194.00 | $225.00 | |
| 18 | 40600982 | HMA SURF REM BUTT JT | 134 | SQ YD | $34.57 | $40.00 | |
| 19 | 40603310 | HMA SC "C" N50 | 60 | TON | $194.00 | $225.00 | |
| 20 | 40800050 | INCIDENTAL HMA SURF | 5 | TON | $194.00 | $225.00 | |
| 21 | 44000100 | PAVEMENT REM | 122 | SQ YD | $24.25 | $10.00 | |
| 22 | 44201789 | CL D PATCH T2 12 | 122 | SQ YD | $94.85 | $110.00 | |
| 23 | 48101200 | AGGREGATE SHLDS B | 179 | TON | $53.42 | $35.00 | |
| 24 | 50101500 | REM EXIST SUP-STR | 1 | EACH | $72,393.47 | $88,000.00 | |
| 25 | 50300255 | CONC SUP-STR | 59.7 | CU YD | $1,494.44 | $1,250.00 | |
| 26 | 50300260 | BR DECK GROOVING | 95 | SQ YD | $43.36 | $100.00 | |
| 27 | 50300300 | PROTECTIVE COAT | 125 | SQ YD | $1.79 | $15.00 | |
| 28 | 50800205 | REINF BARS, EPOXY CTD | 24,340 | POUND | $1.24 | $1.50 | |
| 29 | 51500100 | NAME PLATES | 1 | EACH | $804.43 | $370.00 | |
| 30 | 542A0223 | P CUL CL A 1 18 | 30 | FOOT | $75.99 | $41.00 | |
| 31 | 59100100 | GEOCOMPOSITE WALL DR | 31 | SQ YD | $30.13 | $30.00 | |
| 32 | 60108108 | PIPE UNDERDR T 1 8 | 92 | FOOT | $27.68 | $20.00 | |
| 33 | 63100085 | TRAF BAR TERM T6 | 4 | EACH | $3,410.00 | $3,585.00 | |
| 34 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,272.50 | $3,430.00 | |
| 35 | 67100100 | MOBILIZATION | 1 | L SUM | $30,681.04 | $42,619.00 | |
| 36 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $33.00 | $35.00 | |
| 37 | 78001110 | PAINT PVT MK LINE 4 | 850 | FOOT | $3.20 | $2.00 | |
| 38 | 78200006 | GRDRAIL REF TYPE B | 4 | EACH | $11.00 | $12.00 | |
| 39 | 78200010 | BARR WALL REF TYPE B | 2 | EACH | $13.20 | $14.00 |