28Y-SR
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $1,458,014 | ||
| 2 | K-Five Construction Corporation | $1,634,994 | +12.1% | |
| 3 | Gallagher Asphalt Corporation | $1,747,946 | +19.9% | |
| 4 | R. W. Dunteman Company | $1,878,845 | +28.9% | |
| 5 | P. T. Ferro Construction Co. | $1,958,143 | +34.3% | |
| 6 | Austin Tyler Construction, Inc. | $2,012,305 | +38.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 K-Five Construc… | #3 Gallagher Aspha… | #4 R. W. Dunteman … | #5 P. T. Ferro Con… | #6 Austin Tyler Co… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | C2C05815 | S-RHUS AROMA GRO 15C | 1,000 | EACH | $67.10 | $28.00 | $64.50 | $61.00 | $28.00 | $64.00 | |
| 2 | K0029618 | WEED CONT BROADLF TRF | 5 | GALLON | $187.00 | $1,500.00 | $180.00 | $170.00 | $75.00 | $2,000.00 | |
| 3 | X0325222 | WEED CONT BASAL TRTMT | 5 | GALLON | $456.50 | $1,500.00 | $450.00 | $415.00 | $75.00 | $1,100.00 | |
| 4 | X0326898 | CENTERLN RUM STRIP 16 | 8,037 | FOOT | $0.6800 | $1.00 | $1.00 | $0.9200 | $1.05 | $0.9000 | |
| 5 | X0327120 | WEED CTRL NTV LSCP EN | 3.12 | ACRE | $1,650.00 | $5,500.00 | $1,600.00 | $1,500.00 | $2,400.00 | $2,350.00 | |
| 6 | X0327979 | PAVMT MRKG REM GRIND | 5,358 | SQ FT | $1.38 | $0.9000 | $0.7000 | $0.6500 | $1.50 | $0.5000 | |
| 7 | X2020110 | GRADING & SHAP SHLDRS | 145 | UNIT | $60.00 | $0.0100 | $85.00 | $259.95 | $0.0100 | $65.00 | |
| 8 | X2200020 | FENCE REM & REINSTALL | 200 | FOOT | $26.40 | $62.00 | $32.00 | $61.54 | $61.50 | $70.00 | |
| 9 | X2501800 | SEEDING CL 4 MOD | 0.4 | ACRE | $2,566.30 | $5,000.00 | $2,500.00 | $2,333.00 | $1,550.00 | $9,000.00 | |
| 10 | X2503110 | MOWING SPL | 0.61 | ACRE | $825.00 | $600.00 | $800.00 | $750.00 | $550.00 | $1,200.00 | |
| 11 | X5537800 | SS CLEANED 12 | 429 | FOOT | $7.04 | $6.00 | $6.50 | $6.00 | $6.00 | $7.00 | |
| 12 | X5538200 | SS CLEANED 24 | 88 | FOOT | $16.78 | $12.00 | $13.00 | $12.00 | $12.00 | $17.00 | |
| 13 | X7800815 | HS THPL PM LN 4 | 16,074 | FOOT | $0.5300 | $0.4000 | $0.4500 | $0.4300 | $0.5800 | $0.5000 | |
| 14 | Z0004562 | COMB C C&G REM & REPL | 454 | FOOT | $45.00 | $110.00 | $78.00 | $120.03 | $75.00 | $60.00 | |
| 15 | Z0005305 | BOX CUL TO BE CLEANED | 124 | FOOT | $20.00 | $58.00 | $60.00 | $58.00 | $58.00 | $150.00 | |
| 16 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $8,500.00 | $18,000.00 | $29,000.00 | $18,500.00 | $18,500.00 | $18,000.00 | |
| 17 | Z0018500 | DRAINAGE STR CLEANED | 5 | EACH | $451.00 | $350.00 | $370.00 | $350.00 | $350.00 | $450.00 | |
| 18 | Z0030850 | TEMP INFO SIGNING | 103 | SQ FT | $25.00 | $0.8500 | $18.00 | $17.00 | $15.00 | $20.00 | |
| 19 | Z0064800 | SELECTIVE CLEARING | 136 | UNIT | $308.00 | $180.00 | $195.00 | $180.00 | $280.00 | $500.00 | |
| 20 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 21 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | |
| 22 | 20100500 | TREE REMOV ACRES | 0.4 | ACRE | $33,000.00 | $5,000.00 | $5,300.00 | $5,000.00 | $30,000.00 | $23,000.00 | |
| 23 | 20200100 | EARTH EXCAVATION | 4,811 | CU YD | $20.00 | $20.00 | $49.00 | $42.90 | $35.00 | $42.00 | |
| 24 | 20201200 | REM & DISP UNS MATL | 1,062 | CU YD | $25.00 | $60.00 | $52.00 | $42.90 | $35.00 | $120.00 | |
| 25 | 20800150 | TRENCH BACKFILL | 83 | CU YD | $60.00 | $42.00 | $60.00 | $42.00 | $55.00 | $40.00 | |
| 26 | 21001000 | GEOTECH FAB F/GR STAB | 788 | SQ YD | $3.00 | $2.00 | $4.00 | $1.49 | $2.00 | $2.25 | |
| 27 | 21101615 | TOPSOIL F & P 4 | 3,354 | SQ YD | $7.15 | $4.50 | $6.90 | $6.50 | $3.75 | $7.00 | |
| 28 | 25000210 | SEEDING CL 2A | 0.7 | ACRE | $3,461.70 | $3,500.00 | $3,325.00 | $3,147.00 | $1,800.00 | $5,800.00 | |
| 29 | 25000400 | NITROGEN FERT NUTR | 149 | POUND | $3.30 | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 | |
| 30 | 25000500 | PHOSPHORUS FERT NUTR | 149 | POUND | $3.30 | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 | |
| 31 | 25000600 | POTASSIUM FERT NUTR | 149 | POUND | $3.30 | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 | |
| 32 | 25000775 | SELECT MOWING STAKES | 10 | EACH | $39.60 | $30.00 | $38.00 | $36.00 | $100.00 | $35.00 | |
| 33 | 25003210 | INTERSEED CL 2A | 0.54 | ACRE | $1,983.30 | $3,500.00 | $2,000.00 | $1,803.00 | $1,700.00 | $4,600.00 | |
| 34 | 25003312 | INTERSEED CL 4A | 2.5 | ACRE | $2,189.00 | $4,500.00 | $2,100.00 | $1,990.00 | $1,700.00 | $2,300.00 | |
| 35 | 25003324 | INTERSEED CL 5B | 0.07 | ACRE | $2,323.20 | $10,000.00 | $2,225.00 | $2,112.00 | $2,000.00 | $11,000.00 | |
| 36 | 25100630 | EROSION CONTR BLANKET | 8,012 | SQ YD | $1.10 | $2.20 | $1.00 | $1.00 | $1.10 | $1.50 | |
| 37 | 28000400 | PERIMETER EROS BAR | 28,842 | FOOT | $2.75 | $2.00 | $2.65 | $2.50 | $2.00 | $3.50 | |
| 38 | 30300001 | AGG SUBGRADE IMPROVE | 263 | CU YD | $50.00 | $60.00 | $65.00 | $47.63 | $75.00 | $55.00 | |
| 39 | 40603340 | HMA SC "D" N70 | 168 | TON | $80.00 | $100.00 | $125.00 | $327.86 | $185.00 | $100.00 | |
| 40 | 40800029 | BIT MATLS TACK CT | 4,222 | POUND | $0.0100 | $0.0100 | $0.0100 | $3.30 | $0.0100 | $0.0100 | |
| 41 | 44000157 | HMA SURF REM 2 | 1,500 | SQ YD | $12.00 | $5.00 | $15.00 | $16.31 | $20.00 | $25.00 | |
| 42 | 44201815 | CL D PATCH T2 14 | 1,578 | SQ YD | $100.00 | $55.00 | $94.00 | $102.56 | $150.00 | $125.00 | |
| 43 | 44201819 | CL D PATCH T3 14 | 338 | SQ YD | $95.00 | $55.00 | $94.00 | $90.59 | $140.00 | $125.00 | |
| 44 | 44201821 | CL D PATCH T4 14 | 338 | SQ YD | $90.00 | $55.00 | $94.00 | $81.29 | $110.00 | $125.00 | |
| 45 | 48203029 | HMA SHOULDERS 8 | 7,882 | SQ YD | $46.60 | $70.00 | $50.00 | $60.05 | $50.00 | $43.00 | |
| 46 | 550A0340 | STORM SEW CL A 2 12 | 229 | FOOT | $65.00 | $44.00 | $61.50 | $44.00 | $100.00 | $57.00 | |
| 47 | 550A0360 | STORM SEW CL A 2 15 | 230 | FOOT | $75.00 | $48.00 | $66.75 | $48.00 | $105.00 | $60.00 | |
| 48 | 550A0380 | STORM SEW CL A 2 18 | 231 | FOOT | $5.00 | $50.00 | $69.50 | $50.00 | $110.00 | $62.00 | |
| 49 | 60201340 | CB TA 4 DIA T24F&G | 5 | EACH | $2,400.00 | $2,150.00 | $3,000.00 | $2,150.00 | $3,000.00 | $3,000.00 | |
| 50 | 60237460 | INLETS TA T23F&G | 3 | EACH | $1,600.00 | $1,250.00 | $1,750.00 | $1,250.00 | $1,700.00 | $2,000.00 | |
| 51 | 63000001 | SPBGR TY A 6FT POSTS | 957 | FOOT | $26.24 | $29.50 | $25.25 | $29.47 | $29.50 | $35.00 | |
| 52 | 63000030 | SPGR ATT TO CULVERT | 24 | FOOT | $170.94 | $125.00 | $165.00 | $124.24 | $125.00 | $145.00 | |
| 53 | 63100167 | TR BAR TRM T1 SPL TAN | 18 | EACH | $2,915.00 | $4,000.00 | $3,000.00 | $3,939.70 | $3,940.00 | $4,500.00 | |
| 54 | 63200310 | GUARDRAIL REMOV | 120 | FOOT | $9.08 | $10.75 | $8.75 | $10.75 | $10.75 | $12.00 | |
| 55 | 64200108 | SHOULDER RUM STRIP 8 | 27,505 | FOOT | $0.3300 | $0.3400 | $0.5000 | $0.8100 | $0.5000 | $0.5000 | |
| 56 | 66900200 | NON SPL WASTE DISPOSL | 890 | CU YD | $70.00 | $90.00 | $65.00 | $64.68 | $70.00 | $60.00 | |
| 57 | 66900530 | SOIL DISPOSAL ANALY | 7 | EACH | $1,375.00 | $1,350.00 | $1,500.00 | $1,200.00 | $1,200.00 | $1,300.00 | |
| 58 | 66901001 | REG SUB P-CONST PLAN | 1 | LSUM | $2,750.00 | $3,250.00 | $3,750.00 | $2,200.00 | $2,200.00 | $3,000.00 | |
| 59 | 66901002 | ON-SITE MON REG SUB | 15 | CAL DA | $990.00 | $750.00 | $1,250.00 | $825.00 | $825.00 | $1,200.00 | |
| 60 | 66901003 | REG SUB F CON REPORT | 1 | LSUM | $2,750.00 | $2,000.00 | $2,900.00 | $1,800.00 | $1,800.00 | $2,000.00 | |
| 61 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $2,000.00 | $3,300.00 | $500.00 | $1,600.00 | $2,500.00 | $3,000.00 | |
| 62 | 67100100 | MOBILIZATION | 1 | L SUM | $30,000.00 | $58,000.00 | $96,000.00 | $108,640.97 | $115,000.00 | $120,000.00 | |
| 63 | 70100310 | TRAF CONT-PROT 701421 | 1 | L SUM | $11,500.00 | $25,450.23 | $1.00 | $1.00 | $168,000.00 | $1.00 | |
| 64 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $0.0100 | $1.00 | $19,000.00 | $16,000.00 | $1.00 | $1.00 | |
| 65 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $0.0100 | $1.00 | $1.00 | $1.00 | $1.00 | $32,500.00 | |
| 66 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $0.0100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 67 | 70300100 | SHORT TERM PAVT MKING | 2,622 | FOOT | $1.00 | $1.00 | $1.00 | $1.67 | $1.50 | $1.00 | |
| 68 | 70300150 | SHRT TRM PAVT MK REM | 874 | SQ FT | $1.50 | $2.00 | $5.50 | $3.94 | $2.00 | $3.50 | |
| 69 | 70300520 | PAVT MARK TAPE T3 4 | 2,622 | FOOT | $2.00 | $0.9000 | $2.00 | $1.00 | $1.00 | $1.00 | |
| 70 | 72501000 | TERMINAL MARKER - DA | 10 | EACH | $55.00 | $52.00 | $52.75 | $51.11 | $51.00 | $60.00 | |
| 71 | 78000200 | THPL PVT MK LINE 4 | 28,842 | FOOT | $0.6800 | $0.5500 | $0.6000 | $0.5800 | $0.6600 | $0.7000 | |
| 72 | 78100100 | RAISED REFL PAVT MKR | 500 | EACH | $30.80 | $24.00 | $27.75 | $26.25 | $31.79 | $32.00 | |
| 73 | 78200005 | GRDRAIL REF TYPE A | 67 | EACH | $11.00 | $10.25 | $11.00 | $10.22 | $10.00 | $12.00 | |
| 74 | 78300200 | RAISED REF PVT MK REM | 500 | EACH | $10.00 | $10.00 | $15.00 | $10.76 | $0.0100 | $50.00 | |
| 75 | 88600600 | DET LOOP REPL | 325 | FOOT | $19.25 | $17.50 | $19.00 | $17.50 | $25.00 | $20.00 |